Cabinet, Tuesday 5 December 2017 at 2.00pm

North West Crewe Package Scheme Delivery and Funding

Decided Executive 3 papers

Cabinet decided this item on Tuesday 5 December 2017. Below is the council's own wording, with the papers it was decided on.

Item87

Resolved

RESOLVED That Cabinet 1. notes that the latest total scheme cost estimate for all phases of the North West Crewe infrastructure package is £41.6 million; 2. recommends to Council that the scheme budget profile be adjusted in line with the attached appendices in the Council’s capital programme; 3. notes that the bid for £5m to the National Productivity Fund (Local Roads element) has been successful and that this money needs to be spent by March 2020; 4. notes that a bid has also been made for £10m to the Housing Infrastructure Fund to support this scheme and that the outcome of this bid is expected by the end of this year, but is not guaranteed; 5. authorises the Executive Director Place in consultation with the Director of Legal Services and the Portfolio Holder for Environment, to complete the assembly of the necessary land and third party funding contributions required for delivery of the scheme; 6. authorises the Executive Director Place, in consultation with the Portfolio Holder for Environment, to proceed with all necessary technical work for the submission of a planning application and to finalise detailed design for all phases of the works, including site investigation and any required early diversions of statutory undertaker’s apparatus, to a maximum scheme budget of £2.53m (Prior years expenditure is approximately £330k); and 7. notes that further Cabinet reports will be coming forward with recommendations on the procurement process and the statutory process to deliver this package of works.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
North West Crewe Funding Strategy: app 1Minutes 956 KB Copy on its way
PDF
North West Crewe Funding Strategy: app 2Minutes 177 KB Copy on its way
PDF
North West Crewe Package Scheme Delivery and FundingMinutes 93 KB Copy on its way

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. North West Crewe Package Scheme Delivery and FundingThis decision
  2. 26/0279/RES - LAND NORTH WESTERN CORNER OF DAVID WHITBY WAY, BASFORD: Reserve matters application.Approved
  3. Drainage - Leighton North West CreweAgreed
  4. Midlands-North West Rail Link Project (15 minutes)Noted
  5. 20/4737M - Demolition of existing buildings and erection of 10 dwellings with associated garages, parking, gardens, access and landscaping, Little Stanneylands, Stanneylands Road, Wilmslow, Cheshire, SK9 4ER for Mrs Kerren Phillips, Jones Homes (North West) Limited & Mr Francis LeeRefused
  6. 19/5765C-Approval of Reserved Matters for access, appearance, landscaping, layout and scale following outline approval 19/0739C - Outline application for an agricultural workers dwelling (permanent), Land to the West of, Pexall Road, North Rode for Mr & Mrs PlattApproved

More from Cheshire East Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of Previous MeetingThat the minutes of the meeting held on 2 July 2026 be agreed as an accurate record and signed by the Chair. Agreed Open
3 Sep 2026 2026/27 Budget - Quarter 1 Forecast OutturnRESOLVED (unanimously): That Cabinet 1. Note the factors leading to a forecast balanced position and the contents of ... Noted Open
3 Sep 2026 Strategic Risk Register Update Q4 2025-26 and Q1 2026-27RESOLVED (unanimously): That Cabinet 1. Note the position of the Strategic Risk Register following the Quarter 4 2025... Noted Open
3 Sep 2026 Finance Leadership Improvement Plan Update and ReviewRESOLVED (unanimously): That Cabinet 1. Note the content and progress made against the Financial Leadership Improveme... Noted Open
3 Sep 2026 Performance Management Framework and Q4 Performance 2025/26RESOLVED (unanimously): That Cabinet 1. Approve the Performance Management Framework (PMF) attached at Appendix A. 2.... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies