RESOLVED THAT: 1. Council be recommended to approve the Heating and Energy Policy included in Appendix 4; 2. Responsibility for monitoring the implementation of the Policy be delegated to the Director of Climate Change, in consultation with the Director of Finance and Assets (Deputy S151 Officer).
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Cheltenham Borough Council Cabinet – 13th September 2022 Heating and Energy Policy
Accountable member Cllr. Alisha Lewis, Cabinet Member Climate Emergency
Accountable officer Gemma Bell, Director of Finance and Assets (Deputy S151 Officer)
Mike Redman, Director of Climate Change and Place Services
Ward(s) affected All
Key/Significant Yes Decision
Executive summary The Heating and Energy Policy has been written as an addendum to our ‘Climate Emergency Action Plan’ to specifically expand on policies and practices in respect of Energy, which comprises a significant portion of our current carbon and financial footprints
This policy sets out the key commitments which will be applied to all energy activity within the Council and Council-owned Properties. Our key objective to manage and reduce our energy usage within all Council buildings, particularly those that are part of our operational portfolio.
Delivery of the objectives stated in this policy will be supported through the development and implementation of an energy action plan. This will include:
Communications Measuring and monitoring arrangements Energy and emissions reporting A sustainable procurement statement Building refurbishment guidelines Building energy performance review There has never been a better time to review and reduce our energy consumption; the coming winter could well be the most expensive on record. By supporting staff to reduce consumption at work, we hope to introduce a wider culture of energy saving across the borough with benefits for financial, social and environmental well-being.
Recommendations It is recommended that Cabinet:
1. Recommend to Council the approval of the Heating and Energy Policy included in Appendix 4.
2. Delegate to the Director of Climate Change, in consultation with the Director of Finance and Assets (Deputy s151 Officer) responsibility for monitoring the implementation of the Policy.
$0223gqgc.docx Page 1 of 6 Last updated 05 September 2022 Financial implications Rising energy costs and the uncertainty over the forecast cost of energy in 2022/23 mean the council are currently facing an unbudgeted pressure of almost £1m to operate the buildings in our portfolio. Work is ongoing to reduce our energy usage and make our buildings more energy efficient and this policy outlines the principles which will be underpin this work.
For the most part this policy will mean a financial saving for the Council but may require some investment on “an invest to save” basis through the Climate Investment Fund. Funding bids will be supported by robust business cases which will be monitored as part of the monitoring arrangements for the strategy.
Contact officer: Gemma Bell, Director of Finance and Assets, [email protected]
Legal implications This report is to provide an addendum: Heating and Energy Policy, to the existing Council’s Climate Emergency Action Plan: Pathway to Net Zero
The overarching legislative context of the Council’s Climate Emergency Action Plan: Pathway to Net Zero, is the Climate Change Act 2008. This Act places a legal duty on central government to set legally binding targets to reduce UK greenhouse gas emissions to net-zero by 2050.The UK legal framework on climate change is also shaped by both case law and international agreements.
Where specific projects or actions are required going forward to support the Climate Emergency Action Plan and ‘Cheltenham’s Green Deal’ (the Climate Change Investment Strategy) further legal advice and support should be sought.
The Council must ensure that any decisions taken must be in accordance with the Council’s Constitution and Financial Rules, particularly in regard to decision making, implementation of strategy/action plans and any funding requirements
Contact officer: One Legal, [email removed]
HR implications No material considerations. (including learning and organisational Contact officer: [email removed] development)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.