It was agreed that an update with these new assessments would be issued following the meeting. - Smoke and CO2 alarms are described as components within the report. All are currently up-to-date and are either wired or battery operated. - Hopefully by the next meeting an updated performance report will be provided based on a new dashboard produced automatically by the system. This should be much easier to read and understand. This report should be created at the touch of a button to ensure we have accessible, up-to-date information.
Word for word from the decision Cheltenham published for this meeting.Source: democracy.cheltenham.gov.uk
Compliance update for Cabinet Housing Committee 12 June 2025
As per the verbal update given at committee on 11 June the current position in relation to asbestos and fire actions is as follows:
Asbestos At end of May 2025 we were reporting 33 overdue asbestos surveys, all of which relate to communal areas.
Of those 33, 11 have been completed, 10 are being completed today (12 June) and the remaining will be completed on Friday 13 June.
Therefore, we will be in a fully compliant position by the end of this week.
Fire At the end of May we were reporting 93 outstanding fire actions of which 17 were high risk1. Since preparing the report we have visited all properties where a high-risk action had been identified and are able to confirm that following a review these have now been recategorized as either medium or low risk.
The position as of 12 June is that we now have 62 outstanding fire actions of which none are high risk.
26 actions relate to fire doors 20 actions relate to the installation of new windows 16 actions relate to compartmentation
Doors: We now have either installation or delivery dates for all outstanding doors
Windows: A manufacturer has now been identified. There is a 12 week lead in time for manufacturing, following which the windows will be installed by one of our existing contractors. A letter has been drafted and will be issued as appropriate to affected residents informing them of the works.
Compartmentation: 9 actions require a specialist contractor who are currently being commissioned, the remaining actions will be completed in house.
1 These actions had been categorized as high risk due to the passage of time and the fact that no site
visit had taken place as opposed to the actual risk presented
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.