Updates on A500 Dual Carriageway and Middlewich Eastern Bypass
AgreedScrutiny2 papers
Environment and Regeneration Overview and Scrutiny Committee agreed this item on Monday 17 June 2019. Below is the council's own wording, with the papers it was decided on.
It was agreed that officers would provide a briefing to Middlewich Town Council on progress of the Middlewich Eastern Bypass. RESOLVED That officers would provide a briefing to Middlewich Town Council on progress of the Middlewich Eastern Bypass.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
Senior Officer: Frank Jordan, Acting Deputy Chief Executive and Executive Director of Place
1. Scheme Background
1.1It has been a long held ambition of the Council and Middlewich residents to secure the delivery of a bypass to relieve traffic congestion in Middlewich town centre. The proposed scheme will be a new single carriageway road, east of the town centre, linking A54 Holmes Chapel Road (Salt Cellar roundabout) to A533 Booth Lane (at Tetton Bridge). The scheme supports economic growth by facilitating up to 1,950 new houses and 6,500 additional jobs in accordance with Local Plan policies. The scheme is consistent with the Cheshire & Warrington Strategic Economic Plan and is a key element of the HS2 Growth Strategy for the Constellation Partnership. There is considerable public support for the proposals, as demonstrated by both the Middlewich Transport Consultation (2016) and the Preferred Route Consultation (2018).
2. Scheme Status
2.1In November 2017, the Council’s Outline Business Case for a new road was accepted to the DfT’s Large Local Major Scheme Programme.
2.2Both Cheshire East Council and Cheshire West & Chester Council, as the relevant planning authorities, have resolved to approve the application subject to conditions.
OFFICIAL 1 2.3. To date, all works on site have been surveys to inform planning, design and licensing.
2.4A programme of preliminary environment works, such as habitat creation, is being developed in order to discharge a number of planning conditions.
2.5The current programme is for the main construction works to start in 2021, with an estimated 30-month construction period.
3. Approvals to Date
3.1September 2017 - Cabinet resolved to prepare a planning application for the Preferred Route.
3.2January 2019 - Cabinet resolved to enter into a 2-stage Delivery Agreement with Balfour Beatty Limited to procure the Scheme. This Agreement allows the Council to commission Stage 1 (Pre-construction) without incurring a commitment to Stage 2 (Construction).
4. Next Steps
4.1A report to Cabinet in July 2019 is seeking approval to prepare for the Compulsory Purchase of land required to deliver the Scheme, should negotiations to purchase this land be unsuccessful.
OFFICIAL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Regeneration Overview and Scrutiny Committee at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the Previous MeetingThat the minutes be approved as a correct and accurate record subject to the amendment with Councillor Farrall’s apol...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.