Cheltenham Borough Council
Cabinet, Tuesday 16 July 2013 at 6.00pm

Leisure facilities strategy and Prince of Wales Stadium Feasibility Options

Agreed Executive 4 papers

Cabinet agreed this item on Tuesday 16 July 2013. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED that the commencement of detailed discussions with tenants and key users of the Prince of Wales Stadium to negotiate future usage arrangements be agreed the strategic principle that facility development and future investment for sport and leisure within the town be focussed on Leisure@ and the Prince of Wales Stadium be supported, as recommended in the Leisure Strategy and associated feasibility studies the detailed business cases for future investment to deliver specific capital developments at a later date, following the successful establishment of a new charitable trust for leisure and culture be considered.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Cabinet

Cheltenham Borough Council Cabinet 16 July 2013 Leisure Facilities Strategy and Prince of Wales Feasibility Study

Accountable member Councillor Rowena Hay, Cabinet Member for Sport & Culture

Accountable officer Sonia Phillips, Director of Wellbeing & Culture

Ward(s) affected All

Key Decision Yes

Executive summary The Leisure & Culture review is one of a number of strategic commissioning projects that aim to find a viable and sustainable future for L&C services. The review has sought to ensure that we maximise the community benefits that our assets, facilities and services deliver, whilst reducing the level of financial subsidy. In respect of sport and leisure, Leisure@ Cheltenham and the adjacent Prince of Wales stadium represent the council’s key hub facility serving the town.

As part of the commissioning review, a Leisure Facilities Strategy has been written and feasibility studies have been undertaken to consider the current operation of the site and a range of future options including changes to the use of existing spaces and the possible addition of new facilities on the site that compliment the current offer. The study into the Prince of Wales Stadium, has also considered the current leasing arrangements on the site within the context of maximising community benefit and financial return from the site.

Following the decision to proceed with the proposed creation of a charitable trust for leisure and culture, the recommendation to Cabinet is that the principles of future investment in sport and leisure to further strengthening the appeal of the current facility mix be agreed.

Recommendations Cabinet is requested to RESOLVE:

1. To agree to the commencement of detailed discussions with tenants and key users of the Prince of Wales Stadium to negotiate future usage arrangements

2. To support the strategic principle that facility development and future investment for sport and leisure within the town be focussed on Leisure@ and the Prince of Wales Stadium, as recommended in the Leisure Strategy and associated feasibility studies

3. To consider detailed business cases for future investment to deliver specific capital developments at a later date, following the successful establishment of a new charitable trust for

Leisure Facility Strategy

Cabinet report version 8 Page 1 of 11 Last updated 05 July 2013 leisure and culture.

Financial implications There are no financial implications arising at this stage.

Contact officer: Sarah Didcote, [email protected],

01242 264125

Legal implications The council intends to establish a new Culture and Leisure Trust to take over the running of the Stadium as from April 2014. As part of the arrangement the council should be clear of its aims and requirements for, in this case, leisure on this land. These can then be written in to the contract documentation and will help define the vision of the council.

The situation regarding the legal liabilities for the occupation of the various facilities should be resolved to enable the most effective use of the facilities at the Prince of Wales Stadium, so that the trust can operate on a clear basis, with minimal uncertainty. This will mean negotiations with the key users of the facilities to clarify their usage, its legal basis and how to move forward.

There are uncertainties regarding the existence of the lease under which the Rugby Club uses the ground and this needs to be resolved so that there is some certainty on this point. However the reports have used the shorthand term of Lease to simplify the explanation of what the situation is. Contact officer: Gary Spencer, [email protected],

01684 272690

HR implications The implications of TUPE transferring the Wellbeing & Culture Division into (including learning and the proposed trust model are already being explored in detail and there are organisational no further HR implications as a result of this report. development) Contact officer: Donna Sheffield, [email protected],

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cheltenham Leisure Facilities Strategy Appendix 2Appendix 917 KB Download
PDF
Cheltenham New Facility Opportunities Report Final Appendix 3Appendix 503 KB Download
PDF
Leisure facilities strategy and Prince of Wales Stadium Feasibility OptionsReport 108 KB DownloadRead as text
PDF
Prince of Wales Feasibility Study Appendix 4Appendix 734 KB Download

At this meeting

Whole meeting

Who was there

8 of 10 attended
SJ
Councillor Steve Jordan Leader of the CouncilCommittee Member, present
JR
Councillor John Rawson Cabinet Member FinanceCommittee Member, present
RH
Councillor Rowena Hay Cabinet Member Sport and CultureCommittee Member, present
PJ
Councillor Peter Jeffries Cabinet Member Housing and SafetyCommittee Member, present
AM
Councillor Andrew McKinlay Cabinet Member Built EnvironmentCommittee Member, present
JW
Councillor Jon Walklett Cabinet Member Corporate ServicesCommittee Member, present
RW
Councillor Roger Whyborn Cabinet Member SustainabilityCommittee Member, present
PP
Pat PratleyOfficer, present
MS
Mark SheldonOfficer, absent
GL
Grahame LewisOfficer, absent

More from Cheltenham Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... Noted Open
15 Sep 2026 Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... Approved Open
15 Sep 2026 Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... Decided Open
15 Sep 2026 Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... Agreed Open
15 Sep 2026 Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies