Item4

Resolved

RESOLVED THAT 1. the early surrender of the lease between Cheltenham Borough Council and Oakley Regeneration Partnership be agreed to enable the Council to assume operational responsibility of the building from 1.11.16. 2. authority be delegated to the Head of Property and Asset Management to enter into a surrender agreement with Oakley Regeneration Partnership that protects the council’s interests with regard to dilapidations, that permits entry for CBC staff onto the premises from 1 November 2016 and that ensures all rents paid in advance are divided appropriately between ONP and CBC. 3. authority be delegated to the Head of Property Services to agree terms with Cheltenham Borough Homes Ltd and Gloucestershire Care Services to secure occupation by those organisations until the expiry date of their existing sub- underleases , upon substantially the same terms as those in the existing sub- underleases granted by ONP to Cheltenham Borough Homes Ltd and Gloucestershire Care Services.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Cabinet

Cheltenham Borough Council Cabinet – 28 October 2016 Oakley Resource Centre

Accountable member Leader, Cllr. Steve Jordan

Accountable officer Strategy and Engagement Manager, Richard Gibson,

Ward(s) affected Oakley, plus neighbouring wards; Pittville, Prestbury, Battledown, All Saints

Key/Significant Yes Decision

Executive summary Cheltenham Borough Council owns the freehold of the Oakley Resource Centre. The building is leased out in its entirety to Oakley Regeneration Partnership (ORP), who then sub-let the building to Oakley Neighbourhood Project (ONP) who in turn sub-let it to Cheltenham Borough Homes and Gloucestershire Care Services. ONP also deliver a range of community activities from the building and hire the meeting rooms out for external use. The building provides a valuable resource for the local community with an estimated footfall of 7,500 visitors per annum.

On 14 September 2016, the joint trustees of ORP and ONP announced that they are undertaking the managed closure of both organisations. As part of this process, ONP staff have been put on notice with contracts terminating on 31.10.16.

The council wishes to take steps to ensure that the community-side of the building remains open to the public from 1 November 2016 and this report sets out the following recommendations:

Recommendations Cabinet resolves to:

1. Agree to the early surrender of the lease between Cheltenham Borough Council and Oakley Regeneration Partnership to enable the Council to assume operational responsibility of the building from 1.11.16.

2. Delegate authority to the Head of Property Services to enter into a surrender agreement with Oakley Regeneration Partnership that protects the council’s interests with regard to dilapidations, that permits entry for CBC staff onto the premises from 1 November 2016 and that ensures all rents paid in advance are divided appropriately between ONP and CBC.

3. If the surrender agreement is not in a position to be signed by 31.10.16, agree that CBC can take possession of the building from 1.11.16.

4. Delegate authority to the Head of Property Services to agree terms with Cheltenham Borough Homes Ltd and Gloucestershire Care Services to secure occupation by those

Oakley Resource Centre Page 1 of 7 Last updated 20 October 2016 organisations until the expiry date of their existing sub- underleases, upon substantially the same terms as those in the existing sub-underleases granted by ONP to Cheltenham Borough Homes Ltd and Gloucestershire Care Services.

Financial implications The council currently foregoes a market rent of £48,000 on this property.

ONP currently bring in rental income from CBH, Gloucestershire Care Services and a range of hire agreements for use of the meeting rooms. ONP also levy a service charge on tenants that recoups the running costs of the building. To 31 March 2017, the council will therefore gain 5 months rental and hire income from the building.

To ensure that the council can ensure that the building is open to the public, a recruitment process has been started for a building supervisor, at a predicted cost of £8,000 to 31 March 2017. Initially, this will be funded via a budget virement from a salary underspend from within the Commissioning Division with a view that this will be compensated by income received once the lease is surrendered and rental income subsequently reverts to the council.

Assuming that the council is able to recharge the majority of the running costs in service charges, it is estimated that taking on the building will bring a positive return to the general fund. The full financial implications of the decision will be captured in the budget setting report to Council in February 2017.

Contact officer: Nina Phillipidis, Deputy s.151 Officer, GO Shared Services

[email protected], 01242 264121

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Oakley Resource CentreReport 109 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 13 attended
SJ
Councillor Steve Jordan Leader of the CouncilCommittee Member, present
FC
Councillor Flo Clucas Cabinet Member Healthy LifestylesCommittee Member, present
CC
Councillor Chris Coleman Cabinet Member Clean and Green EnvironmentCommittee Member, present
RH
Councillor Rowena Hay Cabinet Member FinanceCommittee Member, present
PJ
Councillor Peter Jeffries Cabinet Member HousingCommittee Member, present
AM
Councillor Andrew McKinlay Cabinet Member Development and SafetyCommittee Member, present
RW
Councillor Roger Whyborn Cabinet Member Corporate ServicesCommittee Member, present
PP
Pat PratleyOfficer, in attendance
MS
Mark SheldonOfficer, expected
MR
Mike RedmanOfficer, expected
BT
Beverly ThomasOfficer, expected
RR
Rosalind ReevesSecretary, expected

All 13 on the meeting page

More from Cheltenham Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... Noted Open
15 Sep 2026 Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... Approved Open
15 Sep 2026 Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... Decided Open
15 Sep 2026 Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... Agreed Open
15 Sep 2026 Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies