Revised financing arrangements for improvements to Leisure-at-Cheltenham

Approved Executive 1 paper

Cabinet approved this item on Tuesday 5 December 2017. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED THAT 1. the revised programme of improvements to Leisure-at-Cheltenham as set out in section 3 of this report be approved. 2. Authority be delegated to the Director Resources and Corporate Projects in consultation with the Cabinet Member Healthy Lifestyles and the Borough Solicitor to enter into a contract with Alliance Leisure Services and any other legal agreements and processes necessary to progress the scheme whilst safeguarding the Council’s interest. Council be recommended to : 3. Subject to the conditions in section 7 being met, authorise the Section 151 Officer, in consultation with the Cabinet Member Finance, to seek prudential borrowing of up to £2.236m at an interest rate of 2% per annum to fund the improvements to Leisure-at-Cheltenham as detailed in Section 3 of this report; 4. Authorise the Section 151 Officer, in consultation with the Cabinet Member Healthy Lifestyles, to agree the most advantageous repayment methodology to reclaim the cost of the borrowing from the Cheltenham Trust;
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Cabinet

Cheltenham Borough Council Cabinet 5 December 2017 Council 11 December 2017 Revised financing arrangements for improvements to Leisure-at- Cheltenham

Accountable member Cllr. Flo Clucas; Cabinet Member Healthy Lifestyles

Accountable officer Mark Sheldon, Director Resources and Corporate Project

Ward(s) affected All

Key/Significant Yes Decision

Executive summary Council on 27 March 2017 gave approval to lend The Cheltenham Trust up to £1.5m to fund a range of improvements to Leisure-at-Cheltenham. The loan was to be at an interest rate of 3% per annum. The proposed works were as follows:  Convert two existing squash courts into new studios to enable an increase in the number of class and activity programmes.  Upgrade the existing dry-side changing spaces to reflect the quality of offer that customers expect and that competes well with the local market.  The provision of a new sauna and steam room suite adjacent to the new changing rooms, strengthening the link with health and fitness and replacing the outdated existing health suite facilities.  Extend the existing fitness suite on the ground floor into the current dance studio enabling an increased capacity to meet demand and enable improved functional training space and health support related activities.  Conversion of the existing health suite into an aquatics play space, developing and extending the aquatics opportunities for families with young children and also the commercial hires for children’s birthday parties. Following on from the Council decision, the Trust worked with its development partner Alliance Leisure Services (ALS) to advance the scheme within the agreed financial framework. After much deliberation, it has been concluded that this is not possible. A summary of the reasons for this cost increase are provided in section 2 Part of the reason for the cost increase is that the suite of capital works that would be delivered through the partnership with Alliance Leisure Services has been revised. This includes the original elements included in the March council report but also now includes improvements to the reception and entry arrangements, plus improvements to the swimming changing facilities (funded by a grant from Sport England) and improvements to the air conditioning (funded by CBC). Details of the updated capital works are set out in section 3.

Revised financing of improvements to Leisure-at Page 1 of 15 Last updated 24 November 2017 In terms of the revised capital costs, there is now cost certainty of build and equipment costs of £1.658m excluding the aquatics play-space which is estimated to cost £731k that will be confirmed at the date of this report to Council. In addition, provision has been made for client contingency and client support costs, giving total estimated scheme costs of £2.554m. Once grant funding and other contributions are taken into account, the revised funding requirement is £2.236m. This is the maximum figure that is being considered. Further details of the costs of the scheme are provided in section 4 and exempt appendices 1 and 2.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revised financing arrangements for improvements to Leisure-at-CheltenhamReport 160 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 13 attended
SJ
Councillor Steve Jordan Leader of the CouncilCommittee Member, present
FC
Councillor Flo Clucas Cabinet Member Healthy LifestylesCommittee Member, present
CC
Councillor Chris Coleman Cabinet Member Clean and Green EnvironmentCommittee Member, apologies
RH
Councillor Rowena Hay Cabinet Member FinanceCommittee Member, present
PJ
Councillor Peter Jeffries Cabinet Member HousingCommittee Member, present
AM
Councillor Andrew McKinlay Cabinet Member Development and SafetyCommittee Member, present
RW
Councillor Roger Whyborn Cabinet Member Corporate ServicesCommittee Member, apologies
PP
Pat PratleyOfficer, present
MS
Mark SheldonOfficer, present
MR
Mike RedmanOfficer, expected
BT
Beverly ThomasOfficer, expected
RR
Rosalind ReevesSecretary, expected

All 13 on the meeting page

On this subject at Cheltenham

Search all
  1. Revised financing arrangements for improvements to Leisure-at-CheltenhamThis decision
  2. Revised financing arrangements for improvements to Leisure-at-CheltenhamDecided

More from Cheltenham Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... Noted Open
15 Sep 2026 Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... Approved Open
15 Sep 2026 Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... Decided Open
15 Sep 2026 Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... Agreed Open
15 Sep 2026 Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. Approved Open