Resolved
RESOLVED that the minutes of the meeting held on the 11 December 2014 be agreed and signed as an accurate record.
Audit, Compliance and Governance Committee agreed this item on Wednesday 14 January 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the minutes of the meeting held on the 11 December 2014 be agreed and signed as an accurate record.
Audit Committee
Thursday, 11th December, 2014 6.00 - 7.50 pm Attendees Councillors: Colin Hay (Chair), Chris Nelson (Vice-Chair), Matt Babbage, Flo Clucas, Dan Murch, David Prince and Pat Thornton Also in attendance: Councillor Rowena Hay, Rob Milford (Head of Audit Cotswolds), Andrew North (Chief Executive), Bryan Parsons (Governance, Risk and Compliance Officer), Councillor John Rawson, Mark Sheldon (Director Resources) and Councillor Jon Walklett
Minutes
1. APOLOGIES No apologies had been received.
2. DECLARATIONS OF INTEREST No interests were declared.
3. MINUTES OF THE LAST MEETING The minutes of the last meeting had been circulated with the agenda.
Upon a vote it was unanimously
RESOLVED that the minutes of the meeting held on the 24 September 2014 be agreed and signed as an accurate record.
4. PUBLIC QUESTIONS 2 public questions were received.
Questions from Anne Brookes to the chair of the Audit Committee, Councillor Colin Hay 1. It is the responsibility of the Borough Council, officers and elected members, to ensure that public money is safeguarded and properly accounted for, and the report to this committee regarding the overspend shows a complete failure of control throughout the project, and that even when completed, the actual details of the overspend remain unknown. If managed properly it would have been possible, at any time, to know why, where and how much the overspend was likely to be. The committee, if properly undertaking its duty and responsibility, should question why it is being asked to spend more public money on further audits to identify what was spent. A public interest report following the legal case against the former Chief Executive made recommendations concerning managing risk, yet these have been ignored. We are again in the situation where evaluations are only made after the event, and it seems likely that the overspend on the Art Gallery will be close to or
-1- Draft minutes to be approved at the next meeting on Wednesday, 14 January 2015. possible top £½ million of public money.
What will the committee do to ensure that there is a proper process in place to minimise, at the very least, the risk to the council and public funds, and stop just accepting these hindsight reports promising to identify ways to prevent this happening in the future?
Response from Councillor Colin Hay, Chairman Audit committee The statement made by [name removed] relating to responsibility is correct and the Council has always recognised this by putting in place a series of financial rules and internal controls. In addition to this the council provided a project team, led by a qualified and experienced Project Manager who was supported by an external Construction Project Manager. The Project team was governed by the Council’s financial rules, controls and its Prince 2 based approach to project management, all of which are designed to ensure that public money is safeguarded and properly accounted for.
The Executive Sponsor for the project reported to Council in February 2014 that the outturn cost of the extension to the Art Gallery and Museum had exceeded the budget by £360,000. As a result of this the Council agreed to commission Grant Thornton to carry out a review and to report back to Audit Committee on its findings.
Grant Thornton’s report was considered by the Executive Board and was tabled for consideration at the Audit Committee meeting on the 11th Dec 2014. However since then additional expenditure has been identified and the report has been put on hold until after a discussion by the Audit Committee this evening and to account for any additional work by our internal and external auditors.
The Grant Thornton draft report contained specific recommendations and the management response has been that they will all be accepted and acted upon.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the last meetingReports_pack | 75 KB | DownloadRead as text |
Follow Audit, Compliance and Governance Committee at Cheltenham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | Local government act 1972 - exempt informationRESOLVED THAT: : - in accordance with Section 100A(4) Local Government Act 1972 the public be excluded from the meeti... | Decided | Open |
| 22 Apr 2026 | Internal Audit Plan 2026-27 and Internal Audit Charter and Mandate 2026-27RESOLVED THAT: - the proposed 2026-27 Internal Audit Plan and the Internal Audit Charter and Mandate 2026-27are appro... | Approved | Open |
| 22 Apr 2026 | Local government act 1972 - exempt informationRESOLVED THAT: - in accordance with Section 100A(4) Local Government Act 1972 the public be excluded from the meeting... | Decided | Open |
| 28 Jan 2026 | Local government act 1972 - exempt informationRESOLVED THAT: That in accordance with Section 100A(4) Local Government Act 1972, the public be excluded from the mee... | Decided | Open |
| 22 Oct 2025 | Local government act 1972 - exempt informationRESOLVED THAT: - in accordance with Section 100A(4) Local Government Act 1972 the public be excluded from the meeting... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.