Resolved
RESOLVED That the progress with preparations for producing year end accounts be noted.
Audit and Governance Committee noted this item on Thursday 31 January 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the progress with preparations for producing year end accounts be noted.
2.1Members are asked to note progress on preparations for producing year end accounts.
3.1Members of the Audit and Governance Committee are required to receive regular updates on progress in accordance with the work programme.
4.1Not applicable
5.0Local Ward Members
5.1Not applicable
6.0Policy Implications including – Carbon Reduction, Health
6.1None
7.0Financial Implications (Authorised by the Director of Finance and Business Services)
7.1As covered in the report.
8.0Legal Implications (Authorised by the Borough Solicitor)
8.1None 9.0 Risk Management
9.1Regular liaison meetings are held with the External Audit to review progress and keep any identified risks under review.
10.0Background and Options
10.1The Annual Audit Letter (AAL) for 2011/12 reported that the Council has significantly improved its closure of accounts process. The accounts presented for audit contained no material errors and far fewer other errors than in previous years. Supporting audit trails and working papers were also much better. The AAL also reported that the finance team had implemented the recommendations from the last two audits including important improvements to their quality assurance arrangements. This had all helped to reduce the number of errors identified during the audit and improve the overall quality of the accounts.
10.2The Finance team met with the auditors in October 2012 to discuss specific aspects of the closure of accounts process and also highlight new areas to consider for 2012/13. The clear message from the auditors was that the Finance team now need to ensure that the improvements become embedded in its way of working.
10.3The next stage is to consider how the audit support process can be organised to shorten the time taken to undertake the audit. The 2012/13 audit will be undertaken by our new auditor – Grant Thornton. The key challenge for the Finance team will be to build on last year's progress particularly around maintaining and improving the quality of the draft accounts. We are having regular discussions with the auditors around how best to support the audit process.
10.4The planning process for the 2012/13 Closure of Accounts is underway, the plans and timetables have been updated and are in the process of being communicated with all those concerned. Regular liaison meetings are held with members of the finance team responsible for closure and service accountants. A Final Accounts Workshop is to be provided by CIPFA Finance Advisory Network and Grant Thornton in February and two members of staff are due to attend.
10.5At the Closure Review meeting a number of issues were highlighted to be addressed during 2012/13 as follows:
• Whole of Government Accounts
o Working papers and audit trails to be improved.
a) In 2012/13 there will be a linked consolidated spreadsheet to individual WGA service spreadsheets as a minimum. In addition service finance will be requested to show links from service finance spreadsheets to service to service finance WGA sheets although the size of payroll reports to allow the allocation of salary costs between Salary Costs, NHI and Pension is problematic. Alternative ways of collating this information at trial balance level are currently being explored but may not be available and working accurately by the year-end.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2012/13 Statement of Accounts: Progress ReportMinutes | 92 KB | DownloadRead as text |
Follow Audit and Governance Committee at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2026 | Minutes of Previous MeetingThat the minutes of the previous meeting be approved as a correct record . | Approved | Open |
| 27 Jul 2026 | Audit and Governance Committee Action LogThat the action log and updates received be noted. | Noted | Open |
| 27 Jul 2026 | Draft Annual Governance Statement 2025-26That the Audit and Governance Committee received and reviewed the draft AGS 2025/26, noting that the final proposed A... | Approved | Open |
| 27 Jul 2026 | Internal Audit Opinion 2025-26RESOLVED That the Audit and Governance Committee 1. Noted and considered the contents of the Internal Audit Annual Op... | Noted | Open |
| 27 Jul 2026 | Final Outturn and Draft Statement of Accounts 2025/26That the Audit and Governance Committee 1. Noted the summarised position of the accounts for year ended 31st March 20... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.