22/2692N - LAND OFF, CREWE ROAD, WINTERLEY: Reserved Matters Planning Application (layout, scale, appearance and landscaping) following outline approval reference 19/3889N - Outline application for the erection of up to 55 dwellings with as
ApprovedPlanning2 papers
Southern Planning Committee approved this item on Wednesday 15 March 2023. Below is the council's own wording, with the papers it was decided on.
That for the reasons set out in the report and update report the application be APPROVED, subject to the following conditions: 1. Development carried out to the approved plans 2. Obscure glazing to be fitted to side facing en-suite window of plot 1 3. Prior to the installation of any external lighting details to be provided 4. No removal of any vegetation or the demolition or conversion of buildings shall take place between 1st March and 31st August in any year, unless a detailed survey has been carried out to check for nesting birds 5. Development to be carried out in accordance with Arboricultural Method Statement (Urban Green Drawing UG_1511_ARB_AMS_02 dated 17/01/23) submitted to the Council on 26/01/2023. 6. Provision of landscaping plan 7. Landscaping implementation 8. Liaison Group Informative The developer to be reminded of the CEMP informative attached to the outline consent. In order to give proper effect to the Committee`s intent and without changing the substance of its decision, authority is delegated to the Head of Planning (Regulation) in consultation with the Chair (or in their absence the Vice Chair) to correct any technical slip or omission in the resolution, before issue of the decision notice.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
The principle of development has already been established under outline approval ref 19/3889N. Therefore, the proposal remains acceptable from a pure land use perspective.
The matters sought for approval by this application, the Reserved Matters, which relate access, appearance, layout, scale and landscaping are all deemed to be acceptable. In addition, the proposals are not deemed to create any concerns in relation to amenity, ecology or flood risk, highway safety, subject to updated conditions where necessary.
The application is therefore recommended for approval
Recommendation
APPROVE subject to the conditions
ACTION SINCE COMMITTEE DEFERRAL
The application was heard at the planning committee meeting of 8th February and was deferred for the following reasons:
To allows further discussion to increase the garden sizes and dwelling sizes for certain plots
Further discussion has taken place with the applicant and as a result the proposal has been reduced by 1 dwelling from 55 to 54 houses and the plot types for the substandard properties have been changed.
This has allowed the room sizes of those plots to be increased and now comply with NDSS. The plots with the substandard garden areas have also been sited closer to the road to allow the garden sizes to be increased in line with the 50sqm target (see space standards and amenity sections below) To consider the provision of a pedestrian link to the site to the North East
The applicant has reviewed the potential for a footpath as requested, however after looking at the deed plans for the homes on their Nursery Fields development, the area is fully in the deeds of the customer who purchased plot 24 and therefore does not lie within the applicants ownership or within any management company ownership. Also, the field to the north of the site is also not owned by the applicant so they will not be able to accommodate a footpath link.
REASON FOR REFERRAL
The application is referred to Southern Planning Committee at the request of Cllr Edgar for the following reasons;
1) The affordable housing is not pepper-potted throughout the development. It is concentrated away from the larger properties 2) Of the 20 affordable homes none have 3 bedrooms, they are all 1 or 2 bedrooms 3) Of the market sale houses none are less than 3 bedrooms. Why is the bedroom number distribution not spread evenly over the whole development? 4) Needs improved climate change mitigation, solar panels. heat pumps, car charging, grey water systems. We should not be waiting for new environment legislation to be in place but preparing for it. 5) Need to clearly lay out the plans for long term maintenance of open spaces. Too many applications are unclear on this and result in the Council having to foot the bill in future 6) Size of garages. Are they really a suitable size to be a garage for a modern car? Or just a token to comply with parking spaces need. Car travel will be a necessity to some people on this development. Its is not close to local employment areas 7) Inadequate over all parking provision 8) Site is overdeveloped 9) Why are there no houses on the northern boundary? Is there an expectation of further development to the north? 10) There should be walking connectivity to the other Duchy Estate.to the east. a) to allow easier access to the facilities in Winterley for the other new estate and b) to allow children access to all the play areas. 11) A condition to set up a liaison group with established residents, Parish Council and the developer.
PROPOSAL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
22/2692N: LAND OFF, CREWE ROAD, WINTERLEY: Reserved Matters Planning Application (layout, scale, appearance and landscaping) following outline approval reference 19/3889N: Outline application for the erection of up to 55 dwellings with associated works (access to be considered with all other matteMinutes
7422/2692N - LAND OFF, CREWE ROAD, WINTERLEY: Reserved Matters Planning Application (layout, scale, appearance and landscaping) following outline approval reference 19/3889N - Outline application for the erection of up to 55 dwellings with asThis decision
22/2692N - LAND OFF, CREWE ROAD, WINTERLEY: Reserved Matters Planning Application (layout, scale, appearance and landscaping) following outline approval reference 19/3889N - Outline application for the erection of up to 55 dwellings with asThis decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.