Resolved
RESOLVED That an easement be granted to National Grid over the land at Wilmslow Park, Wilmslow, as referred to in the report, on terms and conditions to be determined by the Asset Manager and the Borough Solicitor.
Health & Wellbeing and Procurement, Assets & Shared Services decided this item on Monday 14 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That an easement be granted to National Grid over the land at Wilmslow Park, Wilmslow, as referred to in the report, on terms and conditions to be determined by the Asset Manager and the Borough Solicitor.
2.1Following consultation with our Health & Wellbeing Department, to approve the grant of the easement over the land on terms and conditions to be determined by the Asset Manager and the Borough Solicitor.
3.1The Council will receive a consideration for granting the right.
3.2The existing gas pipe needs to be replaced.
3.3The easement will not adversely affect the land. National Grid will be responsible for reinstating the condition of the land following completion of any works.
4.1Wilmslow North
5.0Local Ward Members
5.1Councillor Jim Crockatt Councillor Don Stockton Councillor Paul Whiteley
6.0Policy Implications
None 7.0 Financial Implications
7.1National Grid will pay the Council a contribution of £3,024 for the easement as well as £969 towards legal and surveyor’s fees.
8.1Section 123 of the Local Government Act 1972 provides that a local authority may dispose of land it holds on such terms as it chooses but the Secretary of States consent is required if the disposal is for less than the best consideration reasonably obtainable. “Land” is defined as including any “any interest in land and any easement or right in, to or over the land”.
9.0Risk Management Implications
9.1There are no risks associated with the grant of an easement to National Grid.
10.0Background and Options
10.1The land is designated as public open space and is currently managed by the Council’s Health and Wellbeing Department. The land is currently used for recreational purposes and is not subject to any other leases or licences to third parties.
10.2The works are part of National Grid’s larger replacement scheme in the area and the majority of works will be taking place this year. A number of the steel gas pipes have now come to the end of their life span and require replacing.
10.3In some cases the plastic pipe can be slip lined into the old steel pipe but this will not be suitable for this route as it would result in lengthy cut offs and disruptions to the local gas supply.
10.4The laying of this proposed route is scheduled to commence in the spring, with the route taking around a month to lay and back fill. The working area needed will be securely fenced for both security and safety and this will allow the footpath through the park to remain open.
10.5The route National Grid has developed aims to cause minimum disruption to the park and its users.
10.6A schedule of condition will be undertaken prior to the commencement of the works to ensure that the land is not damaged during the works.
10.7National Grid will ensure that the land remains stock proof at all times.
10.8National Grid will pay the Council a contribution of £3,024 for the easement as well as £969 towards legal and surveyor’s fees. 11.0 Access to Information
11.1The background papers relating to this report can be inspected by contacting the report writer:
Name: Charlotte Roper Designation: Surveyor Tel No: 01270 686 148 Email: [email protected]
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Grant of an Easement at Wilmslow Park, WilmslowMinutes | 51 KB | DownloadRead as text |
PDF |
Wilmslow Park Easment Plan154.06.05.05Minutes | 541 KB | Download |
Follow Health & Wellbeing and Procurement, Assets & Shared Services at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Mar 2011 | Rights of Way Improvement PlanRESOLVED That the Cheshire East 2011-2026 Implementation Plan 2011-2015 be approved. | Approved | Open |
| 14 Mar 2011 | The 1st Alsager Scout Group - Surrender and Renewal of Existing Lease AgreementRESOLVED That the Cabinet Member for Procurement, Assets and Shared Services approves the surrender of the existing l... | Approved | Open |
| 14 Mar 2011 | Consent for the Surrender and Re-grant of a Ground Lease to the Trustees of Bollington Leisure CentreRESOLVED That the ground lease to the Trustees of Bollington Leisure Centre be surrendered and re-granted to incorpor... | Decided | Open |
| 14 Mar 2011 | Exclusion of the Press and PublicThat the press and public be excluded from the meeting during consideration of the following items pursuant to Sectio... | Decided | Open |
| 17 Jan 2011 | Cheshire East Rights of Way Improvement Plan 2011-2026RESOLVED That the Draft Cheshire East Rights of Way Improvement Plan 2011-2026 be approved. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.