RESOLVED - That, for the reasons set out in the report, the application be APPROVED, subject to the satisfactory completion of a Section 106 agreement to secure: A scheme for the provision of 1 affordable housing unit - The type, tenure and location on the site of the affordable housing provision - The timing of the construction of the affordable housing and its phasing in relation to the occupancy of the market housing - The arrangements for the transfer of the affordable housing to an affordable housing provider or the management of the affordable housing if no Registered Social Landlord is involved - The arrangements to ensure that such provision is affordable for both first and subsequent occupiers of the affordable housing; and - The occupancy criteria to be used for determining the identity of occupiers of the affordable housing and the means by which such occupancy criteria shall be enforced. and the following conditions: 1. Time 2. Time for Reserved Matters 3. Approval of Reserved Matters 4. Approved Plans 5. No principal windows to side facing elevation adjacent to Manor House 6. Hours of construction 7. Hours of any pile driving activities 8. Retention of Hedgerow boundary to Flowers Lane 9. A scheme to minimise dust emissions arising from construction activities 10. Noise mitigation scheme 11. Maximum of 4No dwellings 12. Provision of pedestrian access point
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
Proposal: Outline application for residential development
Applicant: D and S Wood
Expiry Date: 03-Dec-2012
SUMMARY RECOMMENDATION Approve subject to conditions and S106 Agreement to secure Affordable Housing
MAIN ISSUES Principle - Open Countryside Design – Siting and Layout Amenity Highways Ecology Affordable Housing
Reason for Referral
The application has been referred to Southern Planning Committee as the proposal represents a Departure from the Development Plan.
DESCRIPTION OF SITE AND CONTEXT
The application site is comprised of a triangular shaped plot at the roundabout junction of Flowers Lane / Minshull New Road / Bradfield Road / Smithy Lane. The site is grassed and relatively open with the presence of some timber sheds / outbuildings. The site is situated adjacent to the Crewe Settlement Boundary, but is designated Open Countryside, as defined by the Borough of Crewe and Nantwich Replacement Local Plan 2011.
DETAILS OF PROPOSAL
The application seeks outline planning permission for residential development with all matters reserved. The indicative plans show varying options of between 3 to 4 dwellings.
RELEVANT HISTORY
P02/0273 Erection of Agricultural Buildings (Approved with conditions 30th May 2002) P99/0524 Hay barn and implement shed (Approved with conditions 5th July 1999) P92/0786 Outline application for 2 number dwellings (Refused 23rd October 1992) 7/15596 Outline application for detached bungalow (Refused 7th July 1988) P95/0498 Outline application for a dwelling (Refused 28th July 1995) P93/0869 Outline application for residential development (Refused 9th December 1993)
POLICIES
Borough of Crewe and Nantwich Replacement Local Plan 2011
NE2 (Open Countryside) NE5 (Nature Conservation and Habitats) NE9 (Protected Species) RES5 (Housing in the Open Countryside) BE1 (Amenity) BE2 (Design) BE3 (Access and Parking)
Other Material Considerations
National Planning Policy Framework
CONSULTATIONS (External to Planning)
Highways:
No objection.
Environmental Health:
No objection subject to the following conditions:
1. Land contamination assessment 2. Hours and details of any pile driving: Monday – Friday 09:00 – 17:30 hrs Saturday 09:00 – 13:00 hrs Sunday and Public Holidays Nil 3. Hours of construction: Monday – Friday 08:00 to 18:00 hrs Saturday 09:00 to 14:00 hrs Sundays and Public Holidays Nil 4. A scheme to minimise dust emissions arising from construction activities 5. Noise mitigation scheme
United Utilities:
No objection. Ecology:
No comments received at time of report preparation.
VIEWS OF MINSHULL VERNON & DISTRICT PARISH COUNCIL
No comments received at time of report preparation.
OTHER REPRESENTATIONS
At the time of report preparation an objection has been received from the adjacent property known as Manor House. In summary the objection relates to the following issues:
Overlooking to Manor House Affect on daylight and evening sun Flow of traffic on the access road and if it is wide enough for emergency vehicles Provision of off-road parking Existing access road does not relate to the one shown on the OS and the application plans Access to Flowers Lane - the roundabout is one of the busiest in the area serving Leighton Hospital, Bentley and commuter traffic into Crewe No pavement on Flowers Lane leading to or from the proposed exist which would prove hazardous to pedestrians particularly young mothers or disabled persons What are the intentions for the unmarked building on the boundary of Manor House – is this a further residential dwelling What sewage facilities will be provided for the development? The orchard is a haven for wildlife; bats are often seen flying around. Will the development be detrimental to their habitat?
OFFICER APPRAISAL
Principle of Development
Local Plan Policy
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.