Cheltenham Borough Council
Cabinet, Tuesday 3 March 2020 at 6.00pm

Cyber Central Procurement/Route to market

Approved Executive 2 papers

Cabinet approved this item on Tuesday 3 March 2020. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED THAT 1. the procurement route to market as set out below be approved : a. The Council seek a delivery partner with skills and experience of a Master Developer; b. The delivery partner is secured for all of the Council’s ownership and it is intended there is no separation of the commercial and residential elements of the proposed scheme; c. The structure of the agreement is likely to be delivered through a Development Agreement or a Joint Venture, to be defined during dialogue with bidders; d. Due to the Council’s objectives and need to retain a degree of control over the development, the opportunity will need to be procured following EU procurement rules and it is recommended the Competitive Dialogue procedure is followed; and e. Flexibility is built into the procurement and contract in order to allow for delivery over a lengthy time period, where there will be changes in policies, legislation and market conditions. 2. the draft timetable for procurement noting key stages and time allowed be noted. 3. Authority be delegated to the Managing Director Place and Growth, in consultation with the Cabinet Member Development & Safety and Executive Director Finance and Assets to make key decisions through the dialogue and shortlisting stages of the procurement process. The final decision on the preferred bidder will be a decision of Cabinet prior to any contract close.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Cabinet

Cheltenham Borough Council Cabinet – 3 March 20120 Cyber Central – Route to Market

Accountable Councillor Andrew McKinlay, Cabinet Member Development and Safety member

Accountable Tim Atkins – Managing Director Place and Growth officer

Ward(s) affected All (site is in Hester’s Way and Springbank)

Key/Significant Yes Decision

Executive This report seeks authority for the Council to start its search for a development summary partner to bring forward the land acquired at West Cheltenham for development. The vision is for the site to deliver a campus that integrates high-tech workplaces with leading academic facilities, exemplar homes and leisure uses. The campus once fully developed will deliver over 7,000 new jobs across 2m sq ft of commercial space and up to 3,000 homes.

Since acquiring the land, the Council has been engaged in an early exercise to identify, explore and review options for a range of legal and transactional delivery structures. This work has included identifying the key project objectives, understanding an acceptable level of risk and return (both delivery and development) and explored revenue vs capital receipt opportunities.

In advance of the formal procurement process, the Council has been engaged in a series of soft market testing interviews relating to Cyber Central. These have sought feedback on the approach and procurement process from a range of key operators, investors and developers in the market. This feedback has been used in formulating the delivery strategy for the project as recommended below.

A high level ambitious programme has been established in seeking a development partner. Assuming a start date in mid-April it is estimated that the Council will have selected a preferred bidder by late 2020/2021.

As the vision requires a unique and high standard deliverable, the council seeks to retain a reasonable level of input in shaping this important extension to Cheltenham, this is supported by its investment in the land and further financial commitment to support housing delivery. The report proposes to follow an EU compliant competitive dialogue process to explore how the ambition and financial investment can be best utilised. This is a resource intensive process and carries a considerable level of risk, however, if the ambitious objectives set out the Council’s Place and Corporate strategies around growth and cyber excellence are to be achieved, we are advised this is the best route to market.

$xfxp2zly Page 1 of 10 Last updated 02 March 2020 Recommendation That Cabinet: s 1. Approves the procurement route to market as set out below:

a. The Council seek a delivery partner with skills and experience of a Master Developer;

b. The delivery partner is secured for all of the Council’s ownership and it is intended there is no separation of the commercial and residential elements of the proposed scheme;

c. The structure of the agreement is likely to be delivered through a Development Agreement or a Joint Venture, to be defined during dialogue with bidders;

d. Due to the Council’s objectives and need to retain a degree of control over the development, the opportunity will need to be procured following EU procurement rules and it is recommended the Competitive Dialogue procedure is followed; and

e. Flexibility is built into the procurement and contract in order to allow for delivery over a lengthy time period, where there will be changes in policies, legislation and market conditions.

2. Considers the draft timetable for procurement noting key stages and time allowed.

3. Delegates authority to the Managing Director Place and Growth, in consultation with the Cabinet Member Development & Safety and Executive Director Finance and Assets to make key decisions through the dialogue and shortlisting stages of the procurement process. The final decision on the preferred bidder will be a decision of Cabinet prior to any contract close.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2020_03_03_Cyber_Central_Appendix_2Appendix 1 MB Download
PDF
Cyber Central Procurement/Route to marketReport 340 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 14 attended
SF
Sarah FarooqiOfficer, in attendance
HM
Harry MayoOfficer, expected
SJ
Councillor Steve Jordan Leader of the CouncilCommittee Member, present
FC
Councillor Flo Clucas Cabinet Member Healthy LifestylesCommittee Member, apologies
CC
Councillor Chris Coleman Cabinet Member Clean and Green EnvironmentCommittee Member, present
RH
Councillor Rowena Hay Cabinet Member FinanceCommittee Member, present
AH
Councillor Alex Hegenbarth Cabinet Member Corporate ServicesCommittee Member, present
PJ
Councillor Peter Jeffries Cabinet Member HousingCommittee Member, present
AM
Councillor Andrew McKinlay Cabinet Member Development and SafetyCommittee Member, present
MS
Mark SheldonOfficer, expected
MR
Mike RedmanOfficer, expected
BT
Beverly ThomasOfficer, expected

All 14 on the meeting page

On this subject at Cheltenham

Search all
  1. Cyber Central Procurement/Route to marketThis decision
  2. Cyber Central Garden Community - Draft Supplementary Planning GuidanceApproved
  3. West Cheltenham/Cyber Central Update ReportApproved

More from Cheltenham Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... Noted Open
15 Sep 2026 Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... Approved Open
15 Sep 2026 Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... Decided Open
15 Sep 2026 Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... Agreed Open
15 Sep 2026 Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. Approved Open