RESOLVED THAT 1) the essential and desirable items listed in paragraphs 4.1 and 4.2 are purchased by Cheltenham Borough Council within a total cost of £66,000 . 2) a sum of £5000 is provisioned for maintenance and support of the system over a 5 year period as follows: i ) £1000 for 2018/19 from the £75K allocated for the capital expenditure ii) in subsequent years it is proposed to increase the current Municipal Offices maintenance budget by £1000 p.a to cover this either through a transfer from existing budgets or a growth bid. 3) the remaining £8 K from the £75 K allocated is retained during 2018/19 for additional unforeseen costs and contingencies that may arise during the implementation, and/or later enhancements to be authorised by the Head of Property Services in consultation with the Cabinet Member Corporate Services.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 10 April 2018 Replacement audio visual system in the Council chamber
Accountable member Cabinet Member Corporate Services, Councillor Roger Whyborn
Accountable officer Director of Corporate Resources, Mark Sheldon
Ward(s) affected All
Key/Significant No Decision
Executive summary For some time there have been intermittent problems with the sound system in the Council Chamber which has caused difficulties in public meetings and there is a widespread view amongst councillors and some of the public that it is not fit for purpose. There are limitations of the current equipment which is now over 12 years old and no longer manufactured and it is not cost effective to carry out anything other than ad hoc repairs as required.
A project was set up in September 2017 to consider the options for replacing the system and a Cabinet Member working group was set up to help define the priorities. The project aims to replace the current audio system in the Council Chamber, and add additional options dependent on costings, and business case, as well as to prioritise compliance with the requirement to provide ‘assistive listening’.
The requirements were put out to tender in January this year and a preferred supplier was chosen on the basis of cost and quality.
In February 2018 Council allocated a sum of up to £75,000 to be earmarked for this expenditure and it is now coming back to Cabinet to approve the final purchase. The proposed expenditure and rationale for the options chosen are set out in this report.
Recommendations 1) That the essential and desirable items listed in paragraphs 4.1 and 4.2 are purchased by Cheltenham Borough Council within a total cost of £66,000.
2) That a sum of £5000 is provisioned for maintenance and support of the system over a 5 year period as follows: i) £1000 for 2018/19 from the £75K allocated for the capital expenditure ii) in subsequent years it is proposed to increase the current Municipal Offices maintenance budget by £1000 p.a to cover this either through a transfer from existing budgets or a growth bid.
3) That the remaining £8K from the £75 K allocated is retained during 2018/19 for additional unforeseen costs and contingencies that may arise during the implementation,
Page 1 of 13 Last updated 29 March 2018 and/or later enhancements to be authorised by the Head of Property Services in consultation with the Cabinet Member Corporate Services.
Financial implications The initial costs of £67,000 for the purchase of the equipment and first year’s maintenance costs will be funded from the 2018/19 capital budget of £75,000 approved by Council at the budget setting meeting on19 February 2018. The balance of £8,000 will be used for further equipment or additional associated costs in 2018/19 or carried forward for use in future years.
Annual maintenance costs of £1,000 per annum for the financial year 2019/20 onwards will be included as growth to the council’s revenue base budget, subject to approval by Council as part of the 2019/20 budget setting process
Legal implications Tenders within budget and not exceeding £100,000 can be accepted by an authorised officer. The form of contract must be approved by the Council Solicitor in accordance with the Contract Rules.
The data protection aspects of the new system will need to be fully considered prior to implementation. This should include a retention policy (which will also be relevant to managing information in a freedom of information context).
HR implications There are no direct HR implications arising from this report. (including learning and organisational Julie McCarthy ( HR Manager – Publica Group) development) [email protected] Tel: 01452 264355
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.