Cheltenham Borough Council
Cabinet, Tuesday 15 September 2026 at 6.00pm

Suitable Alternative Natural Greenspace (SANGs) Action Plan

Approved Executive 4 papers

AI summaryCheltenham Cabinet approved a plan to upgrade three green spaces as alternatives to the Cotswold Beechwoods SAC, diverting visitors away from the protected woodland to meet the council's legal duties under the Habitats Regulations 2017.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet approved the Focused Implementation Plan for Measures to Avoid Recreational Impacts at the Cotswold Beechwoods SAC
Money£839,751Estimated cost including 20-year maintenance and contingency
What happens nextInfrastructure works at three sitesPriors Farm, Benhall Open Space and Pittville Park (West) to be enhanced
Who it affectsResidents and developers in CheltenhamNew housing must contribute to SANG funding; existing green spaces will be upgraded

What was decided

Cabinet approved the Focused Implementation Plan for Measures to Avoid Recreational Impacts at the Cotswold Beechwoods SAC. Report P8

Cabinet delegated authority to the Director of Planning and Building Control, in consultation with the Cabinet Member for Planning and Building Control, to review and make minor amendments to the Plan as required. Report P9

Cabinet endorsed collaboration with partner authorities and Natural England to monitor and review the effectiveness of mitigation measures. Report P10

Why

The Council is legally required under the Conservation of Habitats and Species Regulations 2017 to ensure that development does not adversely impact the integrity of the Cotswold Beechwoods SAC. The Focused Implementation Plan provides a structured approach to meeting these obligations. Report 3.1

A pragmatic approach has been adopted tailored to Cheltenham's specific circumstances, recognising the context of Local Government Reorganisation and the challenges of acquiring new land in an urban area. Report 3.2, 4.1

Enhancing existing green spaces rather than providing new SANG allows faster, more cost-effective delivery, avoids land acquisition complexity and brings positive benefits to existing and new communities. Report 4.3

What happens next

Developer contributions will finance the capital infrastructure improvements at the three shortlisted green spaces and associated monitoring requirements. Report P13

Monitoring will include visitor surveys, ecological assessments, infrastructure audits and financial tracking. Annual Monitoring Reports and reviews of the Plan every five years will support adaptive management. Report P35

The Council may commission external specialists for technical monitoring tasks and will continue collaborative working with Natural England and partner authorities. Report P35, P33

The money

  • £480 per dwelling Developer contribution rate before 1st April 2026 Report P15
  • £550.46 per dwelling Developer contribution rate for applications received on or after 1st April 2026 Report P15
  • £200,000 Current SANG income held by Cheltenham Borough Council Report P76
  • £559,280 Projected SANG income over the JCS/Cheltenham Plan period to 2031 Report P76
  • £779,172 Total infrastructure costs excluding contingency and with 20-year maintenance Report 6.3, 7.3
  • £839,751 Total infrastructure costs including contingency and 20-year maintenance Report P17, 7.3
  • £1,321,652 Estimated cost with 80-year in-perpetuity maintenance excluding contingency Report P16, 7.2
  • £1,261,073 Estimated cost with 80-year in-perpetuity maintenance including contingency Report 7.2
  • £11,650 Annual revenue budget based on 20-year maintenance costs Report P17
  • £30,320 Annual capital budget based on 20-year maintenance costs Report P17

Options considered

  • Rejected: Option 1: Apply Natural England guidelines with 80-year in-perpetuity maintenance. This would mean limited infrastructure with potentially lesser impact as funding would be held in reserves for long-term maintenance rather than upfront delivery. Report P89
  • Chosen: Option 2: Continual monitoring with adjustment for caution and buffering. Built into the Focused Implementation Plan as presented. Report P90, 8.2
  • Chosen: Option 3: Investigate alternative funding sources such as external grants, CIL and Council Capital funding. Built into the Focused Implementation Plan to allow more SANG contributions to be invested in enhancement and maintenance. Report P91, 8.2

