CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cheltenham Borough Council
Cabinet, Tuesday 11 June 2024 at 6.00pm

Energy efficiency proposals for Leisure@Cheltenham

Approved Executive 1 paper

Cabinet approved this item on Tuesday 11 June 2024. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED that: 1. a capital investment of £264,500 to replace the existing lighting system in the leisure centre with LED technology is approved; 2. a capital investment of £83,750 from the Green Investment Fund to install pool covers across the building is approved; 3. authority is delegated to the Director of Finance and Assets (Deputy s151 Officer) to procure and award the contract for the installation of the equipment and monitor the implementation.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Cabinet

Executive summary

In February 2022, Full Council approved a £10m Green Investment Fund to support initiatives which would deliver a return and contribute to reducing the carbon footprint of the town. Detailed savings proposals and a full business case for these capital investments were presented to the Green Investment Board on 1 March 2024. The business case was approved for £83,750 of investment into swimming pool heat retention covers and it was also recommended that the LED lighting investment be made despite not meeting the 3% return criteria. This is because the lighting on the site is at the end of life and requires replacement as part of the planned maintenance programme. The LED option provides both financial and carbon improvements when compared to the existing infrastructure. The business case shows that both investments will reduce energy usage sufficiently to cover the annual cost, with the pool covers having a return on investment of 16.4%.

The conditions of the Green Investment funding require Cabinet ratification of the decision made by the Green Investment Board which is reflected in the recommendations below.

Page 1 of 7 Report for 11 June 2024

Recommendations: that Cabinet/Council:

1. Approves a capital investment of £264,500 to replace the existing lighting system in the leisure centre with LED technology;

2. Approves a capital investment of £83,750 from the Green Investment Fund to install pool covers across the building; and

3. Delegates authority to the Director of Finance and Assets (Deputy s151 Officer) to procure and award the contract for the installation of the equipment and monitor the implementation.

1. Implications

Financial implications

The 2024/25 budget includes an energy budget of £1.6m which represents is a 60% increase since 2021/22. This is driven by the inflationary increases in energy costs felt through 2022/23 and almost half of this energy is used at Leisure@ Cheltenham. Any reduction in energy usage will start to reduce the pressure from these areas of the revenue budget.

Signed off by: Gemma Bell, Director of Finance and Assets, 01242 264124

The procurement of these services will be above the current procurement threshold. Officers will undertake a compliant procurement exercise in accordance with the Public Contract Regulations 2015 and will engage with One Legal and Publica during this process.

Signed off by: One Legal, [email removed]

1.3HR implications

There are no direct implications from the recommendations.

Signed off by: Shona Corbett, HR Business Partner, [email protected]

1.4Environmental and climate change implications

The proposed investment in improved systems for controlling operational energy use will help to lower our consumption, delivering both financial and carbon savings. As outlined within the Climate Action Plan, these works underpins an essential stage in the decarbonisation plan, for the highest emitting asset within our property portfolio, which dominates our scope 1&2 emission performance.

Page 2 of 7 Report for 11 June 2024

Signed off by: Maizy McCann, Climate Emergency Officer, [email protected]

1.5Property/asset implications

The replacement of the LED lighting is an opportunity to use the planned maintenance programme to proactively reduce the carbon footprint of the site.

Signed off by: Gemma Bell, Director of Finance and Assets, 01242 264124

1.6Corporate policy framework implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Energy efficiency proposals for Leisure@CheltenhamReport 253 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 23 attended
VA
Councillor Victoria AtherstoneCommittee Member, present
FC
Councillor Flo ClucasCommittee Member, apologies
CM
Cabinet Member Planning & Building ControlCommittee Member, present
ID
Councillor Iain DobieCommittee Member, present
RH
Councillor Rowena HayCommittee Member, present
MH
Councillor Martin HorwoodCommittee Member, present
PJ
Councillor Peter JeffriesCommittee Member, present
AL
Councillor Alisha LewisCommittee Member, present
IT
Councillor Izaac TailfordCommittee Member, present
CH
Claire HughesOfficer, in attendance
GE
Gareth EdmundsonOfficer, in attendance
PJ
Paul JonesOfficer, expected

All 23 on the meeting page

More from Cheltenham Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... Noted Open
15 Sep 2026 Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... Approved Open
15 Sep 2026 Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... Decided Open
15 Sep 2026 Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... Agreed Open
15 Sep 2026 Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies