RESOLVED THAT: The further development of be approved as part of the Authority’s Property Portfolio Strategy. An additional budget allocation of £515,000 be approved in accordance with the delegation provided by Council on 12 th December 2016. The tender received from EG Carter Construction to build the additional units be accepted with a total scheme cost not to exceed £1.1 million. Authority be delegated to the Head of Property Services, in consultation with the Borough Solicitor to: · Conclude the construction contract with EG Carter Construction. · Take all necessary steps and undertake all necessary procedures including the entering into of any legal arrangements or other documentation as may be required to implement or facility the development.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet Report – 10th September 2019 Cheltenham Enterprise Centre
Accountable member Cabinet Member for Finance, Councillor Rowena Hay
Accountable officer Head of Property & Asset Management, Dominic Stead
Ward(s) affected St. Peter’s
Key/Significant Yes Decision
Executive summary Cheltenham Borough Council owns the freehold of the Cheltenham Enterprise Centre. Planning consent was granted in 2003 to build 8 light industrial units (this was later revised to 7 units). The construction of the first phase was completed in 2007 and comprised of 4 units, from which the council receives a rental income. It is proposed to build the additional units (Phase II) as part of the council’s Property Portfolio Strategy as approved by Cabinet on the 6th December 2016.
Cabinet previously approved the Phase II development on the 11th July 2017. However, due to delays in tendering, the anticipated development cost has risen from £585,000 to £1,003,600 million, but a budget of £1.1m is requested to allow for contingencies.
Recommendations That Cabinet:
1. Approves the further development of Cheltenham Enterprise Centre as part of the Authority’s Property Portfolio Strategy.
2. Approves an additional budget allocation of £515,000 in accordance with the delegation provided by Council on 12th December 2016.
3. Accept the tender received from RG Carter Construction to build the additional units with a total scheme cost not to exceed £1.1 million.
4. Authority to be delegated to the Head of Property Services, in consultation with the Borough Solicitor to;
3.1Conclude the construction contract with RG Carter Construction.
3.2Take all necessary steps and undertake all necessary procedures including the entering into of any legal arrangements or other documentation as may be required to implement or facility the development.
Cheltenham Enterprise Centre Page 1 of 6 Last updated 06 September 2019 Financial implications At a meeting on 12th December 2016, the council agreed a budget allocation of £10m, to support development of the investment property portfolio. In order to maximise the contribution to the MTFS, it is proposed that the building of additional units at Enterprise Way be funded 100% from the capital receipts allocation. The Council approved a recommendation that any transaction under £5m, can be approved by Cabinet, in consultation with the Asset Management Working Group and the chairman of the overview and scrutiny committee.
With an estimated minimum of £10 per sq/ft rental, this build would give a return of 6.42% assuming a build cost of £1,003,600. The business case and net yield calculations can be found in appendix 2.
Contact officer: Andrew Knott, [email removed] 01242 264121
Legal implications The Authority has power to improve its land, and in doing so in this instance would be increasing the revenue from its assets. When the units are ready for letting, it is likely that the authority to approve the grant of the individual leases would lie within the existing delegation to the Cabinet Member.
The Council’s Contract Rules would have had to have been followed in selecting a contractor.
Contact officer: Donna Ruck, Solicitor [email protected] 01684 272696
HR implications No direct HR implications arising from this report. (including learning and organisational HR Manager – Operations Contact Officer development) [email removed] 01242 264355
Key risks Investment in property and carrying out development activities carries risks. Property rentals, values and occupancy rates typically fluctuate broadly in line with regional, national and global economies. It is also uncertain how Brexit will affect the UK economy in the short and long term. In the event of voids, the council will be liable for the service charge of the unit/s. The site is a former tannery, so there may be areas of undiscovered contamination.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.