RESOLVED THAT the virement of funds from Section 106 contributions (£62,000) and Parks & Gardens operational revenue budgets (£37,500) into the Pittville Play Area budget be approved and the variation to the contract with our supplier EIBE be approved.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet Meeting – 8th March 2016 Report of Cabinet member for Clean and Green Environment Virement of Funds to Pittville Park Play Area Project
Accountable member Councillor Chris Coleman, Cabinet member for Clean and Green Environment
Accountable officer Tracey Crews, Director of Planning
Ward(s) affected Pittville Ward
Key/Significant No Decision
Executive summary This report has come to Cabinet to ask for approval of a virement of £99,500 from the council’s Section 106 contributions and green space operational budget to the Pittville Park Play Area project budget. This virement is required because the external funds originally anticipated have not been fully achieved. It is therefore proposed that the council use up to £99,500 of existing approved budgets to ensure this important project is delivered by Summer 2016.
It was agreed to include the refurbishment of the aviaries as part of the project, this was approved as a delegated Cabinet Member Decision on 14 September 2015 increasing the project value to £535,500. The value and scope of the contract needs to be varied to include these works.
This project has generated unprecedented levels of positive public opinion and interest and continues to do so as the scheme evolves.
Recommendation To approve the virement of funds from Section 106 contributions (£62,000) and Parks & Gardens operational revenue budgets (£37,500) into the Pittville Play Area budget and to approve the variation to the contract with our supplier EIBE.
Financial implications The budgets proposed for virement have not been spent during 2015/16 and are available to recycle into the Pittville Park Project.
Page 1 of 6 Legal implications The current contract does not cover the entire scheme and so a contract variation is being proposed; this will avoid a new procurement having to be carried out. The S106 contributions must be spent in accordance with the terms of the agreements under which they were provided
HR implications No Implications (including learning and organisational Contact officer: Julie McCarthy, development) Julie [email removed], 01242 264355
Key risks Inability to utilise the funding and consequently vary the contract value will mean the play area will be unable to be completed until alternative funding is secured and cost more in the long run
Corporate and The play area redevelopment forms part of our environmental outcomes community plan within the corporate action plan for 2015/16 (env4), and has been highly Implications publicised and supported by councillors and the residents of Cheltenham. The work is on track to be completed by June 2016 and any delay to this would impact access to the extended play area by both able bodied children and those with disabilities.
Environmental and No implications arising from this report climate change implications
Property/Asset Funding for the aviary refurbishment is secured and this work will proceed. Implications Contact officer: David Roberts
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.