14/01270/CONDIT Unit 3, Maida Vale Business Centre, Maida Vale Road

Refused Planning 6 papers

Planning Committee refused this item on Thursday 21 August 2014. Below is the council's own wording, with the papers it was decided on.

Item33

Resolved

Refuse Letters of Rep: 10 Update Report: Officer comments; additional representation MP introduced this application to vary two conditions on this business unit which has been used as a commercial laundry for a number of years. The applicant is seeking to increase the hours of operation. The application is at Planning Committee at the request of Councillor Sudbury, who is concerned about loss of amenity. The recommendation is to permit, subject to revised conditions. Public Speaking: [name removed], neighbour, in objection With every fibre of her body, urges Members to refuse this application. This is a mixed residential and business area. Nothing has changed since the site was developed in 2000 in terms of residents requiring less amenity, or since 2002 when this unit’s working hours were increased by 11%. If anything, amenity should be more valued now than it was 14 years ago, with the pace of life as it is. Neighbours simply want to keep things as they are – no increase in noise due to increased hours; peace and quiet on summers’ evenings, Saturday afternoons, Sundays and Bank Holidays. Is not a complainer without good reason. Members on Planning View did not experience the full noise from the unit on their site visit, as it would not be in the unit’s best interest to show that. From time to time, all the unit occupiers are on their premises outside their contractual hours - this is challenged by residents but maybe overlooked if there is no noise – but with CLC, it is not about giving an inch and taking a mile – they just take, take, take. They worked on Easter weekend and the 26 th May Bank Holiday, as well as regular Easters, Christmases and New Years – even the Queen’s Jubilee. Has video evidence to prove it which was offered to CBC but not accepted. Other people look forward to Bank Holidays, but she braces herself, knowing that CLC will steal her peace and relaxation – it is very stressful and frustrating. Has exhausted every avenue to reason with CLC and get the council to enforce the current terms. Nothing happens to resolve this, only an application for more working hours. It is exhausting to have to repeatedly confront this Groundhog Day situation. There are eight objections, five of which refer to lack of enforcement; has submitted complaints about this recently. The 2002 conditions have not been respected by CLC or enforced by the council when residents have raised concerns over the last 12 years. If the scenario is that the two parties do not ... view the full minutes text for item 33.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Planning Committee

APPLICATION NO: 14/01270/CONDIT OFFICER: [name removed] REGISTERED: 15th July 2014 DATE OF EXPIRY: 9th September 2014

WARD: Leckhampton PARISH: None

APPLICANT: [name removed]: None

LOCATION: Unit 3, Maida Vale Business Centre, Maida Vale Road

PROPOSAL: Variation of condition 2 (hours of business) and condition 3 (hours of loading/unloading) on planning permission ref. 02/00813/CONDIT granted 25th July 2002 to allow the premises to be used between the hours of 7.00am and 7.00pm Monday to Friday, and 7.00am and 3.00pm on Saturday, Sunday and Bank Holidays

RECOMMENDATION: Recommendation at Committee

This site map is for reference purposes only. OS Crown Copyright. All rights reserved Cheltenham Borough Council 100024384 2007 1. DESCRIPTION OF SITE AND PROPOSAL 1.1 This application relates to Unit 3 within the Maida Vale Business Park at Maida Vale Road in Leckhampton; Unit 3 has been occupied by Cotswold Linen Care, a commercial laundry business, for a number of years.

1.2Planning permission ref. CB19293/07 was granted in 1999 for the erection of ten industrial starter units; planning permission having previously been granted for 9 units in 1991 and subsequently renewed in 1996.

1.3Condition 5 of the implemented planning permission relates to hours of operation and reads:

The premises shall be used for the purpose specified only between the hours of 8.00am and 6.00pm on Mondays to Fridays inclusive 8.00am to 1.00pm on Saturdays and at no time on Sundays or Bank Holidays. Reason: To safeguard the amenities of the occupiers of the adjoining residential properties.

