Resolved
RESOLVED that the Cheltenham Crematorium Project lessons learnt report be noted.
Audit, Compliance and Governance Committee noted this item on Wednesday 24 April 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Cheltenham Crematorium Project lessons learnt report be noted.
Cheltenham Crematorium Project Lessons Learnt Update - Audit Committee – 24th April, 2019 Response to Scrutiny Task Group Recommendations
This document sets out the actions taken during the development of Cheltenham’s new crematorium, in response to the Overview and Scrutiny Task Group recommendations, arising from its review of the previous cremator replacement project in 2009-11
Recommendation Programme Response Was the response successful? On future projects, where the Council is bringing Selection of consultant for initial feasibility Yes. The results of the feasibility study, in a consultant to offer specialist knowledge and study was based on a 30:70 ‘cost to quality’ specifically the recommendation to build a experience, the evaluation criteria should be set weighting and an interview / presentation new crematorium and the establishment of a so that the ‘quality’ factor is given more process was undertaken. programme budget, have been vindicated by weighting than ‘cost’ and a face-to-face the subsequent success of the development interview should be carried out. project.
At an early stage, more opportunities should be Funeral directors were involved throughout Yes. Their views (most notably support for a provided for the industry (in this case the funeral the project development, from face-to-face new build solution) have been influential directors) to input any technical expertise or meetings with consultants at the initial throughout the project. Their involvement and recommendations, whilst being cautious as to feasibility stage, through to invitations to take support helped mitigate the impact of their own agendas. part in ‘funeral walk-through rehearsals’ in significant and recurring problems with the old the new buildings. cremators.
During the procurement process there should be A three month programme of commissioning Yes. The design and installation of FT an agreed and adequate period of testing, to and testing of the new cremators took place cremators was procured as a sub-contract by confirm that equipment is functioning properly after they were delivered to site. the lead contractor, Willmott Dixon, who thus before final payment is made. That the remain liable to CBC for defects during the 12 percentage of money retained for this purpose In contract negotiations, it was agreed that months period following handover. is more significant than the 5% held back on the 3% of the interim amounts payable would be earlier project. retained, pending final sign-off on the project.
Consideration should be given to putting in A 10 year maintenance contract is in place Yes. Whilst there were some procurement place a maintenance contract at the same time with the cremator suppliers. It was tendered and contractual complexities surrounding the as agreeing the purchase contract. and selected by Willmott Dixon with CBC novation process, we were successful in involvement, alongside the design and obtaining a competitively tendered package
Page 1 of 6 9th April 2019 Cheltenham Crematorium Project Lessons Learnt Update - Audit Committee – 24th April, 2019 Response to Scrutiny Task Group Recommendations Recommendation Programme Response Was the response successful? installation contract. It has subsequently been (design, installation and maintenance) from a novated to CBC. reputable cremator manufacturer, who is arguably the market leader.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Briefing NotesReport | 100 KB | DownloadRead as text |
Follow Audit, Compliance and Governance Committee at Cheltenham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | Local government act 1972 - exempt informationRESOLVED THAT: : - in accordance with Section 100A(4) Local Government Act 1972 the public be excluded from the meeti... | Decided | Open |
| 22 Apr 2026 | Internal Audit Plan 2026-27 and Internal Audit Charter and Mandate 2026-27RESOLVED THAT: - the proposed 2026-27 Internal Audit Plan and the Internal Audit Charter and Mandate 2026-27are appro... | Approved | Open |
| 22 Apr 2026 | Local government act 1972 - exempt informationRESOLVED THAT: - in accordance with Section 100A(4) Local Government Act 1972 the public be excluded from the meeting... | Decided | Open |
| 28 Jan 2026 | Local government act 1972 - exempt informationRESOLVED THAT: That in accordance with Section 100A(4) Local Government Act 1972, the public be excluded from the mee... | Decided | Open |
| 22 Oct 2025 | Local government act 1972 - exempt informationRESOLVED THAT: - in accordance with Section 100A(4) Local Government Act 1972 the public be excluded from the meeting... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.