Crewe Town Board, Thursday 19 June 2025 at 9.30am

Minutes of Previous meeting (3 Minutes)

Approved Committee 2 papers

Crewe Town Board approved this item on Thursday 19 June 2025. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

That the minutes of the previous virtual meetings held on 2 May 2025 and 16 May 2025 be approved as correct records.
Word for word from the decision Cheshire East published for this meeting. Source: moderngov.cheshireeast.gov.uk

Follow this further

Built from Cheshire East's papers

What the report saysPro

Report to Crewe Town Board

CHESHIRE EAST COUNCIL Minutes of a meeting of the Crewe Town Board held on Friday, 16th May, 2025 at Virtual Meeting via Microsoft Teams

PRESENT

Tony Davison, Simon Yates, Andy Butler, Rick Carter, Paul Colman, Sally Hepton, Guy Kilminster, Graham McKnight and Councillor Jill Rhodes

ALSO IN ATTENDANCE

Pete Turner, Lindsay Lewis, Daniel Lindsay, Dan Welch

OFFICERS IN ATTENDANCE

Charles Jarvis, Head of Economic Development Jez Goodman, Development and Regeneration Manager Diane Moulson, Senior Member Development Officer

1 APOLOGIES FOR ABSENCE (1 MINUTE)

Apologies for absence were received from Kate Blakemore, Ian Moston, Doug Kinsman, Councillor Nick Mannion, Connor Naismith MP and Phil Cresswell.

2 DECLARATIONS OF INTEREST (1 MINUTE)

There we no declarations of interest from Board Members other than those already on file.

3 TOWNS FUND SIX-MONTHLY PERFORMANCE REPORT (30 MINUTES)

The Board received a presentation and update on the sixth-monthly Towns Fund performance report for September 2024 – March 2025 from Daniel Lindsay, Ekosgen, and Jez Goodman, Development and Regeneration Manager.

Programme Level Considerations

In February 2025, the Ministry of Housing, Communities and Local Government (MHCLG) approved an extension to project spend into 2026/27 for the following projects:

• Warm and Healthy Homes (up to £750,000) • History Centre Public Realm (up to £400,000) • Repurposing Our High Street (up to £318,300) • Valley Brook Green Corridor (up to £425,500) It was noted that since the last update, MHCLG had also confirmed that other project spend could fall into 2026 / 2027 provided all spend had been contractually committed by March 2026.

These updates had reduced some of the risks concerning project spend within the Towns Fund timescales.

It was noted that although projects were significantly behind their original expenditure profiles (due in part to the timescales necessary to develop business cases and confirm funding, but also the extended timescales required to deliver projects), through the approval of PARs and funding extensions, there was confidence that the remaining projects would be delivered.

It was noted that significant progress had been made across a number of projects:

• Most of the Pocket Park project activity has been delivered. • The new Youth Club at Mirion Street (part of the YouthZone project) was almost complete. • The new Civic & Cultural Space (part-funded using some of the TF grant) completed in April. • The Repurposing Our High Street grant scheme had supported more businesses to open in the town centre, with visual improvement to the streetscape. • Physical development was progressing at YouthZone at Oak Street. • The next period would see further physical works progressing in connection with the Mill Street Corridor, Cumberland Arena, Warm & Healthy Homes projects.

It was noted that there were issues with utility providers, including their capacity and intelligence to provide accurate and timely information relating to physical developments. There had also been an issue with internal capacity and processes which contributed to a project delay (Cumberland Arena), but this was quickly addressed. The underlying risk around capacity remains highlighted as a significant one, as there were ongoing challenges related to organisational delivery capacity, impacted by budgetary pressures and strategic priorities, including Cheshire East Council as:

• Delivery lead for several projects, • Accountable body & programme manager, and • The local planning authority. This has been mitigated to some degree by identifying additional project management capacity.

No new programme-level challenges were expected in the next 6-12 months, providing that there were no significant macro-economic changes, although the programme risks identified concerns with cost, capacity and communications. Whilst Cheshire East Council was the lead delivery partner on most projects, it was not in a position to plug any financial gap which emerged in projects.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Minutes of Previous MeetingMinutes 121 KB DownloadRead as text
PDF
Minutes of Previous meeting (3 Minutes)Minutes 132 KB Download

At this meeting

Whole meeting

On this subject at Cheshire East

Search all
  1. Minutes of Previous meeting (3 Minutes)This decision
  2. Minutes of the Previous MeetingApproved
  3. Minutes of Previous meetingApproved
  4. Minutes of Previous MeetingApproved
  5. Minutes of Previous MeetingApproved
  6. Minutes of Previous MeetingAgreed

More from Cheshire East Crewe Town Board

All decisions
MeetingDecisionOutcome
3 Jul 2026 Minutes of Previous meetings (3 Minutes)That the minutes of the meetings held on 1 May 2026 and 5 June 2026 be agreed as a correct record and signed by the C... Agreed Open
3 Jul 2026 Appointment of Vice-Chair (5 Minutes)RESOLVED (Unanimously): That Simon Yates be confirmed as the Vice Chair of the Crewe Town Board for the next year. Decided Open
3 Jul 2026 Crewe BID Delivery Plan Update (30 Minutes)That the update be noted. Noted Open
3 Jul 2026 Crewe Town Board and the Future of Crewe (5 Minutes)RESOLVED (Unanimously): That the report be formally approved and ratified. That the information contained within the ... Approved Open
3 Jul 2026 Towns Fund Performance Update (30 Minutes)RESOLVED (Unanimously): That the Towns Fund Performance Update be noted. That the proposed reallocation of Towns Fund... Noted Open