RESOLVED (by majority): That the Finance Sub Committee Delegate authority to the Director of Growth and Enterprise to dispose of the Site on terms and conditions to be agreed in consultation with the Governance, Compliance and Monitoring Officer and the Executive Director of Resources and S151 Officer. Delegate authority to the Director of Growth and Enterprise, in consultation with the Governance, Compliance and Monitoring Officer and the Executive Director of Resources and S151 Officer; to complete all legal documentation required to complete the disposal of the Site and including (but not limited to) the completion of any licence or similar agreements and planning agreements required prior to disposal or relating to the Councils retained former landfill area.
Word for word from the decision Cheshire East published for this meeting.Source: moderngov.cheshireeast.gov.uk
Disposal of Residential Land at Leighton Green, Crewe
Report of: Peter Skates, Director of Growth and Enterprise
Report Reference No: FSC/03/25-26 Ward(s) Affected: Crewe St Barnabas and Leighton Ward For Decision or Scrutiny: Decision
Purpose of Report 1 The purpose of this report is to duly and properly consider the offers received following the completion of marketing operations in relation to the Leighton Green, Crewe (‘the Site’) residential development opportunity, as shown outlined in red in Appendix I.
2 This report seeks a decision to proceed with the freehold disposal of the Site to Persimmon Homes Limited.
Executive Summary 3 The Site comprises a circa 16.64 hectare (41.14 acre) residential development site with the benefit of outline planning permission for development of up to 400 dwellings. The Site forms part of Local Plan Site 4 - ‘Leighton West’ (LPS4) and part of a Masterplan promoted jointly by Bloor Homes, Vistry Homes and the Council’s Economic Development Team (previously Engine of the North).
4 In April 2024, the Site was advertised by the Council’s retained agents Sanderson Weatherall as available for ‘For Sale’ as a single parcel, inviting offers on conditional and unconditional bases. The Council received the twelve offers detailed in Appendix IV. Eleven offers were submitted on a ‘subject to planning’ basis (securing full planning permission for bidders’ proposed masterplans) and all offers were subject to technical due diligence in the form of confirmatory surveys, cost deductions for off-site services and a pre- application meeting with the Local Planning Authority.
5 Volume housebuilders adopt a commercial approach to assess the value of development land and, therefore, the amount they offer landowners for sites. This assessment involves producing a layout plan/masterplan for the proposed development and then calculating the gross development value of that development, then deducting estimated development costs (eg base build costs for the houses, abnormal costs, professional fees) and developer’s profit. The residual sum represents the ‘Net’ offer they can afford to pay for the site.
6 To reflect to risks associated with the development of large residential development sites, most volume housebuilders only purchase sites following the grant of full planning permission, after having obtained all due diligence surveys and costed all site abnormal costs. The few that contemplate unconditional purchases factor significant risk into their offers but still typically require ground investigation surveys prior to purchase.
7 Although the offers submitted by the twelve bidders were on a ‘Net’ basis, they were all subject to being re-priced based upon the confirmatory surveys results and the pre-application meeting. The re-pricing would reflect any changes in each bidder’s advised abnormal cost deductions (e.g. onsite surface water strategy, compliance with Cheshire East Design Code, foundation solutions) and their layout/masterplan.
8 An analysis of the offers revealed that some bidders had significantly under- estimated abnormal cost deductions (used to assess the land value offered), artificially increasing the level of their ‘Net’ offer whereas other bidders had been more realistic. This is a common situation for this type of disposal where some bidders either fail to undertake sufficient initial due diligence, or deliberately under-estimate the cost deductions at bidding stage to secure preferred bidder status, and then re-negotiate the price following the subsequent due diligence phase. To provide a ‘like for like’ comparison of bids, the Council’s advisors re-modelled each bidder’s price submissions to reflect more realistic abnormal costs deductions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Fourth Financial Review 2025/26That the Sub Committee 1 note the factors leading to a forecast balanced position and note the contents of Annex 1, S...
MTFS Strategies - Investment StrategyThat the Finance Sub-Committee: 1. Note the draft position of the Medium-Term Financial Strategy and the draft status...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies