Provision for 2010/2011 (Year 2) Playbuilder Project

Approved Committee 3 papers

Health and Wellbeing approved this item on Friday 8 January 2010. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

RESOLVED That the Cabinet Member for Heath and Wellbeing approves (1) the evaluation process for the twenty-one applications received in the second phase of the Playbuilder Project; and (2) the fourteen sites evaluated for improvement in the second phase of the Playbuilder programme and the funding allocated to each project.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Health and Wellbeing

Recommendations

That the Cabinet Member for Heath and Wellbeing approves

(1) the evaluation process for the twenty-one applications received in the second phase of the Playbuilder Project; and

(2) the fourteen sites evaluated for improvement in the second phase of the Playbuilder programme and the funding allocated to each project.

Reasons for recommendations

3.1The authority has received a grant from the Department for Children, Schools and Families (DCFS) through the Playbuilder Capital Fund to improve play provision across the Borough of Cheshire East.

3.2Invitations for expressions of interest to apply for funding to refurbish play sites for the second year of the Playbuilder programme were circulated widely via local press and the Cheshire East Website.

3.3The twenty-one applications were received and evaluated against Play England’s Ten Design Principles and Cheshire East Playbuilder criteria (Appendices 1 and 2 respectively) to establish need and suitability; fourteen sites met the criteria.

3.4Within the project delivery over two years, every effort has been made to achieve a demographic spread of sites across Cheshire East. 3.5 The nominated play sites for year two are listed below:

Play Area District Funding Macclesfield Area Arnold Road Play Area Disley 45,000 Weston Playing Field Macclesfield 22.500 Adlington Road Play Bollington 22,500 Barnaby Road Poynton 45,000 Bollington Cross Bollington 22,500 Sutton Playing Field Sutton 19,000 Fulshaw Park Wilmslow 45,000 Congleton Area Bromley Farm Congleton 45,000 Sandbach Park Sandbach 45,000 Rode Heath Play Area Rode Heath 45,000 Wood Park Alsager 45,000 Crewe Area Wybunbury Play Area Wybunbury 45,000 Weston Play Area Weston 19,000 Stapeley Area Stapeley 45,000

Wards affected

4.1Alderley, Alsager, Bollington, Disley, Congleton Town East, Doddington, Macclesfield Forest, Macclesfield West, Poynton, Sandbach, Sandbach East & Rode.

5.0Local Ward Members

5.1Cllr Elsie Alcock, Cllr Carolyn Andrew, Cllr Marc Asquith, Cllr Rhoda Bailey, Cllr Andrew Barratt, Cllr Chris Beard, Cllr Darryl Beckford, Cllr Sandy Bentley, Cllr David Brickhill, Cllr David Brown, Cllr Harold Davenport, Cllr Mathew Davies, Cllr Rob Fletcher, Cllr Stella Furlong, Cllr Hilda Gaddum, Cllr Liz Gilliland, Cllr Martin Hardy, Cllr John Hammond, Cllr Derek Hough, Cllr Shirley Jones, Cllr Frank Keegan, Cllr Peter Mason, Cllr Gillian Merry, Cllr Burry Moran, Cllr Howard Murray, Cllr Lesley Smetham, Cllr Diana Thompson, Cllr Andrew Thwaite, Cllr Rodney Walker CBE, Cllr Roger West,

6.0Policy Implications

6.1None

7.0Financial Implications for Transition Costs (Authorised by the Borough Treasurer)

7.1None 8.0 Financial Implications 2009/10 and Beyond (Authorised by the Borough Treasurer)

8.1Cheshire East Council has been awarded the following amounts from the DCFS Playbuilder Fund.

Capital Revenue Year 1 £473,336 £25,703 Year 2 £533,548 £17,135

8.2There is no additional funding required from Cheshire East Council; the funding was added to the Capital Programme for approval by Cabinet on the 3rd November 2009.

9.0Legal Implications (Authorised by the Borough Solicitor)

9.1Legal Services will be required to advise on the contractual arrangements necessary to secure the delivery of the works contained in the programme.

Risk management

10.1Failure to complete both years one and two would result in the claw back of the funding by the Department of Children, Schools and Families.

11.0Background and Options

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 3.2 MB Download
PDF
Appendix 2Appendix 2 87 KB Download
PDF
Provision for 2010/2011 (Year 2) Playbuilder ProjectMinutes 63 KB DownloadRead as text

At this meeting

Whole meeting
10Provision for 2010/2011 (Year 2) Playbuilder ProjectThis decision

More from Cheshire East Health and Wellbeing

All decisions
MeetingDecisionOutcome
10 Jul 2009 Minutes of Previous meetingRESOLVED That the minutes of the meeting of 1 May 2009 be approved as a correct record. Approved Open
10 Jul 2009 Cheshire and Warrington Local Access ForumRESOLVED That (1) Cheshire East Council enter into a Joint Local Access Forum with Cheshire West and Chester Council ... Decided Open
10 Jul 2009 The future of the Silk Heritage TrustRESOLVED That (1) the proposal to develop a business case to facilitate the aspiration to establish the National Silk... Decided Open
1 May 2009 Provision for Skate/BMX Park/Plaza at South Park, MacclesfieldRESOLVED That the contract for the design, supply and installation of a skate/BMX park in South Park, Macclesfield be... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies