Reallocation of Funds to Support High Street Improvement Phase 2

Approved Executive 1 paper

Cabinet approved this item on Tuesday 11 February 2020. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

RESOLVED THAT: the spending of £161,402 on the allotment improvement works identified in this report be approved, and that the remaining £400,000 be reallocated towards the Cheltenham High Street phase 2 improvements.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Cabinet

Cheltenham Borough Council Cabinet – 11th February 2020 Reallocation of Funds to Support High Street Improvement Phase2

Accountable members Councillor Rowena Hay, Cabinet Member Finance

Accountable officers Tracey Crews – Director of Planning

Ward(s) affected All

Key Decision Yes

Executive summary In the budget outturn report that was considered by Council on 22nd July 2019, the Council made an “in principle” decision that £400,000 be reallocated to the High Street fund to support delivery of phase 2 of the Cheltenham High Street improvement plans, subject to the production of this report.

This report outlines the current situation with regard to a portion of the Midwinter capital receipt retained by the Council in 2012 to make provision for additional allotments, and allotment improvements following the sale of former allotment land at Midwinter. It summarises the current situation with regard to allotment demand, and outlines what improvements need to be made to existing sites in line with the Small Holdings and Allotment Act 1908 in order to reallocate the remaining funds.

Recommendations 1. To approve the spending of £161,402 on the allotment improvement works identified in this report. To reallocate the remaining £400,000 towards the Cheltenham High Street phase 2 improvements.

Financial implications The report sets out the change in capital funding that is now set out in the budget for 2020/21. The council need to be aware that should the demand for allotments increase in the future then we will be required to provide adequate provision. This should be covered by the monies set aside for allotment improvements within section 4.1 on this report.

Contact officer: Andrew Knott

[email removed], Tel: 01242 264121

$fshugp3d Page 1 of 6 Last updated 31 January 2020 Legal implications The duties of the Authority regarding the use of expenditure of a capital receipt from the sale of statutory allotment land and the duty to provide sufficient allotments is contained in S32(7) and S23(1) of the Small Holdings and Allotments Act 1908, a summary of which is set out in section 2 of this report. Provided that the Authority is satisfied that it has discharged its duties, the Authority may use the remaining capital receipt for matters on which capital money may be spent.

Should the demand for allotments increase, the Council will be required to provide adequate provision.

Contact officer: Donna Ruck

[email protected] 01684 272696

HR implications None (including learning and organisational Contact officer: [email removed] 01242 264355 development)

Key risks See appendix 1 of this report.

Corporate and Reallocation of funds will directly contribute towards the Council’s Key community plan Priority: “Continuing the revitalisation and improvement of our vibrant town Implications centre and public spaces.”

Environmental and Regeneration of the town centre will contribute towards the Council’s travel climate change Plan, and “Habitat Cheltenham” objectives by enhancing biodiversity and implications creating wildlife corridors.

Property/Asset Allotment site improvement works identified in this report would be Implications scheduled to take place in financial year 2020/2021

Contact officer: [email protected] 01242 264151

$fshugp3d Page 2 of 6 Last updated 31 January 2020 1. Background 1.1 In 2012 the Council ring-fenced £600,000 from the proceeds of the Midwinter sale for the provision of new allotments to meet potential future demand. Elmfield Playing Field, situated next to Midwinter Allotment site, was identified as the location where new allotments would be created if demand led to the need for additional allotment provision within the Borough.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Reallocation of Funds to Support High Street Improvement Phase 2Report 357 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
SF
Sarah FarooqiOfficer, present
HM
Harry MayoOfficer, present
SJ
Councillor Steve Jordan Leader of the CouncilCommittee Member, present
FC
Councillor Flo Clucas Cabinet Member Healthy LifestylesCommittee Member, present
CC
Councillor Chris Coleman Cabinet Member Clean and Green EnvironmentCommittee Member, present
RH
Councillor Rowena Hay Cabinet Member FinanceCommittee Member, present
AH
Councillor Alex Hegenbarth Cabinet Member Corporate ServicesCommittee Member, present
PJ
Councillor Peter Jeffries Cabinet Member HousingCommittee Member, present
AM
Councillor Andrew McKinlay Cabinet Member Development and SafetyCommittee Member, present
MS
Mark SheldonOfficer, expected
MR
Mike RedmanOfficer, expected
BT
Beverly ThomasOfficer, expected

More from Cheltenham Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... Noted Open
15 Sep 2026 Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... Approved Open
15 Sep 2026 Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... Decided Open
15 Sep 2026 Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... Agreed Open
15 Sep 2026 Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies