Permit Letters of Rep: 0 Update Report: None Councillors Godwin and Fisher were absence from the Chamber for the debate and vote on this item MJC introduced the application, which is at Committee because the Parish Council has objected, believing the proposal to be inappropriate in the AONB. The applicant had previously installed unauthorised solar panels on the barn, but these have now been removed and this application is to replace them. Public Speaking: None. Member debate: HM: as a member of the Cotswold Conservation Board, said their management plan is keen to promote renewable energy so as not to despoil the countryside, but is also concerned about the look of the countryside too. As it has raised no objection here, it seems reasonable that the Committee cannot object either. Vote on officer recommendation to permit 11 in support – unanimous PERMIT
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
APPLICATION NO: 14/00122/FUL OFFICER: [name removed] REGISTERED: 3rd February 2014 DATE OF EXPIRY: 31st March 2014
WARD: Battledown PARISH: Charlton Kings
APPLICANT: [name removed]: SF Planning Limited
LOCATION: Ham Court, Ham Road, Charlton Kings
PROPOSAL: Erection of freestanding solar panels
RECOMMENDATION: Permit
This site map is for reference purposes only. OS Crown Copyright. All rights reserved Cheltenham Borough Council 100024384 2007 1. DESCRIPTION OF SITE AND PROPOSAL 1.1 The application site relates to land to the south of Ham Court, which is a grade II listed property within the ward of Battledown.
1.2The applicant seeks planning permission for the erection of freestanding solar panels within the grounds of the property and to the south of the main house.
1.3The application is before Planning Committee as the parish council have objected to the proposal due to insufficient information and because the proposal is not suitable for the Area of Outstanding Natural Beauty.
2. CONSTRAINTS AND RELEVANT PLANNING HISTORY
Constraints: Area of Outstanding Natural Beauty Residents Associations
Relevant Planning History: 02/01781/FUL 14th February 2003 PER Demolition of outbuilding and erection of two storey extension
02/01782/LBC 14th February 2003 GRANT Demolition of outbuilding and erection of two storey extension
3. POLICIES AND GUIDANCE Adopted Local Plan Policies CP 4 Safe and sustainable living CP 7 Design CO 2 Development within or affecting the AONB
National Guidance National Planning Policy Framework
4. CONSULTATIONS Parish Council 25th February 2014
OBJECTION - insufficient information - not suitable for AONB
Cotswold Conservation Board 12th February 2014
Subject to no objections from the Council's Built Environment Officer or Ecological adviser, the Cotswolds Conservation Board supports this proposal which is in accordance with the Cotswolds AONB Management Plan 2013-18 and the Board's Position Statement on renewable energy generation in the Cotswolds AONB. Heritage and Conservation 25th February 2014
Further to: pre-application site visit and application information
Analysis of Site This site has wider views to it from across an adjacent field. From this long distance view it is possible to see the principal listed house (ie Ham Court) and the adjacent listed barn and the proposed location of the solar panels.
Comments i. This application has come about due to the fixing of solar panels to the roof of the near-by listed barn, without listed building consent; resulting in the issuing of an enforcement notice and a subsequent dismissed appeal.
ii. I have visited the site after the result of the dismissed appeal, with a view to consider alternative locations for the solar panels.
iii. The proposed location is acceptable provided it is screened to the north and the west by a new hedge. The proposal suggests a mixed hedge which has the advantages of looking like a rural hedge on the filed boundary, but the disadvantage of being deciduous thus allowing views of the panels during the period when the hedge has lost its leaves.
iv. Since the landscaped screen is such a key element in the acceptability of the proposals I suggest that the planting of the hedges, the type of hedge and the retention of the hedge in perpetuity is conditioned.
CONCLUSION: approve subject to conditions
Conditions:
LAN02B Landscaping scheme (short version) Prior to the commencement of development, a detailed scheme for the proposed hedge planting shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall specify species, density, planting size and layout. The scheme approved shall be carried out in the first planting season following the occupation of the building or completion of the development, whichever is the sooner. Reason: To ensure that the development is completed in a manner that is sympathetic to the site and its surroundings in accordance with Local Plan Policies CP1 and CP7 relating to sustainable development and design.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.