CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cheltenham Borough Council
Planning Committee, Thursday 16 July 2015 at 6.00pm

14/02938/FUL Pittville Campus

Agreed Planning 6 papers

Planning Committee agreed this item on Thursday 16 July 2015. Below is the council's own wording, with the papers it was decided on.

Item153

Resolved

Permit, subject to S106 agreements Letters of Rep: 178 Update Report: None Officer introduction: LW introduced the application for a new student village, as above. It was deferred in January to allow the University an opportunity to address the suggested refusal reasons, relating to architectural design and amenity, in particular off-site noise and disturbance during the evening and night-time, as well as the size of the development, number of students, and ability to manage the site effectively. In addition, the legal agreement regarding highway works and travel plan was not complete. Since January, the University and everyone else has worked hard to address these concerns : new architects were appointed and the University has engaged more directly with local residents through a Residents Liaison Group which has met six times. The meetings have been constructive and focused on detail of the Operational Management Plan, which is now more consolidated and detailed regarding off-site strategies than previously, and no longer based on assumptions and ideas, with no guarantee of delivery. Fundamental to the officer recommendation to permit is the new S106 agreement which would ensure long-term provision of a late-night shuttle bus, volunteer patrol scheme and continuation of a community liaison group. This and the highways legal agreement are signed and ready for issue. It is disappointing that the University didn’t consider reduction in the student numbers proposed for this site, continuing to put forward the economic argument to meet current and increasing shortfall in student accommodation. This is a material consideration, but the appropriate management of the students is critical, whatever the number proposed. There are now defined and clear strategies to manage off-site student behaviour and reduce potential harm to neighbours’ amenity, secured long-term via the S106 agreement. There is still some criticism regarding design and appearance, but the revised scheme is an improvement, more refined and consistent in approach to materials and elevation treatment. There are no objections from consultees. The application is now sufficiently advanced for officers to understand and assess the merits of the proposal which, on balance, is considered acceptable. With the presumption in favour of development unless the adverse impacts would significantly outweigh the benefits, the recommendation is to permit subject to the two legal agreements relating to amenity and highway works. Finally, would add that the new drawings on Council’s website replace some of the original drawings which were shown at the wrong scale in relation to paper size. These drawings have ... view the full minutes text for item 153.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Planning Committee

APPLICATION NO: 14/01928/FUL OFFICER: [name removed] REGISTERED: 23rd October 2014 DATE OF EXPIRY: 22nd January 2015

WARD: Pittville PARISH: Prestbury

APPLICANT: Uliving And University Of Gloucestershire

AGENT: Plainview Planning Ltd

LOCATION: Pittville Campus, Albert Road, Cheltenham

PROPOSAL: Erection of a student village incorporating 577 new-build student bedrooms, the refurbishment of the existing media centre (which will include a reception/security desk, a gym, retail facilities, multi-faith area, refectory and bar, quiet study area, laundrette, ancillary office space), and the provision of a mixed use games area. In addition, the proposal involves the demolition of existing teaching facilities and the retention and refurbishment of 214 existing student rooms.

RECOMMENDATION: Permit subject to s106 Obligation

This site map is for reference purposes only. OS Crown Copyright. All rights reserved Cheltenham Borough Council 100024384 2007 1. DESCRIPTION OF SITE AND PROPOSAL 1.1 Members will recall that this application was deferred at the January 2015 Planning Committee meeting. The reason for deferral was to give the applicants the opportunity to address the issues and concerns highlighted by officers, Members and local residents during the course of determining the application. Whilst the principle of the redevelopment of the site to provide additional student accommodation was not in dispute, there were significant issues and a lack of information raised in relation to architectural design, size and scale of proposed development, student numbers and their management both on and off- site, parking, vehicular and pedestrian traffic, impact upon the amenities of local residents and wider Pittville area and the lack of robust strategies to ensure the effective long-term management of students.

1.2The above concerns were, in part, brought about by prematurity; the applicants requesting that the application be determined at the January Committee in order to secure appropriate funding for the project, which at that time, was subject to tight deadlines in terms of submitting funding bids. The majority of the above issues therefore remained unresolved in January and in effect, time had ‘run out’ in terms of the negotiation process.