1.4Condition 6 of the planning permission relates to loading and unloading and reads:

No loading or unloading shall take place between the hours of 6.00pm and 8.00am Mondays to Fridays, between noon on Saturday and 8.00am Mondays, nor at any time on Bank Holidays. Reason: To safeguard the amenities of the occupiers of the adjoining residential properties.

1.5The planning history sets out that such relatively tight controls were imposed on the original planning permission because of the nature of the development and its proximity to adjoining residential development, particularly where the end user of the industrial units was not known.

1.6Since the original grant of planning permission, a number of applications have been made on various units within the business centre to extend their hours of operation.

1.7With specific regard to Unit 3, Cotswold Linen Care first applied to extend their hours of operation and loading and unloading in March 2002. This application sought permission to use the premises from 7.00am to 8.00pm Monday to Friday, 7.00am to 3.00pm on Saturdays and 9.00am to 2.00pm on Bank Holidays. The application was refused by the Planning Committee in May 2002 as it was considered at that time that such “a relaxation of controls imposed in respect of hours of operations and deliveries to and from the premises would…give rise to an intensification of activity within this industrial/business centre which would have a harmful effect on the amenities at present enjoyed by the occupiers of adjoining and nearby residential premises”.

1.8Subsequently a revised application, ref. 02/00813/CONDIT, was submitted in May 2002 – this application was approved by the Planning committee in July 2002 subject to the following conditions:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
14/01270/CONDIT Unit 3, Maida Vale Business Centre, Maida Vale RoadReport 63 KB DownloadRead as text
PDF
Unit 3 Maida Vale Business Centre: report update 21st AugustReport 17 KB Download
PDF
Unit 3, Maida Vale Busienss Centre: report update 19th AugustReport 23 KB Download
PDF
Unit 3, Maida Vale Business Centre: additional representation 21st AugustReport 309 KB Withheld: personal details
PDF
Unit 3, Maida Vale Business Centre: additional representations 19th AugustReport 222 KB Withheld: personal details
PDF
Unit 3, Maida Vale Business Centre: representationsReport 33 KB Withheld: personal details

At this meeting

Whole meeting

Who was there

19 of 19 attended
GB
Councillor Garth BarnesChair, present
JF
Councillor Jacky FletcherVice-Chair, present
PB
Councillor Paul BakerCommittee Member, present
AC
Councillor Andrew ChardCommittee Member, present
MB
Councillor Matt BabbageCommittee Member, present
DS
Councillor Diggory SeacomeCommittee Member, apologies, sent representative
FC
Councillor Flo ClucasCommittee Member, present
BF
Councillor Bernard FisherCommittee Member, present
CH
Councillor Colin HayCommittee Member, apologies, sent representative
HM
Councillor Helena McCloskeyCommittee Member, present
AM
Councillor Andrew McKinlayCommittee Member, present
KS
Councillor Klara SudburyCommittee Member, present

All 19 on the meeting page

More from Cheltenham Planning Committee

All decisions
MeetingDecisionOutcome
21 Aug 2025 Declarations of InterestIt was agreed that this does not constitute a prejudicial interest, and he was therefore not required to leave the Ch... Agreed Open
17 Jun 2021 Any other items the Chairman determines urgent and requires a decisionIt was agreed that it was not relevant, the Chair disagreed as he thought that it was good to see that it was a mix o... Agreed Open
17 Dec 2020 20/01371/FUL Balcarras School, East End Road, Charlton Kings, Cheltenham GL53 8QFAgreed that the proposal was positive and had to be supported to cover the capacity required. It was the best that co... Agreed Open
17 Sep 2020 Minutes of last meetingRESOLVED THAT The minutes of the meeting held on 20 th August 2020 were approved and signed as a correct record. Approved Open
18 Jun 2020 ApologiesRESOLVED THAT Councillor McCloskey be appointed as Vice-Chair on a temporary basis. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies