RESOLVED THAT 1. It be noted that the Head of Paid Service has delegated authority under the Authority’s constitution to enter into the grant agreement with Sport England. 2. Authority be delegated to the s.151 Officer, in consultation with the Cabinet Member Healthy Lifestyles and Cabinet Member Finance, to agree any subsequent arrangements with the Trust to manage the capital funds to achieve the completion and funding of the works as set out in this report.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet 11 July 2017 Arrangements for managing a Sport England Grant to make improvements to Leisure-at-Cheltenham
Accountable member Cllr. Flo Clucas; Cabinet Member Healthy Lifestyles
Accountable officer Richard Gibson, Strategy and Engagement Manager
Ward(s) affected All
Key/Significant No Decision
Executive summary The Cheltenham Trust successfully bid to Sport England for a Swim Local grant that will fund a range of improvements at leisure-at-Cheltenham to encourage people to swim. The grant award is broken down into two elements. A revenue grant of £150,981 to fund improvements to the swimming experience and the range of programmes that are on offer. A capital grant of £184,480 to fund the creation of new disabled changing units and improvements to the female changing area. Due to the Trust only having 7 secure years left of their lease, Sport England have offered the capital grant to Cheltenham Borough Council to manage. This report puts forward a solution for managing the capital grant in 2017.
Recommendations 1 Note that the Head of Paid Service has delegated authority under the Authority’s constitution to enter into the grant agreement with Sport England.
2 Cabinet delegates authority to the s.151 Officer, in consultation with the Cabinet Member Healthy Lifestyles and Cabinet Member Finance, to agree any subsequent arrangements with the Trust to manage the capital funds to achieve the completion and funding of the works as set out in this report.
Financing of improvements to Leisure@ Page 1 of 8 Last updated 30 June 2017 Financial implications Payment of the £184k grant is subject to a number of conditions including Securing of planning permission and compliance with conditions Securing of landlords permission Submission of a project plan and key indicators Submission and management of a project risk register Evidence of a safeguarding policy Final design being signed off by Sport England Compliance with procurement rules A restriction on title being registered at the Land Registry
Contact officer: Sarah Didcote GO Business Partner Manager (West) [email protected] 01242 264125 Legal implications Sport England requires the Authority as the landowner to enter into the grant agreement for a period of 25 years. One Legal has given detailed legal advice to council officers on the terms, conditions and restrictions imposed by this grant agreement.
As the Authority is responsible for compliance with the terms of the Sport England Grant Agreement, if any funds are passed onto the Trust to manage, then advice has been given to officers that the Authority should enter into an agreement with the Trust in which the Trust agrees to comply with the terms of the Sport England Grant and indemnify the Authority for any losses caused by any breach of the agreement.
Contact officer: Donna Ruck, Solicitor, One Legal Tel: 01684 272696 [email protected]
HR implications No HR implications identified with this report (including learning and organisational development)
Financing of improvements to Leisure@ Page 2 of 8 Last updated 30 June 2017 Property/Asset Leisure-at Cheltenham is currently leased to the Trust on a 15 year term Implications starting on October 2014 with a break clause at year 10, which is why Cheltenham Borough Council has been offered the grant and not the Trust. There are a number of property risks in accepting the grant.
There is an obligation on the Council to seek Sport England’s permission when letting the whole of the Leisure Centre for the next 25 years. It is unclear what the recourse is for not seeking this permission, but it is thought that partial or full repayment of the grant could be one. Seeking permission could also impact in terms of time delays on re-letting the Leisure Centre as there is no set time in which Sport England has to reply when approached for permission.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.