Permit Letters of Rep: 0 Update Report: None MJC introduced the application as above, at Committee because CBC is the applicant, and with a recommendation to permit Public Speaking: None. Member debate: None. Vote on officer recommendation to permit 15 in support – unanimous PERMIT
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
PROPOSAL: Installation of replacement extraction ducting
RECOMMENDATION: Grant
This site map is for reference purposes only. OS Crown Copyright. All rights reserved Cheltenham Borough Council 100024384 2007 1. DESCRIPTION OF SITE AND PROPOSAL 1.1 The application site comprises a three storey building in a parade of units known as Lynworth Exchange and which have residential units above.
1.2The application for planning permission is for the installation of replacement extraction ducting at No. 20 Lynworth Exchange. At ground floor level, the unit’s current use is as a hot food takeaway.
1.3The application is before committee because the application is made by the Council.
2. CONSTRAINTS AND RELEVANT PLANNING HISTORY
Constraints: Neighbourhood Shopping Area
Relevant Planning History: 87/00465/PF 21st May 1987 PER Provision Of Security Shutters To Shop
81/00971/PF 26th February 1981 PER Change of use from retail fruit and vegetable to hot food take away (fish & chips)
3. POLICIES AND GUIDANCE Adopted Local Plan Policies CP 1 Sustainable development CP 3 Sustainable environment CP 4 Safe and sustainable living CP 7 Design
National Guidance National Planning Policy Framework
4. CONSULTATIONS
4.1Building Control No comment.
4.2Environmental Health 6th October 2015
4.3Recommend informative:
MANAGEMENT OF ASBESTOS (The Control of Asbestos Regulations 2006 Regulation 5) WHEN REFURBISHMENT OR OTHER WORK WHICH DISTURBS THE FABRIC OF THE BUILDING ARE PLANNED THEN IT WILL BE NECESSARY TO COMPLETE A REFURBISHMENT AND DEMOLITION SURVEY, IN AREAS WHERE THE MANAGEMENT SURVEY HAS NOT BEEN INTRUSIVE, BEFORE THE WORK IS CARRIED OUT. This type of survey is used to locate and describe, as far as reasonably practicable, all asbestos contain materials in the area where the refurbishment work will take place or in the whole building if demolition is planned. The survey will be fully intrusive and involve destructive inspection, as necessary, to gain access to all areas, including those that may be difficult to reach.
A refurbishment and demolition survey may also be required in other circumstances, e.g. when more intrusive maintenance and repair work will be carried out.
The full guidance document (HSG 264) is available on line at: http://www.hse.gov.uk/PUBNS/books/hsg264.htm
5. PUBLICITY AND REPRESENTATIONS
Number of letters sent 7 Total comments received 1 Number of objections 0 Number of supporting 0 General comment 1
5.1No neighbour representations have been received.
6. OFFICER COMMENTS 6.1 Determining Issues
6.2The determining issues in this case are the design of the development and residential amenity.
6.3Design
6.4Policy CP7 of the Local Plan states that development will only be permitted where it complements and respects neighbouring development and the character of the locality.
6.5The existing exterior ductwork measures 225 mm in circumference and is located to the rear of No. 20 Lynworth Exchange. The proposal is to replace this with ductwork measuring 500 mm in width and 225 mm in depth. The profile of the ductwork would not change from that of the existing and would project above the eaves height of the building by 1 metre. Galvanised steel would be utilised for the ductwork which would be the same as the existing. Overall, it is considered that the proposal would be acceptable in design terms and safeguard the character of the area
6.6Impact on neighbouring properties
6.7Policy CP 3 of the Local Plan states that development will only be permitted where it would “not give rise to harmful levels of pollution to land, air or water.” Further, Policy CP4 requires development to not cause unacceptable harm to the amenity of adjoining land users and to locality.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.