Congleton Link Road - Approval to Proceed with the Compulsory Purchase of Land Required to Deliver the Scheme

Approved Executive 3 papers

Cabinet approved this item on Tuesday 14 June 2016. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED That Cabinet 1. Subject to a positive resolution of the Strategic Planning Board to grant planning permission for the scheme, approves the use of the powers of compulsory purchase to undertake the acquisition of land and new rights required for the construction of the Congleton Link Road and authorises: a) The making of an order (or orders) un der under Sections 239, 240, 246, 250 and 260 of the Highways Act 1980 and all other powers as appropriate for the compulsory purchase of land and rights required for the construction of Congleton Link Road as shown on drawing No: B1832001-CPO-LTR-GA-001 (“the CPO”); b) The making of a Side Roads Order (or orders) under Sections 8, 14 and 125 of the Highways Act 1980 and all other necessary powers to improve, stop up existing highways, construct lengths of new highway and stop up and provide replacement private means of access as required to deliver the Congleton Link Road (“the SRO”); c) The Executive Director - Place in consultation with the Director of Legal Services to make any amendments necessary to the contemplated orders arising as a result of further design work or negotiations with landowners or affected parties or for any connected reasons in order to enable delivery of the Congleton Link Road; d) The Executive Director - Place in consultation with the Director of Legal Services to take all appropriate actions to secure the confirmation of the contemplated orders including: i. To take all necessary action to secure the making, submission to the Secretary of State for confirmation and (if confirmed) implementation, of the SRO and the CPO including the publication and service of all relevant notices and for the Director of Legal Services to secure the presentation of the Council’s case at any public inquiry and the subsequent service of Notices to Treat and Notices of Entry or, as the case may be the execution of General Vesting Declarations; ii. To negotiate and enter into agreements and undertakings with the owners of any interest in the CPO and/or the SRO (“the Orders”) and any objectors to the confirmation of the Orders setting out the terms for the withdrawal of objections to the Orders including where appropriate, the inclusion in and/or exclusion from the CPO of land or new rights or the amendments of the SRO and to authorise the Director of Legal Services to agree, draw up, and to sign all necessary legal documents to record such agreements and undertakings; iii. In the event that ... view the full minutes text for item 6.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Congleton Link Road: Approval to Proceed with the Compulsory Purchase of Land Required to Deliver the SchemeMinutes 155 KB Copy on its way
PDF
Congleton Link Road: CPO: Appendix AMinutes 10 MB Copy on its way
PDF
Congleton Link Road: CPO: Appendix BMinutes 923 KB Copy on its way

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. Congleton Link Road - Approval to Proceed with the Compulsory Purchase of Land Required to Deliver the SchemeThis decision
  2. 23/2713C - Land north of the Congleton Link Road (‘CLR’) known as Somerford Green, CongletonApproved
  3. Recommendation from Cabinet- Congleton Link Road - Award Of Construction Contract And Submission of Final Business CaseApproved
  4. Congleton Link Road - Procurement StrategyApproved
  5. Congleton Link Road - Funding Strategy and Approval in Principle to Underwrite the Costs of Delivering the SchemeApproved
  6. Congleton Link Road - Preferred Route Assessment and Next StepsApproved

More from Cheshire East Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of Previous MeetingThat the minutes of the meeting held on 2 July 2026 be agreed as an accurate record and signed by the Chair. Agreed Open
3 Sep 2026 2026/27 Budget - Quarter 1 Forecast OutturnRESOLVED (unanimously): That Cabinet 1. Note the factors leading to a forecast balanced position and the contents of ... Noted Open
3 Sep 2026 Strategic Risk Register Update Q4 2025-26 and Q1 2026-27RESOLVED (unanimously): That Cabinet 1. Note the position of the Strategic Risk Register following the Quarter 4 2025... Noted Open
3 Sep 2026 Finance Leadership Improvement Plan Update and ReviewRESOLVED (unanimously): That Cabinet 1. Note the content and progress made against the Financial Leadership Improveme... Noted Open
3 Sep 2026 Performance Management Framework and Q4 Performance 2025/26RESOLVED (unanimously): That Cabinet 1. Approve the Performance Management Framework (PMF) attached at Appendix A. 2.... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies