Grant Letters of Rep: 0 Update Report: Officer update MJC said this is a county council application for repair works to Cudnall Bridge, following a recent incident where a vehicle collided into it. It is in a conservation area, and the work has been assessed accordingly and considered acceptable. As Members on Planning View are aware, the work has already been carried out, and the blue update refers to Members’ concerns about the quality of the finish of that work. Officers will ask that it is redone, with the render more appropriate and improving the juncture to the pier. This will be requested if permission is granted. Public Speaking: None. Member debate: KS: is concerned about the issue of the finish, and whether Gloucestershire Highways will actually re-do the work. Does not have much faith that it will be done. HM: notes that Condition 1 requires the work to be completed in five years; understood that a three-year limit was normal now. MJC, in response: - listed building consents differ from ordinary planning permissions in this respect – they have different time frames on account of coming under different acts. Vote on officer recommendation to grant 13 in support 1 abstention GRANT
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
PROPOSAL: Reinstate bridge parapet, pilaster and approach wall following partial damage
RECOMMENDATION: Grant
This site map is for reference purposes only. OS Crown Copyright. All rights reserved Cheltenham Borough Council 100024384 2007 1. DESCRIPTION OF SITE AND PROPOSAL Cudnall Bridge is a grade II listed limestone ashlar bridge and parapet with three matching ashlar end piers and one very damaged pier to which this application refers. The proposal is to reinstate the damaged part of the parapet; pier and approach wall following the partial damage of the structure caused by a lorry collision. The site is prominent and the whole ensemble is an attractive set piece within the setting of the Cudnall Street Conservation Area.
2. CONSTRAINTS AND RELEVANT PLANNING HISTORY Constraints: Flood Zone 2 Flood Zone 3 Listed Buildings Grade 2
Relevant Planning History: None.
3. POLICIES AND GUIDANCE Adopted Local Plan Policies CP 7 Design BE 9 Alteration of listed buildings
National Guidance National Planning Policy Framework
4. CONSULTATIONS
Wales And West Utilities 16th August 2016 Comments available to view on line.
Parish Council 9th August 2016 No objection
GCC Highways Planning Liaison Officer 9th August 2016 I have no objection to the proposed repair works.
Statement of Due Regard Consideration has been given as to whether any inequality and community impact will be created by the transport and highway impacts of the proposed development. It is considered that no inequality is caused to those people who had previously utilised those sections of the existing transport network that are likely to be impacted on by the proposed development. It is considered that the following protected groups will not be affected by the transport impacts of the proposed development: age, disability, gender reassignment, marriage and civil partnership, pregnancy and maternity, race, religion or belief, sex, sexual orientation, other groups (such as long term unemployed), social- economically deprived groups, community cohesion, and human rights.
Gloucestershire Centre For Environmental Records 12th August 2016 Report available to view on line.
5. PUBLICITY AND REPRESENTATIONS Number of letters sent 6 Total comments received 0 Number of objections 0 Number of supporting 0 General comment 0
5.1A site notice was displayed near to the site and an advertisement was placed in the Gloucestershire Echo as required.
6. OFFICER COMMENTS 6.1 Determining Issues
6.2The determining issue is the impact of the proposed repair works on the remaining listed structures which are largely intact. The damaged pier has previously been replaced and on that occasion the materials and finish of the pier was not a sympathetic match to the existing piers. The piers were rendered and the block work scribed into the render. An attempt is being made with this proposal to match the ashlar stone work and this is welcomed. Due to the vulnerability of the pier’s location and likelihood that it will be struck again the use of cast stone on this occasion has been supported. The cast stone will have the appearance of natural stone and allows for the core to be reinforced.
7. CONCLUSION AND RECOMMENDATION 7.1 This proposal is a pragmatic solution for a vulnerable listed structure and although the materials are not like for like the appearance will be improved, and this, in view of its location and the strong likelihood that the pier will be hit again is considered an appropriate response. The proposal accords with local and national policy that seeks development that enhances sensitive heritage locations and is therefore recommended for approval subject to the following conditions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.