RESOLVED THAT 1. The decisions of Council set out in 1(a), (b) and (c) of the report be noted. 2. The extension of the CTP trial be agreed. 3. The Managing Director Place and Growth, in consultation with the Cabinet Member Development and Safety be authorised to work with GCC to facilitate the extension of the CTP trial.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Council – 21st January 2019 Cabinet - 22nd January 2019 Cheltenham Transport Plan – Update Report
Accountable member Councillor Andrew McKinlay – Cabinet Member Development & Safety
Accountable officer Tim Atkins – Managing Director (Place & Growth)
Ward(s) affected All
Key/Significant Significant Council – Key Cabinet Decision
Executive Summary Phase 4 of the Cheltenham Transport Plan (CTP) has been in place since 28th June 2018, following the successful implementation of the proceeding phases.
The CTP is delivering central government and (GCC) as transport authority policy, and also aligns with CBC’s corporate strategy as approved on 26th March 2018.
This report draws on the evidence from two technical appendices dealing with highway and environmental / economic matters. These highlight that the trial is having an overall positive impact and is successfully achieving objectives relating to modal shift, reduction in traffic, increased footfall and connectivity in the town centre and in particular assisting to strengthen Cheltenham’s ‘High Street’ offer. Issues relating to air quality based on monitoring to date are broadly neutral.
The report of the County Council’s cabinet member sets out the details of issues relating to the trial relating to transport and highway matters. It highlights issues that have arisen during the trial and proposes the trial period be extended along with the introduction of a number of mitigations.
It recommends that council notes and supports the findings of those reports and that Cabinet formally agree to the continuation of the trial with the proposed mitigations.
1. Council is recommended to: Recommendations a) Note and support the positive economic and environmental impact of the CTP set out in Appendix 2;
b) Note the Gloucestershire County Council Lead Cabinet Member Briefing findings and recommendations (Appendix
$hkb1mlon.docx Page 1 of 5 Last updated 21 January 2019 c) to extend the CTP trial for a further period with mitigation measures; and
d) Recommend that Cabinet agrees to the extension of the CTP trial.
2. Cabinet is recommended to:
a) Note the decisions of Council set out in 1(a), (b) and (c) above; and
b) Agree to the extension of the CTP trial; and
c) Authorise the Managing Director Place & Growth in consultation with the Cabinet Member of Development and Safety to work with GCC to facilitate the extension of the CTP trial.
Financial implications Any long term public realm changes associated with mitigation measures may require a CBC financial contribution, in line with the existing CBC / GCC funding arrangement related to the project.
Legal implications None specific in respect of the report recommendations. The County Council holds the statutory powers and responsibilities in respect of traffic regulation.
HR implications None relevant to this report (including learning and organisational development)
Key risks The key risks are set out in the risk matrix below.
Corporate and The delivery of the CTP stage 4 and closure of Boots Corner to general community plan traffic is a priority set out in the Council’s Corporate Plan. Implications
Environmental and An objective of the Local Sustainable Transport Fund is to encourage climate change modal shift to more sustainable forms of transport (walking, cycling & implications public transport) thereby contributing to national targets to reduce carbon emissions.
$hkb1mlon.docx Page 2 of 5 Last updated 21 January 2019 1. Background 1.1 Phase 4 of the CTP has been in place since 28th June 2018, following the successful implementation of the proceeding phases.
1.2The CTP is delivering central government and (GCC) as transport authority policy, and also aligns with CBC’s corporate strategy as approved on 26th March 2018.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.