RESOLVED That the minutes be approved as a correct record subject to the last paragraph under the heading Minute No.8 ‘Task Groups’-‘Branding’ being amended to state that it was a number of new bus stops which had been erected and not bus shelters. In addition under Minute No.6 ‘Shared Back Office-Update Report’ an additional paragraph was included as follows:- (vi) That ICT Shared Services be a small part of ICT provisions that data centre(s) would continue in the East with a view to establishing a single Cheshire East Centre hosting all Cheshire East systems.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
Report to Advisory Panel - Performance and Capacity
Public Document Pack
CHESHIRE EAST COUNCIL Minutes of a meeting of the Advisory Panel - Performance and Capacity held on Thursday, 11th December, 2008 at Westfields, Middlewich Road, Sandbach, Cheshire, CW11 1HZ
PRESENT
Councillor J Hammond (Chairman) Councillor Mrs D Thompson (Vice-Chairman)
Councillors [name removed], T Beard, D Brown, P Edwards, [name removed], L Gilbert, M Hardy, H Murray, J Narraway and D Stockton 1 APOLOGIES FOR ABSENCE
Councillor P Mason.
2 DECLARATIONS OF INTEREST
A number of Councillors who were existing County Councillors, Borough Councillors and Town and Parish Councillors declared a personal interest in the business of the meeting en bloc.
3 PUBLIC SPEAKING TIME/OPEN SESSION
There were no members of the public present, wishing to address the Panel.
4 MINUTES OF PREVIOUS MEETING
RESOLVED
That the minutes be approved as a correct record.
5 BUDGET UPDATE REPORT
Consideration was given to a report providing the Panel with an update in respect of progress in relation to the Budget. It was noted that the final paragraph commencing with the words “The current financial scenario identifies a possible funding gap …” should not have been included within the report and should be deleted.
It was reported that the high level financial planning process had been reported to the Cheshire East Cabinet on 16 June 2008 and set out a number of stages of the budget setting process for 2009-10; Stage 1 (April to June 2008), 2008-9 baseline; Stage 2 (June to September), high level planning; Stage 3 (October to December), refinement and adjustment of options; Stage 4 (January to February) finalisation of the 2009-10 budget.
In considering the report Members of the Panel raised the following issues: (i) With reference to Stage 3, it was noted that Cheshire East Cabinet had set a target of £35M savings, which would include income generation for the three year planning period. It was queried what areas the Council would be considering. Some examples were given, including the examination of assets and also consideration of external funding, which had to be funding which met the Council’s priorities.
(ii) It was queried how the inflation rate used had been assessed. It was reported that the original scenario had gauged inflation at 2.5%, however, the position had changed over the last few months and it was proposed to revisit the inflationary factors and to revise the figures accordingly. This issue had been discussed at a recent Budget Cabinet Away Day and it would be necessary to strike a balance between the assumptions made and the provision of services.
(iii) It was queried how the proportions were distributed between Cheshire West and Chester and the Cheshire East Authorities in respect of the assets owned by the County Council. It was noted that the split was mainly geographic, but where there was shared property ownership with regard to delivery, consideration would be given on a case by case basis.
(iv) With regard to the County Council’s investment in the Icelandic Bank, it was queried what proportion would be inherited by the Cheshire East Authority. It was noted that the current position looked more positive in respect of this matter, but both new Authorities would have to consider the future risk in terms of the repayment of the investments.
(v) Clarification was sought as to the amount of reserves to come from each Authority. A brief summary was provided and more detailed figures would be circulated to the Panel. It was noted that the position in respect of reserves was being reviewed on a quarterly basis by the Cheshire East Cabinet. The Medium Term Financial Strategy would be reported to the Cabinet at its meeting to take place in the following week and would include details of the reserves position.
(v) With reference to Stage 4, it was queried where the key dependencies in respect of service design principles and shared services originated from. It was noted that these had been put forward by the various Workstreams.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Advisory Panel - Performance and Capacity at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.