Environment and Communities Committee approved this item on Thursday 20 January 2022. Below is the council's own wording, with the papers it was decided on.
(Unanimously) That: 1) the 2021 update and publication of the Cheshire East Brownfield Land Register, comprising the sites listed in Appendix 1 be approved; and 2) future updates and publications of Part 1 of the Cheshire East Brownfield Land Register be delgated to the Head of Planning.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
Report of: Jayne Traverse, Executive Director of Place
Report Reference No: EC/29/21-22
Ward(s) Affected: All wards
1. Executive Summary 1.1. It is a legal requirement for local planning authorities to prepare, publish and update a brownfield land register (BLR) at least once a year. The purpose of the BLR is to provide up-to-date, publicly available information on brownfield land suitable for housing. 1.2. The council published its first Brownfield Land Register in December 2017 and it has been updated annually since. This report seeks agreement to the Council’s 2021 update of the Brownfield Land Register. 1.3. The report also invites the Committee to delegate the preparation and publication of subsequent annual updates to Part 1 of the Register to the Head of Planning. Any proposal to include sites within Part 2 of the Register would still be brought to the Committee for a decision given that this would involve a grant of Permission in Principle (PiP).
2. Recommendations 2.1. That the Committee: 2.1.1. Approve the 2021 update and publication of the Cheshire East Brownfield Land Register, comprising the sites listed in Appendix 1. 2.1.2. Delegate future updates and publications of Part 1 of the Cheshire East Brownfield Land Register to the Head of Planning.
3. Reasons for Recommendations 3.1. The preparation and publication of a brownfield land register is a statutory requirement. The Environment and Communities Committee is responsible
OFFICIAL for the development and delivery of the Local Development Framework, including the Brownfield Land Register. 3.2. Delegation to the Head of Planning relates only to Part 1 of the Register, which will predominantly comprise sites already with permission or identified for development within the Local Plan. The inclusion of a site in Part 1 of the Register does not trigger PiP.
4. Other Options Considered 4.1. The preparation and publication of a BLR is a statutory requirement. Regulations also set out how registers must be prepared 5. Background 5.1. In April 2017 two pieces of legislation came into force: The Town and Country Planning (Brownfield Land Register) Regulations 2017 (referred to as “the Regulations” in this report); and
The Town and Country Planning (Permission in Principle) Order 2017 (referred to as “the Order” in this report) 5.2. The Regulations require local planning authorities to prepare and maintain a register of previously developed (AKA ‘brownfield’) land in their area. The Register can have two parts. 5.3. It is a mandatory requirement to publish a Part 1 BLR. Part 1 includes all previously developed land in the local planning authority’s area meeting the following four criteria: the land has an area of at least 0.25 hectares or is capable of supporting at least 5 dwellings; the land is suitable for residential development; the land is available for residential development; and residential development of the land is achievable.
5.4The terms “suitable”, “available” and “achievable” are defined in the Regulations. Such sites will include those with planning permission and allocated in a local or neighbourhood plan. 5.5. When deciding which sites to enter on their register, a local planning authority must have regard to the development plan, national policies and advice and any guidance issued by the Secretary of State. However, the inclusion of a site on Part 1 of the BLR does not mean it will automatically be granted planning permission. 5.6. The inclusion of a site in Part 2 triggers a grant of ‘permission in principle’ (PiP) for that land. For the local planning authority to enter sites into Part 2, certain consultation, publicity requirements and other procedures set out in regulations must be met first. PiP is similar to an outline planning permission.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment and Communities Committee at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
Third Financial Review of 2025/26RESOLVED (unanimously): That the Environment and Communities Committee Note the overall Council’s Financial position ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.