RESOLVED THAT 1. the Community Infrastructure Levy - Preliminary Draft Charging Schedule be endorsed for public consultation. 2. the Head of Planning i n consultation with the Leader of the Council be authorised to prepare the final consultation documents as required, based on the information in Appendix 2. 3. the Head of Planning be authorised to agree the date of consultation on the Preliminary Draft Charging Schedule with Gloucester and Tewkesbury Councils. 4. a report is prepared following the consultation on the Preliminary Draft Charging Schedule and reported to a subsequent meeting of Cabinet. 5. Each Joint Core Strategy partner agrees to contribute £25,000 per authority to underwrite the set up costs of developing a CIL.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 14 April 2015 Community Infrastructure Levy – Draft Preliminary Charging Schedule
Accountable member Councillor Jordan - Leader
Accountable officer Tracey Crews – Head of Planning
Ward(s) affected All
Key/Significant Yes Decision
Executive summary Further to agreement by Cabinet on 18 June 2013 to progress preparation of a Community Infrastructure Levy (CIL) for Cheltenham, The Borough Council in collaboration with Gloucester and Tewkesbury councils appointed Peter Brett Associates to consider whether a CIL should be taken forward. The reports appended to this covering report explain the assessment undertaken and details the potential CIL rates. This has been developed into a Preliminary Draft Charging Schedule for consultation.
The preparation of a CIL Charging Schedule will enable the Council to ensure that new development contributes proportionately to infrastructure provision to support development in the area.
The development of a CIL supports delivery of the Gloucester, Cheltenham and Tewkesbury Joint Core Strategy and the Cheltenham Plan. Consultation on a Preliminary Draft Charging Schedule allows the Council to collect the views of the community and development professionals operating in the borough, and allows further consideration of bringing in a CIL and outlines possible charging rates.
Recommendations 1. To endorse the Community Infrastructure Levy - Preliminary Draft Charging Schedule for public consultation. 2. Authorise the Head of Planning in consultation with the Leader of the Council to prepare the final consultation documents as required, based on the information in Appendix 2. 3. Authorise the Head of Planning to agree the date of consultation on the Preliminary Draft Charging Schedule with Gloucester and Tewkesbury Councils. 4. That a report is prepared following the consultation on the Preliminary Draft Charging Schedule and reported to a subsequent meeting of Cabinet. 5. Each Joint Core Strategy partner agrees to contribute £25,000 per authority to underwrite the set up costs of developing a CIL.
$wobj11mt.docx Page 1 of 14 Last updated 01 April 2015 Financial implications The Community Infrastructure Levy Cabinet Report dated 18th June 2013 flagged that the statutory process involving formal consultation and public examination would have a financial impact in terms of both set up and on-going costs. Budgetary provision at this stage was not specifically set aside by the partner councils.
The costs incurred in 2014/15 are £82,000 to date. A proportion of these set-up costs will be covered by the Homes and Communities Agency fund LSIF (Large Site Infrastructure Fund), and the Joint Core Strategy Reserve will be used to cover the balance of costs incurred in 2014/15.
This will leave a depleted JCS Reserve as at 31st March 2015.
Further to this, there are likely to be additional costs of c.£75,000 in 2015/16 whilst the process moves through the consultation and examination phases. To cover these costs a recommendation is made to seek approval for a £25,000 contribution per partner council.
The Council will need to fund this from either the 2014/15 outturn position, provided an underspend is achieved, or at worst the expenditure will have to be met from general balances.
Should CIL be adopted by the Council, as well as set-up costs, there will be an ongoing cost to administer the scheme. This will need to be fully understood and costed during the next stage of the project, giving consideration to the Regulations, which provide for Charging Authorities to use up to 5% of the annual CIL income to administer the system, as well as the opportunity to recover some of the set-up costs incurred up to 2 years prior to adoption.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.