Implications

  • Legal: The Council is legally obliged under the Conservation of Habitats and Species Regulations 2017 to ensure that development does not adversely affect the integrity of the SAC. Failure to have a suitable plan risks non-compliance and legal challenge. Report P20, P109
  • Financial: Developer contributions at the agreed rate may be insufficient to meet 80-year in-perpetuity maintenance costs, creating a potential funding gap. A 20-year capping approach is recommended as more pragmatic. Report P15, P16, P17
  • Financial: The current SANG income of approximately £200,000 is projected to rise to £559,280 by 2031. The full infrastructure costs excluding contingency are estimated at £779,172, potentially leaving a shortfall. Report P76, 6.3
  • Financial: Viability challenges on planning applications cannot be resolved by reducing Habitat Regulations mitigation requirements, meaning SANG costs are non-negotiable in the planning balance. Report 7.4
  • Environmental: The plan aligns with the Council's Climate Emergency Action Plan and supports biodiversity protection through habitat management, visitor engagement and alternative green space provision. Report P24
  • Risk: Without sufficient funding there is a risk of non-compliance with legal obligations and ecological degradation of the SAC. Report P83
  • Other: Local Government Reorganisation may result in the successor Gloucestershire Council wishing to adopt a broader, county-wide approach to SANG delivery and management. Report P21, 3.2

Who and where

  • Cheltenham Borough Council, as competent authority under the Habitats Regulations Report P1
  • Partner authorities: Stroud District, Tewkesbury Borough, Gloucester City and Cotswold District Councils Report P34
  • Natural England, providing strategic oversight and ecological expertise Report P33
  • Residents of Cheltenham and visitors to green spaces at Priors Farm, Benhall Open Space and Pittville Park (West) Report P58, P59, P60
  • Developers making residential planning applications in Cheltenham Report P15, P76

Timeline

  • 2019: Visitor survey conducted to define the Zone of Influence of 15.4km Report 2.1
  • 2nd April 2024: Cabinet adopted the Cotswolds Beechwoods SAC Recreation Mitigation Strategy Report P1, 2.1
  • 1st April 2026: Developer contribution rate increased from £480 to £550.46 per dwelling Report P15, P74
  • 15th September 2026: Cabinet approved the Focused Implementation Plan
  • 2031: End of JCS/Cheltenham Plan period; projected SANG income of £559,280 by this date Report P76
  • Every five years: Reviews of the Focused Implementation Plan Report P35
  • Minimum 80 years: Long-term SANG management and monitoring obligation under the Habitats Regulations Report P4, P83

Plain English for the jargon

  • SAC: Special Area of Conservation; a European designated site of ecological importance protected under the Conservation of Habitats and Species Regulations 2017
  • SANG: Suitable Alternative Natural Greenspace; land secured and managed to mitigate impacts of new residential development on protected natural habitats
  • SAMM: Strategic Access Management and Monitoring; measures at the SAC itself to manage visitor access
  • Zone of Influence (ZoI): The geographical area from which visitors to the SAC originate, defined as 15.4km in this context
  • S106: Section 106 of the Town and Country Planning Act 1990; planning obligations attached to planning permissions
  • JCS: Gloucester, Cheltenham and Tewkesbury Joint Core Strategy
  • CIL: Community Infrastructure Levy; a planning charge used to fund infrastructure improvements
  • Biodiversity Net Gain: An approach to development that leaves biodiversity in a better state than before
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

RESOLVED THAT: 1. the Focused Implementation Plan for Measures to Avoid Recreational Impacts at the Cotswold Beechwoods SAC is approved; 2. authority is delegated to the Director of Planning and Building Control, in consultation with the Cabinet Member for Planning and Building Control, to review and make minor amendments to the Plan as required; 3. the collaboration with partner authorities and Natural England to monitor and review the effectiveness of mitigation measures is endorsed.
Word for word from the decision Cheltenham published for this meeting. Source: democracy.cheltenham.gov.uk

Follow this further

Built from Cheltenham's papers

What the report saysPro

Report to Cabinet

Executive summary

The Cotswold Beechwoods Special Area of Conservation (SAC) is a European designated site of ecological importance, threatened by increasing recreational pressure due to population growth and development. Cheltenham Borough Council, in partnership with neighbouring authorities and Natural England, has developed a Recreation Mitigation Strategy to ensure compliance with the Conservation of Habitats and Species Regulations 2017 (as amended). This helps fulfil the council’s legal duty as a ‘competent authority’. This provides for both Strategic Access Management and Monitoring (SAMMs) at the SAC itself; and to deflect access away from the SAC the provisions of Suitable Natural Alternative Greenspace (‘SANG’) or other infrastructure projects (away from the SAC), such as improvements to existing greenspace sites. This was adopted by Cabinet on 2nd April 2024 with a commitment to bring forward an action plan for Cheltenham Borough. Report to Cabinet, 15 September 2026

This report, in respect of the SANG/other Infrastructure Projects element of the Recreation Mitigation Strategy, seeks Cabinet approval for a Cheltenham Focused Implementation Plan – an action plan which outlines infrastructure project improvements to three existing public green spaces. Suitable Alternative Natural Green Space (SANG) seeks to divert visitors away from sensitive sites, in this case, the Cotswolds Beechwoods SAC.

