It was agreed to amend the second recommendation to include consultation with the Cabinet Member Housing, which would be particularly relevant if the number of dwellings changed. A Member commented on the benefit the developments on garage sites had brought to those areas and praised CBH, the council and the contractors for their work with those communities. The care and attention paid to the neighbours during the construction phase had been much appreciated and hoped this approach would continue. RESOLVED THAT 1. Subject to subsequent Council approval, the Authority be authorised to accept the tender received from J Harper and Sons enter into a JCT Design and Build Contract for the construction of up to twelve new dwellings with Total Scheme Costs not to exceed £1,772,000. 2. authority be delegated to the Head of Property and Asset Management, in consultation with the Borough Solicitor and the Cabinet Member Housing to: 2.1 Conclude the JCT Design and Build contract with J Harper and Sons. 2.2 Tak e all necessary steps and undertake all necessary procedures, including entering into any legal agreements or other documentation as may be required to implement or facilitate the developments . 2.3 Agree the final number of dwellings that will be built, in the event that the council is unable to proceed with the development of all twelve new dwellings because of site complications (such as unresolved rights ... view the full minutes text for item 8.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 8th November 2016 Council – 12th December 2016
Housing Revenue Account New Build- Garage site redevelopments and the use of Right to Buy Receipts
Accountable member Councillor Peter Jeffries, Cabinet Member Housing
Accountable officer Martin Stacy, Lead Commissioner – Housing Services
Ward(s) affected Hester’s Way, Battledown, Springbank (and potentially any ward should Right to Buy Receipts be also used to purchase dwellings)
Key Decision / Yes Significant
Executive summary In March 2015 Cabinet resolved that the Authority seek bids from contractors to build new homes across Cheltenham on a number of garage sites. Following a recent procurement exercise this report seeks approval to enter into a JCT Design and Build Contract with J Harper and Sons with Total Scheme Costs not to exceed £1,772,000. The scheme will deliver up to twelve new homes on three HRA garage sites.
Whilst the Authority’s preferred option is to build affordable homes on council-owned land, the complex nature of some of these sites means that it may not always be possible to spend Right to Buy Receipts in this way due to the government imposed time limits on the use of these Receipts. (Right to Buy Receipts must be used within 3 years; otherwise they have to be returned to the government with interest.)
It is therefore proposed that any Right to Buy Receipts that cannot be used for building new affordable homes on council-owned land be used instead for purchasing dwellings, subject to appropriate parameters, as detailed in the recommendation below and at Section 5.4 of this report.
To date three homes have been purchased in this way, with a further four homes in the pipeline, following Cabinet approvals in November 2015 and again in September 2016 to use Right to Buy Receipts for this purpose.
Recommendations That Cabinet:-
1. Subject to subsequent Council approval, authorise the Authority to accept the tender received from J Harper and Sons enter into a JCT Design and Build Contract for the construction of up to twelve new dwellings with Total Scheme Costs not to exceed £1,772,000.
2. Delegate authority to the Head of Property and Asset Management, in consultation with the Borough Solicitor to:
2.1Conclude the JCT Design and Build contract with J Harper and Sons.
$rlwwp2as.docx Page 1 of 12 Last updated 28 October 2016 2.2 Take all necessary steps and undertake all necessary procedures, including entering into any legal agreements or other documentation as may be required to implement or facilitate the developments.
2.3Agree the final number of dwellings that will be built, in the event that the council is unable to proceed with the development of all twelve new dwellings because of site complications (such as unresolved rights of way issues).
3. Delegate authority to the Head of Property and Asset Management, in consultation with the Section 151 Officer and Cabinet Member for Housing, to use the Right to Buy Receipts to purchase dwellings that are considered suitable for use as affordable housing (in accordance with the parameters set out within paragraph 5.4 of this report) PROVIDED THAT the Head of Property Services is satisfied it would not be possible to use these receipts to support the approved delivery of new affordable housing on council owned sites due to time restrictions on the use of these receipts and PROVIDED FURTHER that the expenditure remains within Council approved budgets for the use of delivering new affordable housing.
4. Authorise the Borough Solicitor to negotiate and complete such documents as she deems necessary or desirable to conclude the transactions negotiated by the Head of Property and Asset Management.
5. Authorise the Authority to charge Affordable Rents to all dwellings.
Cabinet recommends that Council:
6. Authorise the allocation of up to £1,772,000 for the construction of up to twelve new dwellings.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.