15/01162/FUL Pittville School, Albert Road

Agreed Planning 7 papers

Planning Committee agreed this item on Thursday 18 February 2016. Below is the council's own wording, with the papers it was decided on.

Item265

Resolved

Permit Letters of Rep: 15 Update Report: Additional representation LW introduced both application at Pittville School, the first as described above, and the second an outline for 58 dwellings, with access only to be agreed and all other issues relating to design, appearance, layout and landscaping to be considered at reserved matters stage. Access to the dwellings would be via the new estate roads through adjoining Starvehall Farm leading onto New Barn Lane, and also include cycle and pedestrian links to Albert Road and Cakebridge Road. These are stand-alone applications, but were submitted alongside each other and are entirely interrelated, with the residential scheme presented as an enabling project to cover the construction costs and delivery of the new sports facilities. This provides justification for the loss of the playing field which the Council would otherwise not support. The applications were deferred from the January meeting to allow time to reach agreement on the triggers for phased release and occupation of the housing scheme, to ensure the construction of the sports centre is started before commencement of the housing development, and that the sports facilities are complete and fit for purpose prior to completion of the housing scheme. The construction of the two sites should run roughly in parallel and the legal agreement delivers this. It has also been confirmed that construction costs of the sports hall will be covered by the value of the residential scheme which will also provide 40% affordable housing. Officers now have confidence for the proposed delivery mechanisms and the recommendation is therefore to permit both applications subject to conditions and the applicant entering into bilateral legal agreements and a final draft of the S106 agreement now in place and agreed. A holistic approach has been taken in assessing the two schemes, but two debates and two votes are needed. GB: the sports hall application will be considered first. The County highways officer is present, and also a representative of the Local Lead Flood Authority – Matthew Panou –to answer questions relating to drainage and flood risk. Public Speaking: [name removed], local resident, in objection His and his neighbours’ homes are vulnerable to flooding from Wyman’s Brook between Prestbury Road and Albert Road, which flooded in 2007 and is officially a high flood risk area in Environment Agency records. The Albert Road culvert is the smallest of local culverts and therefore a bad pinch point, causing the brook to back up and flood, and to make matters worse, water is delivered to this section from local run-off and from tributaries bringing water from further afield. With four new building developments, yet more water could be delivered into this already over-loaded section at times; residents need solid assurance that the sustainable drainage systems will work in practice, and expert ... view the full minutes text for item 265.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Planning Committee

Background

1.2Members will be aware that the two applications for Pittville School were deferred just prior to January’s Committee meeting. The reason for deferral was to allow more time for officers to complete negotiations with the applicant and reach agreement on the level of affordable housing provision; the final report of the District Valuation Service had also not been received at this stage. Discussions were similarly incomplete in respect of the Heads of Terms for the s106 Legal Agreement, specifically, the triggers for commencement and completion of elements of both the sports centre and residential schemes.

1.3Fundamentally, the scenario officers are seeking to avoid is a completed housing scheme and the sports facilities not finished or not even started. The wording and provisions of the s106, in this regard, would need to be clear, tight and robust and ensure that the two developments are constructed in parallel.

1.4Members are reminded that the residential scheme is put forward as an enabling project which would fund the delivery of the new sports facilities for Pittville School. This provides justification for the loss of the school playing field; the Council would otherwise not be in a position to support the proposed residential development.

The previous Officer report attached to the schedule for January’s Committee meeting is still relevant and outlines, in full, the policy background, design, amenity, drainage, traffic and highway issues associated with both applications. The Officer report (attached as an appendix) should be read in conjunction with this update.

1.5Environmental Health – Amenity Issues

1.6Prior to January’s Committee meeting, officers sought clarification from the Environmental Health team (EHO) with regards the noise related conditions suggested for the artificial hockey pitch and tennis courts. Although revised acoustic fencing details had been submitted by the applicant, in the absence of full relevant noise data accompanying the sports centre application, officers needed to be assured that the detail, attenuation measures and surveys required to be submitted and approved by the LPA post decision would result in an acceptable level of noise emission from the site and that this matter could be adequately dealt with via condition.

1.7The EHO considers that it is very unlikely a noise consultant would advise that a particular scheme was totally unworkable and could not be achieved through various noise reduction measures. Therefore, there should not be a situation where the proposals would become unacceptable, having, if necessary, applied various constraints such as additional screening.

1.8The Environmental Health Officer’s revised consultee comments are as follows. Note that, the comments and suggested conditions relating to lighting and hours of operation have not been amended:-

The number, size, location, distance from properties, etc. of the hockey pitch and tennis courts are generally acceptable.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
15/01162/FUL Pittville School, Albert RoadReport 290 KB DownloadRead as text
PDF
Appendix: Lead Flood Authority letterAppendix 50 KB Download
PDF
Pittville School FUL & OUT: January officer reportReport 869 KB Download
PDF
Pittville School FUL & OUT: January report updateReport 12 KB Download
PDF
Pittville School FUL & OUT: additional representation 18th FebruaryReport 86 KB Withheld: personal details
PDF
Pittville School FUL: online representationsReport 72 KB Withheld: personal details
PDF
Pittville School FUL: representation submitted by postReport 27 KB Withheld: personal details

At this meeting

Whole meeting

Who was there

17 of 19 attended
GB
Councillor Garth BarnesChair, present
JF
Councillor Jacky FletcherVice-Chair, present
PB
Councillor Paul BakerCommittee Member, present
AC
Councillor Andrew ChardCommittee Member, present
DS
Councillor Diggory SeacomeCommittee Member, present
BF
Councillor Bernard FisherCommittee Member, present
CH
Councillor Colin HayCommittee Member, present
AL
Councillor Adam LillywhiteCommittee Member, present
HM
Councillor Helena McCloskeyCommittee Member, present
AM
Councillor Andrew McKinlayCommittee Member, present
KS
Councillor Klara SudburyCommittee Member, present
PT
Councillor Pat ThorntonCommittee Member, present

All 19 on the meeting page

On this subject at Cheltenham

Search all
  1. 15/01162/FUL Pittville School, Albert RoadThis decision
  2. 19/00388/FUL, Berkhampstead School, Pittville Circus Road, CheltenhamRefused
  3. 18/01947/FUL & LBC 61 Pittville LawnRefused
  4. 18/01216/FUL Pittville Recreation CentreDecided
  5. 17/02022/FUL & LBC The Cheltenham Townhouse, 12-14 Pittville LawnDecided
  6. 16/02105/FUL Cotswold Grange Hotel, Pittville Circus RoadDeferred

More from Cheltenham Planning Committee

All decisions
MeetingDecisionOutcome
21 Aug 2025 Declarations of InterestIt was agreed that this does not constitute a prejudicial interest, and he was therefore not required to leave the Ch... Agreed Open
17 Jun 2021 Any other items the Chairman determines urgent and requires a decisionIt was agreed that it was not relevant, the Chair disagreed as he thought that it was good to see that it was a mix o... Agreed Open
17 Dec 2020 20/01371/FUL Balcarras School, East End Road, Charlton Kings, Cheltenham GL53 8QFAgreed that the proposal was positive and had to be supported to cover the capacity required. It was the best that co... Agreed Open
17 Sep 2020 Minutes of last meetingRESOLVED THAT The minutes of the meeting held on 20 th August 2020 were approved and signed as a correct record. Approved Open
18 Jun 2020 ApologiesRESOLVED THAT Councillor McCloskey be appointed as Vice-Chair on a temporary basis. Decided Open