Item5
Resolved
RESOLVED – That the committee: 1. Approves the proposed expansion of Springfield School (by way of a satellite site) from 170 pupil places to 250 places (an increase of up to 80 places) from September 2022. 2. Approves the procurement of a contract of works and authorise the Director of Children’s Services to award a construction contract to facilitate the provision of additional places at Springfield School (satellite site) together with any other agreements associated with or ancillary to the contract. 3. Recommends that full Council approves a fully funded Supplementary Capital Estimate of £3m to be included as a named scheme within the Children and Families Capital Programme, which is being funded by capital grants.
Word for word from the decision Cheshire East published for this meeting.
Source: moderngov.cheshireeast.gov.uk