RESOLVED THAT: 1. In advance of planning permission being considered by the Planning Committee on (anticipated 18 August 2022), and noting the costs and risks set out in this report, Cheltenham Borough Council agrees to lead the delivery of an Ice Rink in Cheltenham for the 2022 Christmas period; 2. A total potential financial commitment as set out in section 2.22 of this report alongside the income targets be approved; 3. It be noted that officers are progressing procurement, and that the authority to appoint a contractor to provide the Ice Rink be delegated to the Director of Communities and Economic Development, ... view the full minutes text for item 8.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 12th July 2022 Cheltenham Christmas Ice Rink
Accountable member Cllr Max Wilkinson, Cabinet Member for Economic Development, Culture, Tourism and Wellbeing
Accountable officer Tracey Birkinshaw, Director of Communities and Economic Development
Ward(s) affected All
Key/Significant Yes Decision
Executive summary Cheltenham Borough Council led the delivery of the town’s Christmas ice rink in 2021. It welcomed over 43,000 skaters, making a significant contribution to Cheltenham’s festive offering and providing a much needed boost to town centre footfall and trading after such a challenging period. Spending in the town from the ice rink and Christmas Market totalled £14m. The ice rink itself covered its costs and made a small £5k surplus. It received significant positive public support and the Marketing Cheltenham Team have been working on a small number of areas identified for improvement arising from the 2022 installation, reported to Cabinet on 1st March 2022. This report summarises this at section 6, but does not repeat the earlier report,
The focus of this report is the financial case and the decision making for this.
In March, Cabinet noted the significant success of the ice rick and agreed that the Council should seek to provide a further temporary ice rink in Cheltenham for the 2022 Christmas period. This agreement was subject to:
a) a fully costed business case; b) securing the necessary planning consents; c) procuring an operator; d) the final commitment being brought back to Cabinet for approval (this report).
This paper therefore sets out the costed business case and financial implications for the ice rink.
Recommendations That Cabinet
1. Approves, in advance of planning permission being considered by the Planning Committee on (anticipated 18 August 2022), and noting the costs and risks set out in this report, for Cheltenham Borough Council to lead the delivery of an Ice Rink in Cheltenham for the 2022 Christmas period;
2. Approves a total potential financial commitment as set out in section 2.22 of this report alongside the income targets;
$aag0mwmn.docx Page 1 of 14 Last updated 01 July 2022 3. Notes that officers are progressing procurement and delegates appointment of a contractor to provide the Ice Rink to the Director of Communities and Economic Development, including agreeing the terms of the contract and entrance fees in consultation with Director of Finance and Assets and the Cabinet Member for Economic Development, Culture, Tourism and Wellbeing.
$aag0mwmn.docx Page 2 of 14 Last updated 01 July 2022 Financial implications CBC will be required to enter into a contract with an ice rink operator, whilst incurring other direct costs to support the successful delivery of the event. This will mean a potential total financial commitment of up to £350,000.
In the 2022/23 budget, a sum of £350,000 has been identified in Marketing Cheltenham’s operational budget for the creation/contribution towards an event in Cheltenham in 2022/23. There is also an income target of £395,000 for the event which generates a net contribution of £45,000 to support the wider activities of Marketing Cheltenham during the year.
The budget projections were generated from event information from 2021. Ongoing financial monitoring support will be provided to project officers to ensure that timely and informed decisions can be made to maximise the financial success of the event.
Contact officer: Gemma Bell, Director of Finance and Assets, [email protected]
Legal implications Section 145 of the Local Government Act 1972 grants a wide power to local authorities to provide entertainment. The powers also permits the charging of admission fees and the setting aside of areas of parks or ‘pleasure grounds’ for that purpose.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.