Resolved
RESOLVED THAT the updated Local Development Scheme for Cheltenham Borough, attached to the report at Appendix 2, be ADOPTED and take effect immediately.
Cabinet approved this item on Tuesday 10 October 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED THAT the updated Local Development Scheme for Cheltenham Borough, attached to the report at Appendix 2, be ADOPTED and take effect immediately.
Cheltenham Borough Council
Cabinet – 10th October 2017
2017 Cheltenham Local Development Scheme
Accountable member Councillor Jordan – Leader
Accountable officer Philip Stephenson – Development Manager Strategy
Ward(s) affected All
Executive summary The Cheltenham Borough Local Development Scheme (LDS) outlines the timetable for preparing statutory development plan documents in the Borough. The published version (adopted by the Council in February 2015) requires revision as the timetable is now out of date following an extended examination of the Joint Core Strategy and to incorporate the latest timescales for the Cheltenham Plan. Due to changes in the Council’s constitution since the last version in 2015, the decision to adopt an amended LDS can now be made by Cabinet rather than full Council.
Recommendations That it be RESOLVED:
1. That the updated Local Development Scheme for Cheltenham Borough, attached to the report at Appendix 2, be ADOPTED and take effect immediately.
Financial implications The approval of the LDS document itself does not have any direct financial implications for the authority, as it is simply an overview of the agreed timetable for the production of different Development Plan Documents. However each of these (the Joint Core Strategy and Cheltenham Plan) have separate financial implications, which are considered through their own programme management.
The JCS budget is monitored by Cross Boundary Programme Board
The Cheltenham Plan budget is monitored by the Head of Planning
Contact officer: [email protected] 01242 775 154
LDS 2015 – Council report 2017 Page 1 of 5 Last updated 28 September 2017 Legal implications The preparation and maintaining of a Local Development Scheme is required under section 15 of the Planning and Compulsory Purchase Act 2004. This must specify (among other matters) the documents which, when prepared, will comprise the Local Plan for the area and the timetable for the preparation and revision of those documents. The Local Plan, together with Neighbourhood Plans making the Development Plan for the Borough.
Contact officer: [email protected], 01684 272013
HR implications There are no staffing or Trade Union implications. (including learning and organisational Contact officer: [email protected], 01242 264355 development)
Key risks Failure to produce the Local Development Scheme would be contrary to the requirements of the Act and could cause delay in the Examination in Public/progression of the Joint Core Strategy or Cheltenham Plan, as such development plan documents when examined need to be prepared in accordance with the Local Development Scheme. It would also mean that elected members and the public would be less well informed as to the overall timetable for the production of Development Plan Documents.
Environmental/Social/ The Local Development Scheme is not subject to Sustainability Appraisal, Equality Implications but both the Joint Core Strategy and Cheltenham Plan referred to in it are, and sustainability appraisal including habitats and equalities assessment are being progressed as according to their individual programme management timetables in the JCS and Cheltenham Plan Project Initiation Document.
Property Implications There are no property implications arising from the LDS itself, although both the JCS and Cheltenham Plan contain sites which are partly or completely within the Borough’s ownership. Decisions on those documents will require consideration by the property service.
[email protected], 01242 264151
1. Background 1.1 The Local Development Scheme (LDS) collects together the separate timetables for the preparation of statutory development plan documents (DPD) and presents them in one document with commentary.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2017 Cheltenham Local Development SchemeReport | 96 KB | DownloadRead as text |
PDF |
2017_10_10_CAB_CBC_LDS FinalReport | 117 KB | Download |
Follow Cabinet at Cheltenham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... | Noted | Open |
| 15 Sep 2026 | Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... | Approved | Open |
| 15 Sep 2026 | Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... | Decided | Open |
| 15 Sep 2026 | Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... | Agreed | Open |
| 15 Sep 2026 | Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.