Strategic Infrastructure - Poynton Relief Road (Forward Plan Ref. CE 13/14-51)

Agreed Executive 5 papers

Cabinet agreed this item on Tuesday 12 November 2013. Below is the council's own wording, with the papers it was decided on.

Item94

Resolved

RESOLVED That 1. Cabinet endorses the successful £5.62m funding allocation through the Cheshire and Warrington Local Transport Body process and the inclusion of the scheme and A523 corridor strategy in the Growth deal bid to Government; 2. a DfT compliant business case be developed to allow access to this funding; 3. the objectives of the scheme be defined as: § To support the economic, physical and social regeneration of Poynton and the North of the Borough, in particular Macclesfield. § To relieve existing Village centre traffic congestion and HGVs and reduce traffic on less desirable roads on the wider network. § To deliver a range of complementary measures on the A523 corridor to Macclesfield that addresses Road Safety, Congestion and mitigates the wider environmental impact of traffic. § To improve strategic transport linkages across the Borough, including improving a key strategic link between the A6-MARR, Macclesfield and the M6 thereby facilitating wider economic and transport benefits including higher GVA and job creation. § To allow improvements to the highway network for walking, cycling and public transport 1. the corridor of interest for new possible routes for PRR be agreed as shown in Appendix A to the report; 2. approval to proceed to public consultation on possible new routes for PRR be delegated to the Director of Economic Growth and Prosperity in consultation with the Portfolio Holder for Strategic Communities; 3. the extended scheme programme (Appendix C) be delivered with the following key milestones: Task Start Finish 1. Revised Preferred Route announcement Ongoing May 2014 2. Preliminary Design including improvements to the A523 corridor to Macclesfield and scoping a wider multi modal strategy. May 2014 February 2015 3. Scheme Business Case May 2014 May 2015 4. Environmental Surveys May 2014 (Indicative dates) May 2015 (Indicative dates) 5. Environmental Statement February 2015 (Indicative dates) August 2015 (Indicative dates) 6. Planning Application August 2015 (Indicative dates) January 2016 (Indicative dates) 4. the revised budget profile as set out below be noted: § £0.350m 2013/14 § £0.650m 2014/15 § £0.150m 2015/16 Total £1.150m 5. the scope of the brief be extended to consider measures to address safety, environmental and congestion issues on the A523 corridor between the end of the proposed PRR and the end of the Silk Road in Macclesfield, including undertaking a wider multi modal study to manage traffic growth on the A523 corridor; 6. the necessary professional services for these tasks continue to be procured through the current Highway Services Contract ( Ringway Jacobs) subject to the Strategic Infrastructure Manager being assured of value for money; 7. the project governance ... view the full minutes text for item 94.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Poynton Relief Road: Appendix AMinutes 1 MB Copy on its way
PDF
Poynton Relief Road: Appendix BMinutes 57 KB Copy on its way
PDF
Poynton Relief Road: Appendix CMinutes 177 KB Copy on its way
PDF
Poynton Relief Road: Appendix DMinutes 3 MB Copy on its way
PDF
Strategic Infrastructure: Poynton Relief Road (Forward Plan Ref. CE 13/14-51)Minutes 94 KB Copy on its way

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. Strategic Infrastructure - Poynton Relief Road (Forward Plan Ref. CE 13/14-51)This decision
  2. Recommendation from Strategic Planning Board and Cabinet - Adoption of the Community Infrastructure LevyApproved

More from Cheshire East Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of Previous MeetingThat the minutes of the meeting held on 2 July 2026 be agreed as an accurate record and signed by the Chair. Agreed Open
3 Sep 2026 2026/27 Budget - Quarter 1 Forecast OutturnRESOLVED (unanimously): That Cabinet 1. Note the factors leading to a forecast balanced position and the contents of ... Noted Open
3 Sep 2026 Strategic Risk Register Update Q4 2025-26 and Q1 2026-27RESOLVED (unanimously): That Cabinet 1. Note the position of the Strategic Risk Register following the Quarter 4 2025... Noted Open
3 Sep 2026 Finance Leadership Improvement Plan Update and ReviewRESOLVED (unanimously): That Cabinet 1. Note the content and progress made against the Financial Leadership Improveme... Noted Open
3 Sep 2026 Performance Management Framework and Q4 Performance 2025/26RESOLVED (unanimously): That Cabinet 1. Approve the Performance Management Framework (PMF) attached at Appendix A. 2.... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies