Cheltenham Borough Council
Cabinet, Tuesday 9 October 2018 at 6.00pm

Update regarding business continuity issues at Cheltenham Crematorium

Noted Executive 1 paper

Cabinet noted this item on Tuesday 9 October 2018. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED THAT 1. the ongoing technical issues which the Director of Environment and the bereavement services team are managing in relation to the existing cremator plant be noted; 2. the decision taken by the Crematorium Business Continuity Management Group (CBCMG) to temporarily stop taking new bookings for cremation services be endorsed. 3. the phased shutdown of the cremation operation at the Bouncers Lane site be approved, noting that it may be necessary to arrange for cremations at alternative locations, should there be any further technical failure of the plant; 4. the development of an alternative interim service offer and related charges be approved, subject to consultation with funeral directors, which will be made available until the new crematorium becomes operational in Spring 2019; 5. authority be delegated to the Director of Environment, in consultation with the Cabinet Member for Clean and Green Environment, to finalise details of ... view the full minutes text for item 9.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Cabinet

Cheltenham Borough Council Cabinet – 9th October, 2018 Update regarding business continuity issues at Cheltenham Crematorium

Accountable member Councillor Chris Coleman, Cabinet Member for Clean & Green Environment

Accountable officer Mike Redman, Director of Environment

Ward(s) affected All

Key Decision? Yes

Executive summary This report provides an update in respect of ongoing challenges regarding the reliability of the cremators at Cheltenham crematorium, which will already be well known to members and which is one of the key reasons for the Council deciding to construct the new crematorium facility at the Bouncers Lane site.

Funeral directors have been advised of the current situation and have been requested to ensure that bereaved families are aware of the options available to them.

Recommendations Cabinet is recommended to:-

1. Note the ongoing technical issues which the Director of Environment and the bereavement services team are managing in relation to the existing cremator plant;

2. Endorse the decision taken by the Crematorium Business Continuity Management Group (CBCMG) to temporarily stop taking new bookings for cremation services;

3. Approve the phased shutdown of the cremation operation at the Bouncers Lane site, noting that it may be necessary to arrange for cremations at alternative locations, should there be any further technical failure of the plant;

4. Approve the development of an alternative interim service offer and related charges, subject to consultation with funeral directors, which will be made available until the new crematorium becomes operational in Spring 2019;

5. Delegate authority to the Director of Environment, in consultation with the Cabinet member for Clean and Green Environment, to finalise details of the revised service offer and take any other actions necessary to optimise service delivery arrangements and any associated contractual changes.

6. Note the projected financial impact arising from these

$wff3cjxs.doc Page 1 of 8 Last updated 02 October 2018 recommendations, as set out under the ‘Financial implications’ section below.

Financial implications The phased shutdown of the Council’s cremation operation will have a significant revenue impact in 2018-19, in addition to the income shortfall reported to Council in July 2018, already reflected in the 2018/19 current budget.

Whilst the financial outturn position will be mitigated if the new crematorium completes on time (as is currently expected), officers are anticipating that the net position may be up to £450k below target.

Officers are currently looking at future service options, to mitigate this position, the outcome of which will be reported in the Cabinet Budget monitoring report dated 6th November 2018.

Contact officer: Andrew Knott, [email removed]

Legal implications There is no statutory duty on a local authority to provide burial facilities, but if they do so, the management is governed by the Local Authorities’ Cemeteries Order 1977. Under the Local Government Act S214(1) and S214(7), as Cheltenham Borough Council (being deemed a Burial Authority) elected to provide these burial facilities, it has a responsibility to ensure that it maintains the facilities, which extends to crematoriums. Local authorities are defined as burial authorities and are given the power to provide cemeteries by virtue of the Local Government Act 1972.

Failure to provide such facilities could result in a fine for contravening such obligations under S214(3)(a). The Council has a statutory duty under the provisions of Section 46 of the Public Health (Control of Disease) Act 1984 to undertake the funeral of a deceased person, who died in the Borough of Cheltenham and where no other arrangements have been made or are about to be made.

Therefore, in the absence of any cremation facilities in Cheltenham, arrangements will need to be put in place to ensure this statutory duty is carried out regarding the above.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Update regarding business continuity issues at Cheltenham CrematoriumReport 98 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 13 attended
SJ
Councillor Steve Jordan Leader of the CouncilCommittee Member, present
FC
Councillor Flo Clucas Cabinet Member Healthy LifestylesCommittee Member, present
CC
Councillor Chris Coleman Cabinet Member Clean and Green EnvironmentCommittee Member, present
RH
Councillor Rowena Hay Cabinet Member FinanceCommittee Member, present
AH
Councillor Alex Hegenbarth Cabinet Member Corporate ServicesCommittee Member, present
PJ
Councillor Peter Jeffries Cabinet Member HousingCommittee Member, present
AM
Councillor Andrew McKinlay Cabinet Member Development and SafetyCommittee Member, present
PP
Pat PratleyOfficer, present
MS
Mark SheldonOfficer, expected
MR
Mike RedmanOfficer, expected
BT
Beverly ThomasOfficer, expected
RR
Rosalind ReevesSecretary, expected

All 13 on the meeting page

On this subject at Cheltenham

Search all
  1. Update regarding business continuity issues at Cheltenham CrematoriumThis decision
  2. Progress update regarding the new crematorium project including business case decisions regarding access road and second chapel optionApproved

More from Cheltenham Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... Noted Open
15 Sep 2026 Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... Approved Open
15 Sep 2026 Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... Decided Open
15 Sep 2026 Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... Agreed Open
15 Sep 2026 Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies