16/5848C 35, Woodside Avenue, Alsager, Stoke-On-Trent, Cheshire ST7 2DL: Change of use of an existing double garage into a two bedroom dwelling house, including the provision of a new pitched roof for Mr Steve Mellor
ApprovedPlanning1 paper
Southern Planning Committee approved this item on Wednesday 1 March 2017. Below is the council's own wording, with the papers it was decided on.
RESOLVED (a) That, for the reasons set out in the report, the application be APPROVED subject to the following conditions: 1. Standard time 3 years 2. Approved Plans 3. Pile driving limited to 08:30 to 17:30 Monday to Friday, 09:00 – 13:00 Saturday and not at all on Sundays 4. Submission and approval of details of materials 5. Landscaping details including boundary treatment to be submitted and approved 6. Implementation of landscaping 7. Submission of a noise assessment 8. Provision of an electric vehicle charging point 9. If, during the course of development, contamination not previously identified is found to be present, no further works shall be undertaken in the affected area and the contamination shall be reported to the Local Planning Authority as soon as reasonably practicable (but within a maximum of 5 days from the find). Prior to further works being carried out in the identified area, a further assessment shall be made and appropriate remediation implemented in accordance with a scheme also agreed in writing by the Local Planning Authority. 10. Prior to commencement the developer shall undertake consultation with the HSE and National Grid to confirm that there are no objections to the siting of a dwelling adjacent to the sub-station That, in the event of any changes being needed to the wording of the Committee’s decision (such as to delete, vary or add conditions/informatives/planning obligations or reasons for approval/refusal) prior to the decision being issued, the Head of Planning (Regulation) be granted delegated authority to do so in consultation with the Chairman of the Southern Planning Committee, provided that the changes do not exceed the substantive nature of the Committee’s decision.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
The site is within the Settlement Zone Line of Alsager where there is a presumption in favour of development.
From an economic sustainability perspective, the scheme will assist in the local building business and bring economic benefits to Alsager town centre.
From an environmental and social perspective the proposal is considered to be acceptable in the impact upon local amenities, parking, highway safety, bin storage provision, and traffic generation terms. It would be of an acceptable design that would have a minimal impact upon the amenities of neighbouring properties or future residents.
The proposals are considered to be a sustainable form of development which would comply with the relevant local plan policies and would not compromise key sustainability principles as set out in national planning policy.
Therefore there is a presumption in favour of the development and accordingly it is recommended for approval.
RECOMMENDATION: Approve subject to Conditions
DEFERRAL
The application was deferred by Members in order to allow consultation with the Health and Safety Executive and National Grid regarding the proximity of the proposal to an existing sub station and possible impacts to amenity. Responses from these consultees have not been received at the time of report writing and an update will be provided to members prior to the meeting.
CALL IN
The application has been called in to Committee by Cllr Martin Deakin on the following grounds:
1) It is contrary to section 6 paragraph 48 of the NPPF, "Local planning authorities may make an allowance for windfall sites in the five-year supply if they have compelling evidence that such sites have consistently become available in the local area and will continue to provide a reliable source of supply. Any allowance of development should be realistic having regard to the Strategic Housing Land Availability Assessment , historic windfall delivery rates and expected future trends, and should NOT include residential gardens". This application constitutes an example of such "garden grabbing" and was the principle factor in the Town Council's objection.
2) The proposed highway entrance is considered unacceptable and will result in highway safety concerns. The proposed development would include a shared access and it is also believed that the application will have an adverse environmental impact on the area's wildlife. This will result from the loss of the existing garden land which will harm the local wildlife habitat.
DESCRIPTION OF SITE AND CONTEXT
The site is located in Alsager in a wider area of established housing. The site is located within the rear garden of an existing two storey end terraced house (35) which has been converted to two, one bedroom self contained flats. To the east of the application site lies East Court Garage access road (un-adopted).
The site is within the Alsager Settlement Zone Line as designated in the adopted Congleton Borough Local Plan First Review (2005).
DETAILS OF PROPOSAL
This is a full planning application for the creation of a two bedroom dwelling in the rear garden of 35 Woodside Avenue, Alsager. The dwelling would be created form a disused garage on the site, which is falling into disrepair. A new pitched roof would be added to the building and it would be converted to a two bedroom dwelling.
RELEVANT HISTORY
16/1307C – Two semi-detached dwellings (Land rear of 31A Woodside Avenue) - Approved 11th May 2016
POLICIES
National Policy The National Planning Policy Framework establishes a presumption in favour of sustainable development. Of particular relevance are paragraphs: 14 - Presumption in favour of sustainable development, 47-50 - Wide choice of quality homes and 56-68 - Requiring good design
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
16/5848C 35, Woodside Avenue, Alsager, Stoke-On-Trent, Cheshire ST7 2DL: Change of use of an existing double garage into a two bedroom dwelling house, including the provision of a new pitched roof for Mr Steve MellorMinutes
12516/5848C 35, Woodside Avenue, Alsager, Stoke-On-Trent, Cheshire ST7 2DL: Change of use of an existing double garage into a two bedroom dwelling house, including the provision of a new pitched roof for Mr Steve MellorThis decision
16/5848C 35, Woodside Avenue, Alsager, Stoke-On-Trent, Cheshire ST7 2DL: Change of use of an existing double garage into a two bedroom dwelling house, including the provision of a new pitched roof for Mr Steve MellorThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.