Resolved
RESOLVED That the minutes of the meeting held on 28 January 2016 be approved as a correct record and signed by the Chairman.
Environment Overview and Scrutiny Committee approved this item on Thursday 24 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the minutes of the meeting held on 28 January 2016 be approved as a correct record and signed by the Chairman.
CHESHIRE EAST COUNCIL
Minutes of a meeting of the Environment Overview and Scrutiny Committee held on Thursday, 28th January, 2016 at Committee Suite 1,2 & 3, Westfields, Middlewich Road, Sandbach CW11 1HZ
PRESENT
Councillor J Wray (Chairman) Councillor G Barton (Vice-Chairman)
Councillors M Hardy, N Mannion, A Martin, M Parsons and B Roberts
Councillor D Stockton – Portfolio Holder for Assets and Regeneration
P Griffiths - Infrastructure Delivery Manager R Kemp – Commissioning Manager – Environmental Services P Traynor – Commissioning Manager - Highways
42 APOLOGIES FOR ABSENCE
An apology for absence was received from Councillor H Davenport
43 MINUTES OF PREVIOUS MEETING
Consideration was given to the minutes of the meeting held on 26 November 2015.
RESOLVED
That the minutes be approved as a correct record and signed by the Chairman
44 DECLARATIONS OF INTEREST
There were no declarations of interest
45 WHIPPING DECLARATIONS
There were no whipping declarations
46 PUBLIC SPEAKING TIME/OPEN SESSION
[name removed] and [name removed] attended the meeting to highlight the problem of fly tipping in Cheshire East. [name removed] suggested that there should be a dedicated enforcement officer to eliminate unauthorised dumping of waste by investigating incidents and identifying perpetrators through witness or CCTV evidence leading to warning or prosecution. The officer could also liaise with volunteer organisations, Ansa, clean teams, PCSOs and be responsible for educating residents and schools. 47 COUNCIL'S MAJOR HIGHWAY SCHEMES
Consideration was given to a presentation on the following major highway schemes:
Sydney Road Bridge Replacement
The replacement of a narrow, single lane signal controlled bridge to increase the capacity by taking 2 way traffic without signal control, which would support growth along the corridor and enhance access to key destinations. The estimated cost of the scheme was £10.5m and would be completed by July 2020. Councillors highlighted that a briefing in Crewe library had recently taken place, where they were informed that only side of the bridge was to be replaced and the other side may also need to be replaced in 5 years time. Members questioned why the works would not be completed at the same time. It was agreed that a written answer to the question would be provided.
Congleton Link Road
The scheme was required to gain easier access to the town centre, improve air quality, reduce travel times across Cheshire East, retain and attract new business and improve pedestrian and cycle routes. The estimated cost of the scheme was £80m, which would be made up of government funding and section 106 monies from 2200 new builds. The scheme would be completed by February 2020.
Middlewich Eastern Bypass
The sponsorship of the scheme had been taken over by the Council from private developers. As the current planning permission was due to expire in summer, it was proposed to conduct a fully justified route options assessment leading to a firm recommendation on a preferred route to be submitted to Cabinet in June 2016 with a subsequent planning application, if required.
Poynton Relief Road
A proposed 1.9 mile highway which would relieve congestion and improve links to Macclesfield and support economic, physical and social regeneration of the area. the estimated cost of the scheme was £30m, £22m had been secured through the Governments Local Growth Fund and the remaining £8m would be funded by Cheshire East Council. The relief road would be completed by early 2019.
RESOLVED
That the update be received.
48 ENVIRONMENTAL SERVICES HUB
The Committee received a presentation on the development of the Environmental Services Hub . The presentation informed the Committee that:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of Previous meetingMinutes | 72 KB | DownloadRead as text |
Follow Environment Overview and Scrutiny Committee at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Mar 2016 | Flood Risk ManagementRESOLVED (a) That the presentation be received; (b) That the Chairman be requested to write to the Highways and Infra... | Decided | Open |
| 24 Mar 2016 | Parks StrategyRESOLVED – That the draft parks strategy be noted. | Noted | Open |
| 24 Mar 2016 | Forward PlanRESOLVED That the forward plan be received | Decided | Open |
| 24 Mar 2016 | Work ProgrammeRESOLVED – That items relating to TSSL and Bus Service Routes be considered at the informal meeting to be held on 23 ... | Decided | Open |
| 28 Jan 2016 | Minutes of Previous meetingRESOLVED That the minutes be approved as a correct record and signed by the Chairman | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.