That 1 the report be noted, and 2 the Constitution Committee be recommended to amend the scheme of delegation to allow the Public Rights of Way Manager to determine, in consultation with the Chairman and Vice Chairman of the Public Rights of Way Committee, any Public Path Order applications that are not contested or contentious at the pre-Order consultation stage.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
5.1The introduction of a system to allow applicants’ agents to undertake a considerable amount of the processing work associated with diversion orders is to be introduced.
5.2Uncontested and non-controversial cases are to be determined by the Public Rights of Way Manager in consultation with the Committee Chair and
OFFICIAL 1 Vice Chair rather than necessarily waiting for the next quarterly formal committee meeting.
5.3A system using external consultants to investigate Definitive Map Modification Order (“DMMO”) applications is to be introduced to reduce backlogs and deal with cases set against tight timetables.
5.4The introduction of an option to work with applicant’s agents is intended to assist the PROW team to manage large backlogs of applications by acting as a “safety valve” and allowing a greater number of applications to be dealt with when backlogs increase or when it is deemed expedient to deal with an urgent Town and Country Planning Act 1990 diversion application. Several pilot cases have been tested and it is intended to continue this trial.
5.5Determining non contentious cases without waiting to bring them to quarterly committee meetings will even out workflow demands and ensure a more regular inflow of fees throughout the year.
5.6The PROW team are currently experiencing resource pressures in the DMMO area of work due to a member of staff being on maternity leave. This causes problems processing DMMOs especially when directions from the Secretary of State are received. Currently we have two such cases requiring to be determined within timescales imposed by the Secretary of State.
5.7The proposed changes will better equip the Council to deal with growing pressures in these areas of work by providing increased flexibility. It will also provide a greater ability to deal with the imposition of strict time limits for determining applications in both the areas of diversion order and definitive map modification order applications when the Deregulation Act 2015 is finally implemented.
5.8It is possible for applicants for Public Path Orders (“PPO”) under the Highways Act 1980 and Town and Country Planning Act 1990 to instruct agents to act on their behalf. The process proposed is designed to keep the input of the Council to a minimum and allow applicants a choice in the way that their applications are processed either directly by a Council case officer or through their own agent working with a Council case officer. However the Council must be involved at certain stages of the process as required by the legislation and also to ensure that the interests of the public are maintained. The Council will also reserve the right to determine the extent of the involvement of an agent.
OFFICIAL 5.9 The previous pilot scheme will continue and the PROW team will exercise discretion in all cases as to whether or not to accept an applicant’s request to use an independent agent.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.