RESOLVED THAT 1. the early surrender of the lease between Cheltenham Borough Council and Oakley Regeneration Partnership be agreed to enable the Council to assume operational responsibility of the building from 1.11.16. 2. authority be delegated to the Head of Property and Asset Management to enter into a surrender agreement with Oakley Regeneration Partnership that protects the council’s interests with regard to dilapidations, that permits entry for CBC staff onto the premises from 1 November 2016 and that ensures all rents paid in advance are divided appropriately between ONP and CBC. 3. authority be delegated to the Head of Property Services to agree terms with Cheltenham Borough Homes Ltd and Gloucestershire Care Services to secure occupation by those organisations until the expiry date of their existing sub- underleases , upon substantially the same terms as those in the existing sub- underleases granted by ONP to Cheltenham Borough Homes Ltd and Gloucestershire Care Services.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 28 October 2016 Oakley Resource Centre
Accountable member Leader, Cllr. Steve Jordan
Accountable officer Strategy and Engagement Manager, Richard Gibson,
Ward(s) affected Oakley, plus neighbouring wards; Pittville, Prestbury, Battledown, All Saints
Key/Significant Yes Decision
Executive summary Cheltenham Borough Council owns the freehold of the Oakley Resource Centre. The building is leased out in its entirety to Oakley Regeneration Partnership (ORP), who then sub-let the building to Oakley Neighbourhood Project (ONP) who in turn sub-let it to Cheltenham Borough Homes and Gloucestershire Care Services. ONP also deliver a range of community activities from the building and hire the meeting rooms out for external use. The building provides a valuable resource for the local community with an estimated footfall of 7,500 visitors per annum.
On 14 September 2016, the joint trustees of ORP and ONP announced that they are undertaking the managed closure of both organisations. As part of this process, ONP staff have been put on notice with contracts terminating on 31.10.16.
The council wishes to take steps to ensure that the community-side of the building remains open to the public from 1 November 2016 and this report sets out the following recommendations:
Recommendations Cabinet resolves to:
1. Agree to the early surrender of the lease between Cheltenham Borough Council and Oakley Regeneration Partnership to enable the Council to assume operational responsibility of the building from 1.11.16.
2. Delegate authority to the Head of Property Services to enter into a surrender agreement with Oakley Regeneration Partnership that protects the council’s interests with regard to dilapidations, that permits entry for CBC staff onto the premises from 1 November 2016 and that ensures all rents paid in advance are divided appropriately between ONP and CBC.
3. If the surrender agreement is not in a position to be signed by 31.10.16, agree that CBC can take possession of the building from 1.11.16.
4. Delegate authority to the Head of Property Services to agree terms with Cheltenham Borough Homes Ltd and Gloucestershire Care Services to secure occupation by those
Oakley Resource Centre Page 1 of 7 Last updated 20 October 2016 organisations until the expiry date of their existing sub- underleases, upon substantially the same terms as those in the existing sub-underleases granted by ONP to Cheltenham Borough Homes Ltd and Gloucestershire Care Services.
Financial implications The council currently foregoes a market rent of £48,000 on this property.
ONP currently bring in rental income from CBH, Gloucestershire Care Services and a range of hire agreements for use of the meeting rooms. ONP also levy a service charge on tenants that recoups the running costs of the building. To 31 March 2017, the council will therefore gain 5 months rental and hire income from the building.
To ensure that the council can ensure that the building is open to the public, a recruitment process has been started for a building supervisor, at a predicted cost of £8,000 to 31 March 2017. Initially, this will be funded via a budget virement from a salary underspend from within the Commissioning Division with a view that this will be compensated by income received once the lease is surrendered and rental income subsequently reverts to the council.
Assuming that the council is able to recharge the majority of the running costs in service charges, it is estimated that taking on the building will bring a positive return to the general fund. The full financial implications of the decision will be captured in the budget setting report to Council in February 2017.
Contact officer: Nina Phillipidis, Deputy s.151 Officer, GO Shared Services
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.