RESOLVED (unanimously) THAT an unsecured loan of £50,000 be authorised to St. Margaret’s Hall Users Group for the purposes of enabling the construction of the proposed annex upon terms and conditions as the Director of Resources considers reasonable, and to authorise the Borough Solicitor to conclude such documents as she considers necessary or desirable to protect the Council’s position.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Council – 12 December 2016 Agreement to loan to support the construction of an annex at St. Margaret’s Hall
Accountable member Cllr. Rowena Hay; Cabinet Member Finance
Accountable officer Richard Gibson, Strategy and Engagement Manager
Ward(s) affected St. Margaret’s Hall lies in Warden Hill ward, but serves a much wider geography.
Key/Significant No Decision
Executive summary Council on 18th July 2016 agreed that an in-principle loan be made to The Trustees of St. Margaret’s Hall Users Group for the purposes of enabling further fund-raising to take place in connection with the construction of the proposed annex. The offer was made subject to the following conditions:
1. The offer of the loan in-principle was to remain open for 12 months.
2. The offer of the loan in-principle is only to be used in connection with the proposed Annex and to help the User Group secure the additional funds necessary to enable the build contract to be entered into.
3. Subject to the User Group securing all the necessary funds to cover the proposed total cost of the whole scheme, a further report would be considered by full council to agree whether the “in-principle” loan be turned into an agreed loan.
St. Margaret’s Hall Users Group have now confirmed that all the necessary funds are in place to meet condition 3 and as a result have requested that the “in-principle” loan be turned into an agreed loan.
Recommendations Full council is asked to authorise an unsecured loan of £50,000 to St. Margaret’s Hall Users Group for the purposes of enabling the construction of the proposed annex upon terms and conditions as the Director of Resources considers reasonable, and to authorise the Borough Solicitor to conclude such documents as she considers necessary or desirable to protect the Council’s position.
Financial implications The St Margaret’s Hall user group have secured funds to cover the estimated £150k total cost of the annex. The details of the funding and terms of the proposed loan is included in section 4 of this report.
Contact officer: Sarah Didcote GO Business Partner Manager (West) [email protected] 01242 264125
St. Margaret’s Hall Report to Council 12.12.16 Page 1 of 6 Last updated 02 December 2016 Legal implications The Council has broad powers (including under Section 19 of the Local Government (Miscellaneous Provisions) Act 1976) to support the provision of recreational facilities, including by way of giving grants or loans to third parties.
As the property is leased by the Council to the Users’ Group (and a new lease is proposed), it will be important to ensure that the lease and the loan agreement are co-ordinated and that the works are monitored.
Whilst the taking of a charge over property is usually considered when making a loan of this amount, as in this instance the Council is the landlord, a charge over the lease would be of negligible benefit.
It would be usual, in this instance where the borrower is an unincorporated charity, to limit the liability of the trustees under the loan agreement to the assets of the charity.
Contact officer: Rose Gemmell [email protected] 01684 272014 HR implications No HR implications identified with this report (including learning and organisational development) Property/Asset As set out in the report. Implications Contact officer: David Roberts Head of Property Services [email protected] 01242 264151 Key risks Inability of the St. Margaret’s Hall Users Group to re-pay the loan in accordance with terms and conditions
If the St. Margaret’s Hall Users Group go bankrupt during the construction and of part of the loan has been paid to them, there is a risk that the council will not recoup the loan maximum exposure of £50,000
Construction costs of the annex increase meaning that St. Margaret’s Hall Users Group have insufficient funds to complete the annex.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.