1 That the report be noted; 2 The Head of Strategic HR to look into the reporting to the Staffing Committee of teacher redundancies and costs, the reporting of settlement agreements and costs and the inclusion of benchmarking data in the employee turnover data; and 3 a report be brought to the next meeting in relation to the review of the Council’s redundancy terms, and on the Staff Survey action plans.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
HR Business Development – Transformation, Partnerships, Commissioning and Income Generation
Priority Owner Timescale Performance & Outcome End of Year Review Measures COMPLETE. A To ensure that CEC and Education HR & Head of April – Oct 2016 - Development of People Plan Work to deliver the People Plan H&S service delivery is fit for purpose Strategic and suite of KPIs. 2016/17 has evolved and supporting customer requirements through HR progressed during the year and is the development of People Plan, review of summarised in this update. The HR structure, to support business People Plan for 17/18 is under priorities. development. KPIs developed and monitored.
HRMT Jan 2017 - Review and implementation The HR structure has been of revised HR Structure. reframed to enable further alignment with Council requirements and affordability within the Councils budget parameters.
Jan 2017 - Policy, Procedures and The review of HR policies and processes are reviewed to procedures has progressed and meet customer need and will continue into 17/18. legislation and streamlined as appropriate.
- Positive Employee Relations Joint Consultation Negotiation and effective consultation. Panels (JCNPs) are now in place for People, Place and Corporate Services Directorates. The Corporate JCNP takes place monthly and is chaired by the Chief Executive and attended by Executive Directors.
2 People Plan EoY Review - Red = Significantly off track, Amber = Some delay, Green= On track / completed Appendix 1
To create and deliver HR Team HRMT Ongoing - Development and Assessment against the Development Plan. implementation of HRTD Workplace Wellbeing Charter Plan. continues.
To achieve external accreditation of HRMT Ongoing - Receive external Achieved CH&S external HR/H&S services and work towards accreditation and awards. accreditation – 4th RoSPA award external awards. (Commended).
3 People Plan EoY Review - Red = Significantly off track, Amber = Some delay, Green= On track / completed Appendix 1
HR Business Development – Transformation, Partnerships, Commissioning and Income Generation
Priority Owner Timescale Performance & Outcome End of Year Review Measures COMPLETE. B To continue to develop partnership and HRMT Ongoing - Further partnership and joint Collaborative working with CCG joint working arrangements that improve working arrangements and Health partners is ongoing to service delivery and realise financial identified. explore opportunities for joint savings. working and rationalisation of working arrangements.
- Conduct baseline Base line assessment of current assessment and audit of all service specification for current arrangements. Transactional Services complete.
- Determine measure to Potential saving through the increase service delivery. introduction of e-pay slips will lead to a print saving of £19k per - Identified and realised annum. Implementation has savings. commenced and will be phased during 17/18. COMPLETE. C To work closely with CWAC to identify an Corporate H&S April – Jun 2016 - Development of Service New OHU service provider outsource provider for OHU services. Manager Specification. operational.
- Completion of tender process to identify new service provider.
4 People Plan EoY Review - Red = Significantly off track, Amber = Some delay, Green= On track / completed Appendix 1
HR Business Development – Transformation, Partnerships, Commissioning and Income Generation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Exclusion of the Press and PublicThat the press and public be excluded from the meeting during consideration of the following item pursuant to Section...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.