To support the development of this plan, Cheltenham Borough Council appointed Lepus Consulting, a specialist environmental consultancy, to work in collaboration with the Council’s Green Space Team. This partnership ensured the plan is both ecologically robust and locally deliverable. Engagement on this Focused Implementation Plan has taken place with Natural England.

Suitable Alternative Natural Greenspace (SANG) is land secured and managed to mitigate the impacts of new residential development on protected natural habitats. While SANG is typically secured for a minimum period of 80 years, work undertaken with our consultants, Lepus, has examined the practical implications of delivering and managing this long-term commitment within the local context.

As set out in this report, a pragmatic approach is recommended. This involves adopting a 20-year action plan that provides a realistic and deliverable framework for implementation in respect of the mitigation required and ensuring that communities can see and experience tangible benefits from investment and management interventions during that period. The proposed approach reflects Cheltenham's specific circumstances, available funding, and the need to deliver achievable solutions that remain consistent with the principles of SANG and the guidance established by Natural England.

The report has also been prepared in the context of Local Government Reorganisation. It recognises that any future successor authority may wish to review and adopt a broader, more integrated approach to the long-term management of SANG and associated environmental mitigation measures.

Recommendations: That Cabinet:

1. approves the Focused Implementation Plan for Measures to Avoid Recreational Impacts at the Cotswold Beechwoods SAC;

2. delegates authority to the Director of Planning and Building Control, in consultation with the Cabinet Member for Planning and Building Control, to review and make minor amendments to the Plan as required;

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Climate Impact Assessment ToolAppendix 3 153 KB Download
PDF
Shortlisted Sites for Infrastructure ImprovementsAppendix 4 155 KB Download
PDF
Focused Implementation Plan Measures to Avoid Recreational Impacts at the Cotswold Beechwoods Special Area of Conservation (SAC)Appendix 5 9.2 MB Download
PDF
Suitable Alternative Natural Greenspace (SANGs) Action PlanReport 261 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 13 attended
PB
Councillor Paul Baker Cabinet Member Planning & Building ControlCommittee Member, present
FC
Councillor Flo Clucas Cabinet Member Housing & Customer ServicesCommittee Member, apologies
SH
Councillor Steve Harvey Cabinet Member Waste and Recycling and Parks, Gardens and Green Open SpaceCommittee Member, present
RH
Councillor Rowena Hay Leader of the CouncilCommittee Member, apologies
JJ
Councillor Jamie Jamieson Cabinet Member Safety & CommunitiesCommittee Member, present
PJ
Councillor Peter Jeffries Deputy Leader & Cabinet Member Finance and AssetsCommittee Member, present
AL
Councillor Alisha Lewis Cabinet Member Major Developments & Housing DeliveryCommittee Member, present
RP
Councillor Richard Pineger Cabinet Member Climate EmergencyCommittee Member, present
IT
Councillor Izaac Tailford Cabinet Member for Economic Development, Wellbeing, Culture and Public RealmCommittee Member, present
AT
Adele TaylorOfficer, in attendance
JW
Jon WhitlockOfficer, in attendance
HM
Helen MoleOfficer, in attendance

All 13 on the meeting page

More from Cheltenham Cabinet

All decisions
MeetingDecisionOutcome
15 Sep 2026 General Fund and Housing Revenue Account Budget Monitoring Report Q1 2026-27RESOLVED THAT: 1. the contents of the report, including the forecast revenue and capital programme monitoring positio... Noted Open
15 Sep 2026 Sandy Lane Playing Field - Memorandum of UnderstandingRESOLVED THAT: 1. the council entering into a non-binding Memorandum of Understanding (“MOU”) with Patesians Sports a... Approved Open
15 Sep 2026 Disposal of Public Open Space - Grant of Lease - Hatherley Park Vendor PitchRESOLVED THAT: 1. authority is delegated to the Head of Finance and Assets, in consultation with the Monitoring Offic... Decided Open
15 Sep 2026 Leisure and Culture Services ContractRESOLVED THAT: 1. an extension to the management agreement between the council and The Cheltenham Trust until 30 Sept... Agreed Open
15 Sep 2026 Aids and Adaptations PolicyRESOLVED THAT: 1. that the is approved. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies