Resolved
That the supplementary capital estimates for the Pothole grant fund of £5.799m be approved.
Council approved this item on Wednesday 27 April 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
That the supplementary capital estimates for the Pothole grant fund of £5.799m be approved.
Highways and Transport Committee
Date of Meeting: 13th April 2022
Report Title: Highways and Transport 2022-23 Programmes
Report of: John David – Interim Director of Infrastructure and Highways
Report Reference No: HT/22/21- 22
Ward(s) Affected: All Cheshire East Wards
Corporate Plan Open An open and enabling organisation Priorities Fair A council which empowers and cares about people Green A thriving and sustainable place X
1. Purpose of Report 1.1. This report informs committee members of the capital and revenue budgets available for the highway service for 2022/23 and the allocation of those budgets to the various programmes of work. The programmes of work contribute to the Council’s aim to be a thriving and sustainable place and in particular to the priority of having a transport network that is safe and promotes active travel. 2. Executive Summary 2.1. This report explains the allocation of highway revenue and capital funding to deliver day to day maintenance activities and improvement programmes on the public highway, to ensure that the Council can fulfil its statutory responsibilities as a Highway and Transport authority, as well as contributing to the Council’s Corporate Plan and Local Transport Plan objectives and priorities. 2.2. The report outlines the challenging funding position in terms of both capital expenditure (being dependent on Department of Transport (DfT)
OFFICIAL grants) and revenue expenditure (due to the Council’s position in respect of its Medium Term Financial Strategy (MTFS). 2.3. This report follows on from a previous report presented to the Highways and Transport committee on 16 November 2021. This demonstrated to members how budget allocations and programmes had been set for 2021-22 and invited the committee to comment. The feedback has been considered by the highways team as part of the business planning process and preparation of the detailed budget allocations and programme for 2022-23 presented in this report. 2.4. Due to the responsive nature of the service to many variable external factors, the budgets presented do not operate as fixed budgets, but are the basis on which the contractor’s business plan has been set for the start of the financial year in April 2022. Future committee reports through the year will provide progress updates on the delivery of the programmes, including any emerging pressures due to network demands which might call for amendments of some programmes. 2.5. Any comments members may have on these budget allocations are welcomed and will be taken into account, both during the year and in preparation for future years’ budgets, whilst working within the overall available revenue budget envelope and whilst ensuring all statutory responsibilities as Highway and Transport Authority are being fulfilled.
3. Recommendations 3.1. The Committee is recommended to note the apportionment of revenue and capital funding to the key elements of highway services shown in Tables 2 to 4 below and comment on the apportionment to the service programmes. 3.2. Recommend to Council to approve a supplementary capital estimate for the Pothole Fund grant of £5.799m, set out in paragraph 6.6.2. 4. Reasons for Recommendations 4.1. The budgets for the capital and revenue programmes represent the optimal apportionment between programmes to best achieve the Council’s priorities, whilst fulfilling the Council’s responsibilities as the Highway and Transport Authority as far as reasonably practicable within available budgets. 4.2. The allocation of the Pothole Fund grant was received from the DfT after the Medium Term Financial Strategy was approved by Full Council on 24th February 2022, therefore a supplementary capital estimate of £5.799m requires further approval by Full Council.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway and Transport Programme 2022-23Minutes | 827 KB | DownloadRead as text |
PDF |
Recommendation from Highways and Transport Committee: Pothole Fund GrantMinutes | 269 KB | Download |
Follow Council at Cheshire East and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | Minutes of Previous MeetingThat the minutes of the meetings held on 13 May 2026 be approved as a correct record, subject to following amendment:... | Approved | Open |
| 15 Jul 2026 | Recommendation from Cabinet: Final Outturn 2025/26 Approval of Supplementary Revenue and Capital EstimatesRESOLVED (by majority): That Council 1 approve the Supplementary Revenue Estimate requests for allocation of addition... | Approved | Open |
| 15 Jul 2026 | Appointment of Director of Law and Governance (Monitoring Officer)RESOLVED (by majority): That Council approve the appointment of [name removed] as the Director of Law and Governance ... | Approved | Open |
| 15 Jul 2026 | Approval of Absence from Council MeetingsRESOLVED (unanimously): That Council approve Councillor David Brown’s absence from Council meetings for a period of o... | Approved | Open |
| 15 Jul 2026 | Notices of MotionThat the Motion be referred to the Licensing Committee. 2 Peak Cluster Proposed by Councillor L Smetham and Seconded ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.