Resolved
RESOLVED That the Audit Commission’s audit fees letter for 2009/10 be received and the proposed work programme, indicative fee and associated budgetary implications be noted.
Governance & Constitution Committee noted this item on Thursday 25 June 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the Audit Commission’s audit fees letter for 2009/10 be received and the proposed work programme, indicative fee and associated budgetary implications be noted.
2.1That the Audit Commission’s audit fees letter for 2009/10 be received and the proposed work programme, indicative fee and associated budgetary implications be noted.
3.1The Audit fee letter is required to be presented and received by those in the organisation charged with Governance. The relevant Committees for this purpose is the Governance & Constitution Committee.
4.1Not applicable.
5.0Local Ward Members
5.1Not applicable.
6.0Policy Implications including - Climate change - Health
6.1Not applicable.
7.0Financial Implications for Transition Costs (Authorised by the Borough Treasurer)
7.1No transitional cost issues, as the fees quoted relate to 2009/10 financial year. 8.0 Financial Implications 2009/10 and beyond (Authorised by the Borough Treasurer)
8.1The proposed audit fee for 2009/10 is £401,925 (exclusive of VAT). This is based on the Audit Commission’s national fee rate with an uplift of 15% to reflect the perceived risks likely to impact the 2009/10 accounts. These are detailed on page 2 of Appendix 1. The risk scale ranges from nil to 30% uplift.
8.2The base budget for audit fees, inherited from the predecessor councils, totals £299,557 after taking into account an assumed saving of £143,000 which was included in the People and Places business case.
8.3This level of saving was deemed reasonable given the rationalisation from four sets of accounts (County Council and three district Councils) to one, and the consolidation to a single financial system and control framework. It also reflected the relative financial strength of the predecessor councils and a good track record on financial stewardship and financial reporting.
8.4The fee level proposed is clearly in excess of that anticipated at the time when the 2009/10 budget was set. The Audit Commission has however, indicated that the fee will be reviewed throughout the year as their risk assessment is updated and refined. There is scope therefore, to mitigate the potential budget shortfall and Members will be updated accordingly.
8.5There is a risk that the fee could be higher than the figure quoted if the Audit Commission has to undertake additional work over and above that identified, or the council requests additional advice or assistance. In either case, the Governance & Constitution Committee will be consulted before the fee is revised.
9.0Legal Implications (Authorised by the Borough Solicitor)
9.1No significant legal issues. There is a statutory requirement for audited bodies to meet the fees specified by the Audit Commission.
10.1The quoted audit fee for 2009/10 exceeds the budget provision by £102,368. This overspend would fall to be met from council balances as there is no contingency provision to cover the additional costs.
10.2This represents the maximum risk, or worst case scenario. If the risks identified by the Audit Commission can be addressed satisfactorily during the year, then there is potential to eliminate some, or all of the 15% risk element of the fee. This would reduce the potential overspend by up to £52,425.
10.3A programme of regular liaison meetings between senior finance officers and the Audit Commission has been established to keep the identified risk issues under review. The following specific action is already in hand:-
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Audit Commission Audit Fee 2009/10Minutes | 106 KB | DownloadRead as text |
Follow Governance & Constitution Committee at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Mar 2010 | Minutes of Previous meetingRESOLVED That the minutes of the meeting held on 19 th February 2010 be approved as a correct record. | Approved | Open |
| 25 Mar 2010 | Appointments to Outside OrganisationsRESOLVED That (1) Sandbach Park Steering Group be added to the list of approved outside organisations and Councillor ... | Approved | Open |
| 25 Mar 2010 | Independent Remuneration Panel: Mid Year Review of Members' Allowances SchemeRESOLVED That Council be recommended that (1) (a) save as below, no increase be applied to the 2009/2010 rates fixed ... | Agreed | Open |
| 25 Mar 2010 | Implementation of International Financial Reporting Standards (IFRS)RESOLVED That the updated project plan as attached as Appendix A to the report be approved. | Approved | Open |
| 25 Mar 2010 | Update on Comprehensive Area Assessment (Use of Resources)RESOLVED That (1) the findings and the monitoring mechanisms used to ensure timely action in relation to CAA reports ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.