Resolved
RESOLVED 1. That the Flood Risk Management Strategy 2017 be endorsed and be recommended to be rolled out for consultation. 2. That the work of the Flood Risk Management Team be commended.
Environment and Regeneration Overview and Scrutiny Committee decided this item on Tuesday 21 March 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED 1. That the Flood Risk Management Strategy 2017 be endorsed and be recommended to be rolled out for consultation. 2. That the work of the Flood Risk Management Team be commended.
Local Flood Risk Management Strategy 2017 – Draft for Public Consultation
1 www.cheshireeast.gov.uk Local Flood Risk Management Strategy Cheshire East Council __________________________________________________________________________________________________
Notice This document has been produced solely for the purpose of how we will manage flood risk across the borough of Cheshire East. It is has an ongoing review process and will be fully revised at six year intervals in-line with the Cheshire East Preliminary Flood Risk Assessment.
Amendments Reviewer Date Description MT Matt Tandy 18/09/13 Removal of section texts MT/PR Matt Tandy Restructure and update of Strategy by Jacobs Paul Reeves PR Scrutiny Committee 24/04/14 Presentation and approval by the Community Safety Scrutiny Committee Cheshire & Mid Mersey 24/04/14 Circulation to Strategic Partners FRMA’s Paul Reeves 16/05/14 Incorporation of comments and completion of missing data by Jacobs 30/05/14 Final draft for submission PR Scrutiny Committee 05/03/15 Presentation to Environment Overview and Scrutiny Committee – no comments received AB/FK Adrian Bratby 10/03/16 Final review before submission and addition of maps Freideriki Karvouni PR Scrutiny Committee 24/03/16 Presentation to Environment Overview and Scrutiny Committee – no comments received AB/VV Adrian Bratby 10/10/16 Amendments following client review 07/10/2016 Vicky Venn AB Adrian Bratby 24/11/16 Revisions to Appendices 7 and 8 VV Vicky Venn 19/01/17 Final comments prior to submission to cabinet 19/01/2017 SP Stuart Penny 31/01/17 Updated with regards to emerging Local Plan AF Adrian Fisher 09/03/17 Update on emerging Local Plan checked
2 Local Flood Risk Management Strategy Cheshire East Council __________________________________________________________________________________________________
Foreword
This is the first Strategy for Flood Risk Management in Cheshire East. The strategy will help to ensure that the Council, the Environment Agency, United Utilities, neighbouring and other authorities work together to protect homes, businesses and other infrastructure from flooding, whilst ensuring all other relevant considerations are taken into account. It considers how various measures or activities can help to manage flood risk, from better planning of new development to ensuring emergency responders understand which locations are at greatest risk.
The driving force behind this strategy is the duty outlined in the Flood and Water Management Act 2010 to produce a Local Strategy to tackle local and cross boundary issues affecting the Borough. This Act was introduced in reference to climate change developments and the major flood events that affected the UK in 2000 and 2007.
This Local Flood Risk Management Strategy focuses on “local flood risk”. That is flooding which is caused by surface runoff, groundwater and ordinary watercourses (streams and ditches etc.). However it is not the source of flooding that’s most important, it is the effect it has in the Borough. We are keen to make sure that flooding from all sources can be managed together and addressed according to the level of risk.
Managing flood risk locally requires co-operation from all public agencies, businesses and households. Hence it is vital that, in addition to organisations working more collaboratively with each other, we engage with the local communities who are affected by flooding. The strategy set outs the roles and responsibilities of all major stakeholders, including households and community groups, so that there is clarity and understanding about when the different stakeholders need to be involved. We have a strong tradition of partnership working in Cheshire East and we intend to extend this into managing flood risk.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Draft Local Flood Risk Management Strategy 2017Minutes | 18 MB | DownloadRead as text |
Follow Environment and Regeneration Overview and Scrutiny Committee at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Mar 2021 | Minutes of the Previous MeetingRESOLVED- That the minutes of the meeting 12 February 2021 be accepted as a correct and accurate record. | Decided | Open |
| 15 Mar 2021 | Forward PlanRESOLVED- That the be received and noted. | Noted | Open |
| 15 Mar 2021 | Work programmeRESOLVED- That the Work Programme be received and noted. | Noted | Open |
| 12 Feb 2021 | Minutes of the Previous MeetingThat the minutes be approved as a correct and accurate record subject to the amendment with Councillor Farrall’s apol... | Approved | Open |
| 12 Feb 2021 | Forward PlanRESOLVED- That the be received and noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.