1.3For ease of reference, the Minutes and Officer report presented to the January Committee are reproduced in full in the Appendices. The Officer report also provides the background and detail of the proposed development, including site description, context, planning policy considerations and relevant planning history. This report focuses on progress and revisions proposed within the last six months through the negotiations between all parties, including the local community.

1.4It is fair to say that, since January, everyone involved in this project has been working hard and consistently to identify and resolve the issues and concerns raised. The key actions and revisions that have taken place are, in summary, as follows:-

 The appointment of new architects, Feilden Clegg and Bradley Studios (FCB), with a brief to take fresh look at the architectural design and layout of the proposed development taking into account the views of CBC officers, the Architects Panel, Civic Society and local residents.

 Following pre-application discussions, submission of a revised scheme on 12th May 2015 accompanied by a set of supporting documents amended in response to the revised proposals (notably the Design and Access Statement, Planning Statement, Environmental Impact and Noise Assessment, Tree Survey, Utilities Statement, Transport Statement/Travel Plan). The revised Planning Statement and Operational Management Plan (OMP) seek to consolidate all previous Addendums in addition to responding to the revised architectural design.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
14/02938/FUL Pittville CampusReport 474 KB DownloadRead as text
PDF
January Planning Committee MinutesMinutes 222 KB Download
PDF
Pittville Campus: additional representations 10th JulyReport 22 KB Withheld: personal details
PDF
Pittville Campus: representations since 22nd JanuaryReport 1.2 MB Withheld: personal details
PDF
Pittville Campus 22nd January: officer report & updatesReport 333 KB Download
PDF
Pittville campus: report update 10th JulyReport 52 KB Download

At this meeting

Whole meeting

Who was there

19 of 19 attended
GB
Councillor Garth BarnesChair, present
JF
Councillor Jacky FletcherVice-Chair, present
PB
Councillor Paul BakerCommittee Member, present
AC
Councillor Andrew ChardCommittee Member, present
DS
Councillor Diggory SeacomeCommittee Member, present
FC
Councillor Flo ClucasCommittee Member, present
BF
Councillor Bernard FisherCommittee Member, present
CH
Councillor Colin HayCommittee Member, present
AL
Councillor Adam LillywhiteCommittee Member, present
HM
Councillor Helena McCloskeyCommittee Member, apologies, sent representative
AM
Councillor Andrew McKinlayCommittee Member, present
KS
Councillor Klara SudburyCommittee Member, present

All 19 on the meeting page

On this subject at Cheltenham

Search all
  1. 14/02938/FUL Pittville CampusThis decision
  2. 19/00388/FUL, Berkhampstead School, Pittville Circus Road, CheltenhamRefused
  3. 18/01947/FUL & LBC 61 Pittville LawnRefused
  4. 18/01216/FUL Pittville Recreation CentreDecided
  5. 17/02022/FUL & LBC The Cheltenham Townhouse, 12-14 Pittville LawnDecided
  6. 16/02105/FUL Cotswold Grange Hotel, Pittville Circus RoadDeferred

More from Cheltenham Planning Committee

All decisions
MeetingDecisionOutcome
21 Aug 2025 Declarations of InterestIt was agreed that this does not constitute a prejudicial interest, and he was therefore not required to leave the Ch... Agreed Open
17 Jun 2021 Any other items the Chairman determines urgent and requires a decisionIt was agreed that it was not relevant, the Chair disagreed as he thought that it was good to see that it was a mix o... Agreed Open
17 Dec 2020 20/01371/FUL Balcarras School, East End Road, Charlton Kings, Cheltenham GL53 8QFAgreed that the proposal was positive and had to be supported to cover the capacity required. It was the best that co... Agreed Open
17 Sep 2020 Minutes of last meetingRESOLVED THAT The minutes of the meeting held on 20 th August 2020 were approved and signed as a correct record. Approved Open
18 Jun 2020 ApologiesRESOLVED THAT Councillor McCloskey be appointed as Vice-Chair on a temporary basis. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies