RESOLVED THAT: 1. the update on the M5 Junction 10 process is noted; 2. authority is delegated to the Director Communities & Economic Development to: a. respond formally on behalf of Cheltenham Borough Council (as statutory consultee) through our appointed consultants AtkinsRealis to the DCO process in consultation with Cabinet Member Customer & Regulatory Services . b. make representations at the DCO hearings and meetings (either directly or through Cheltenham Borough Council designated officer or through our appointed consultants AtkinsRealis) concerning the M5 Junction 10 project in accordance with the Council’s responses (as statutory consultee) to the consultation.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
This report provides an update on the M5 Junction 10 Improvements Scheme Development Consent Order (DCO) process, which is being promoted by Gloucestershire County Council (GCC) as scheme promoter. GCC have submitted a DCO to the Secretary of State for independent examination.
Consultants AtkinsRealis are appointed jointly on behalf of the planning authorities of Cheltenham and Tewkesbury and the Highways Authority of Gloucestershire County Council (the Joint Councils) to support on the technical specialisms relating to the DCO application.
This report seeks Cabinet authorisation to delegate authority to the appropriate officer to represent the Council through the DCO process in respect of M5 Junction 10 with the support of our appointed consultants. The delegation is required to respond to what will be an ongoing and iterative process.
Recommendations: That Cabinet:
1. notes the update on the M5 Junction 10 process, and
2. delegates authority to the Director Communities & Economic Development to:
Page 1 of 8 Report for Cabinet, 13th February 2024
a. respond formally on behalf of Cheltenham Borough Council (as statutory consultee) through our appointed consultants AtkinsRealis to the DCO process in consultation with Cabinet Member Customer & Regulatory Services. b. make representations at the DCO hearings and meetings (either directly or through Cheltenham Borough Council designated officer or through our appointed consultants AtkinsRealis) concerning the M5 Junction 10 project in accordance with the Council’s responses (as statutory consultee) to the consultation.
1. Implications
1.1Financial, Property and Asset implications
Due to the technical nature of the M5 Junction 10 project, Cheltenham has aligned with the local planning authority of Tewkesbury Borough and the Highways Authority of Gloucestershire County Council to engage consultants to support officers on the technical documentation. To date this has been funded through a grant from Homes England. Ongoing engagement is taking place to seek commitment for this funding through the remaining DCO process.
The consultants AtkinsRealis have been procured utilising Gloucestershire County Council agreed procurement framework. However, acknowledging that Homes England funding at the time of writing remains unconfirmed, the commitments related to this are £47,664.75 across 2023/24 and 2024/25. If the Homes England Funding is unsuccessful further review will be required and a further budget decision may be required in year.
The use of Statements of Common Ground is an integral part of the Development Consent Order process. There will be an expectation from the examining authority that the local authorities will engage in the process. The Statement of Common Ground is designed to clarify which issues are agreed and which issues remain in dispute between the promoter of the Development Consent Order and the local authorities.
As stated in the report, the Council will also need to input into the Local Impact Reports and, in addition, may be required/expected to input into other matters throughout the process including: written representations; participation at hearings, meetings and site visits; responding to written questions or requests for further information; and commenting on other interested parties representations and submissions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.